BIM Information Management: The Complete Guide

BIM Information Management: The Complete Guide

When I became a CAD manager, nobody told me that my real job was information management. I thought I was there to look after software, templates and plotting standards. It took a few years, and one particularly humbling project, to understand what I was actually responsible for. A client had asked for the “latest set of drawings” for a building we had designed. Three people in my own office sent three different sets, each convinced theirs was the latest, and each correct according to the folder they had looked in. The client did not care about our folders. The client cared that nobody could say, with confidence, which information was true.

That moment changed how I saw my job. Drawings, models, schedules, specifications, emails, markups: all of it was information, produced by many hands, consumed by many others and valuable only if the right version reached the right person at the right time. Software was just the container. What mattered was the discipline around it: who asks for what, who produces it, how it is checked, how it is shared, how it is kept.

That discipline has a name, and an international standard to go with it: information management. It is the quiet foundation of everything else in BIM. A beautiful model that nobody can find, trust or hand over is worth very little. A modest model managed well is worth a great deal. This guide is the complete overview: what information management is, what the ISO 19650 framework asks for, which roles and processes are involved, how to build a working system in an office or a project, and how to measure it. It is also the hub for the other guides in this section, which go deep on the CDE, naming, metadata, information requirements, delivery planning and security.


The Short Answer

BIM information management is the set of roles, processes, standards and tools used to specify, produce, check, share, deliver, use and keep information about a built asset, throughout its life.

Information management is a cycle

In the ISO 19650 framework, it means:

  • Asking for information on purpose, through a chain of information requirements.
  • Planning who delivers what, when and in which form.
  • Producing information in identified containers, with a status and a revision.
  • Checking it before it is shared.
  • Sharing it through a Common Data Environment with controlled states.
  • Delivering it at milestones, formally accepted.
  • Keeping it, so that the information produced in a project becomes the information used in operation.

In one sentence:

Information management is how an organization makes sure that the information it relies on is the right information, in the right place, at the right time, with a name and a status.


Information, Data and Documents: Clearing Up the Words

People use these words interchangeably, and the confusion costs time. In the ISO 19650 vocabulary:

TermMeaningExample
DataFacts in a form that can be processedThe value 2100 in a property called “Height”
InformationData placed in context, so that it has meaning for someone“The door D-101 is 2100 mm high and has a 30-minute fire rating”
Information containerA named, persistent set of information that can be retrievedA model file, a drawing, a schedule, a report
Information modelA set of information containers for a project or an assetThe project information model; the asset information model
DocumentInformation recorded in a document formA specification, a drawing, a certificate
MetadataInformation about an information containerIts identifier, status, revision, author, date

The standard recognizes three kinds of content in an information model: geometrical information, alphanumerical information and documentation. That is why “the BIM model” is never the whole story. See ISO 19650-1: Information Management Concepts and Principles and BIM Metadata, Attributes, and Property Sets Explained.


The ISO 19650 Framework in One Page

ISO 19650 organizes information management around a handful of ideas. Each one has a dedicated guide in this section.

IdeaWhat it meansGuide
Information requirementsA chain from organizational needs down to deliverablesISO 19650 Information Requirements Explained: OIR, AIR, PIR, and EIR
RolesAppointing party, lead appointed party, appointed parties, task teams and the information management functionBIM Roles and Responsibilities: Manager, Coordinator, Modeler, and Information Manager
Information containers and identificationEvery container has a unique ID, status and revisionBIM File Naming Conventions and ISO 19650
Common Data EnvironmentThe agreed source of information, with a solution and a workflowCommon Data Environment (CDE): The Complete Guide
Delivery planningTask plans consolidated into a master planMaster Information Delivery Plan (MIDP): Complete Guide and Task Information Delivery Plan (TIDP): Complete Guide
Level of information needJust enough information, for a purposeISO 7817-1: Level of Information Need Explained
SecurityA proportionate, risk-based approachBIM Information Security, Access Control, and Data Governance

For the full standard overview, read ISO 19650 Explained: A Complete Guide for BIM Professionals.


Why Information Management Matters More Than Modeling

Here is an uncomfortable truth I have repeated in many boardrooms: most BIM value is lost not in modeling, but in the handling of the information after it is produced.

FailureWhat it costs
Nobody knows which version is currentRework, wrong decisions, disputes
Information is produced but not requestedWasted effort and heavy models
Information is requested but not producedGaps found at handover
Information is produced and shared uncheckedErrors spread across teams
Information is shared too widelySecurity and confidentiality risks
Information is delivered but cannot be reusedThe owner starts again at every project
Information is lost at project closeLessons and asset data vanish

Each of these is a management failure, not a software failure. The fix is a system.


The Information Management Function

ISO 19650 does not create a job title. It defines a function: the set of activities required to run the information management process. On a project, that function exists on both sides: for the appointing party and for the delivery team.

What the Function Does

ActivityExamples
DefineHelp specify information requirements, milestones, standards and methods
EstablishSet up the CDE, naming conventions, templates and workflows
PlanPrepare and maintain the BEP, MIDP and responsibility matrix
OperateManage access, statuses, transmittals and records
CheckRun quality checks, review submissions, verify compliance
ReportTrack progress, issues and risks to information delivery
ImproveCapture lessons learned and update standards

Who Performs It

  • On a small project, one person may carry it, often alongside a BIM coordinator role.
  • On a large project, it may be a team.
  • The title may be information manager, BIM manager, document controller or something else. What matters is that the activities are assigned and the person has authority and time.

See BIM Roles and Responsibilities: Manager, Coordinator, Modeler, and Information Manager.


The Information Lifecycle

Every piece of information, whether a model, a drawing or a certificate, passes through a lifecycle. Managing information means managing each stage deliberately.

StageQuestions to answerTypical controls
RequestWhat is needed, why, by whom, by when?Information requirements
PlanWho produces it, in what form, with what resources?BEP, MIDP, TIDP, responsibility matrix
CreateIs it produced to the standard?Templates, naming, classification, modeling standards
CheckDoes it meet the requirement?Quality assurance and review
ShareWho may see it, in what state?CDE states, permissions, status codes
UseIs it the right version for this decision?Metadata, revision control
DeliverHas it been formally accepted?Delivery milestones, acceptance criteria
KeepCan it be found and trusted later?Archive, asset information model, retention rules
DisposeShould it be deleted or restricted?Retention and security rules

A useful exercise: pick one type of information in your organization (say, structural models) and walk it through these nine stages. The gaps appear immediately.


Building an Information Management System: A Practical Roadmap

You do not need a large team or an expensive tool to start. You need a sequence. This is the one I use with offices of all sizes.

Stage 1: Understand What You Manage

  1. Inventory your information: what kinds of containers you produce, who creates them, where they are stored.
  2. Map the flows: who sends what to whom, and in which form.
  3. List the pain points: lost files, version confusion, late deliveries, handover gaps.

Stage 2: Agree the Rules

  1. Define roles and responsibilities, including the information management function.
  2. Adopt a naming convention and status codes. See BIM File Naming Conventions and ISO 19650.
  3. Define the information states and the gates between them.
  4. Define metadata: which fields every container must carry. See BIM Metadata, Attributes, and Property Sets Explained.
  5. Write standard templates: BEP, responsibility matrix, MIDP, TIDP, EIR response.

Stage 3: Choose and Configure the Tools

  1. Select a CDE solution that fits the rules, not the other way round. See How to Set Up a Common Data Environment for BIM Projects and Best CDE Platforms Compared: ACC, Trimble Connect, Dalux, BIMcollab, and More.
  2. Configure areas, permissions, workflows, naming enforcement and metadata.
  3. Prepare templates for models, documents and exchanges.

Stage 4: Run It on a Pilot

  1. Pick one project and apply the system fully.
  2. Mobilize and test with real information.
  3. Train the people who will use it.
  4. Record problems and fix the system.

Stage 5: Scale and Improve

  1. Roll out to other projects, adapting to size.
  2. Measure performance and review quarterly.
  3. Update standards from lessons learned.
  4. Connect to operations: link project deliverables to the asset information model.

The Documents of an Information Management System

Information management runs on a small set of documents. Each answers one question.

DocumentQuestion it answersWritten byGuide
OIRWhat does the organization need to know about its assets?Asset owner or operatorOrganizational Information Requirements (OIR): Complete Guide
AIRWhat is needed to operate and maintain this asset?Asset owner or operatorAsset Information Requirements (AIR): Complete Guide
PIRWhat is needed to make project decisions?Appointing partyProject Information Requirements (PIR): Complete Guide
EIRWhat must each appointed party deliver, when and how?Appointing partyExchange Information Requirements (EIR): Complete Guide
BEPHow will the delivery team meet the requirements?Delivery teamBIM Execution Plan (BEP): How to Create and Implement One
MIDPWhat will be delivered, by whom and when, overall?Lead appointed partyMaster Information Delivery Plan (MIDP): Complete Guide
TIDPWhat will this task team deliver and when?Task teamTask Information Delivery Plan (TIDP): Complete Guide
Responsibility matrixWho is responsible for which information?Delivery teamHow to Create a BIM Responsibility Matrix
Project information standard and production methodsHow is information named, structured and produced?Appointing party, completed by the delivery teamBIM File Naming Conventions and ISO 19650
Security planHow is sensitive information protected?Appointing party and delivery teamBIM Information Security, Access Control, and Data Governance

Do not be intimidated by the list. On a small project, several of these can be a page each, or sections of a single document. The thinking is the same.


Information Management Across the Asset Life Cycle

In Project Delivery (ISO 19650-2)

Information management follows the eight activities from assessment of need to close-out, with the project information model growing through the work. See ISO 19650-2: BIM Information Management During Project Delivery.

In Operation (ISO 19650-3)

The asset information model is maintained through trigger events. See ISO 19650-3: Information Management During Asset Operations.

The Handover Between Them

The quality of operation information is decided at the start of the project, through the AIR and OIR. If the owner never says what it needs, the contractor delivers what is convenient.

Specialist Modules

Exchange, security and health and safety have their own parts of the series. See ISO 19650-4: Information Exchange Requirements Explained, ISO 19650-5: Security-Minded BIM Information Management and ISO 19650-6: Health and Safety Information Management.


Information Management for Small Organizations

Many readers work in small offices and ask: “Is all of this realistic for us?” Yes, in proportion. Here is a lightweight version I have implemented in offices of five to twenty people.

ElementLightweight version
RolesOne named information manager, even part-time
RequirementsA one-page requirements note per project
Naming and metadataOne naming convention, a short list of status and revision codes
CDEA single platform or well-structured server with four areas (WIP, shared, published, archive) and role-based permissions
PlansA short BEP, a one-page responsibility matrix, a simple delivery schedule
ChecksA checklist before sharing; a quick validation of exports
RecordsA change log and a transmittal record
ReviewA one-hour lessons-learned session at the end of each project

The principle: never skip an element, but size it to the project.


Measuring Information Management

You cannot improve what you do not measure. These indicators are simple and meaningful.

IndicatorWhat it shows
Time to find the current version of a given documentFindability
Share of containers with correct ID, status and revisionDiscipline in naming and metadata
First-time pass rate at quality checksQuality of production
Share of deliverables delivered on the MIDP dateReliability
Number of information-related issues per milestoneProcess health
Share of requirements that are verifiableQuality of the requirements
Handover completeness against the AIRFitness for operation
Number of security incidents or access exceptionsControl effectiveness
Rework hours attributed to information problemsCost of poor management

See BIM Quality Management: Processes, Metrics, and Best Practices.


Common Mistakes

  1. Treating information management as an IT project. It is a management discipline supported by tools.
  2. Buying a platform before defining the rules.
  3. No named owner for the information management function.
  4. Requirements nobody can verify.
  5. Producing information nobody asked for.
  6. Sharing before checking.
  7. Ignoring metadata, so containers cannot be found or trusted.
  8. Copying another project’s documents without adapting them.
  9. Forgetting operation: no AIR, no asset information model.
  10. No records, so lessons are lost.
  11. Over-engineering a heavy system for a small project.
  12. Never reviewing the system.

See also Common BIM Mistakes Beginners Should Avoid.


A Starter Checklist

  1. Is there a named person carrying the information management function?
  2. Do we have written requirements for each project?
  3. Do we use a naming convention with status and revision?
  4. Do we have a CDE with controlled states and permissions?
  5. Do we have plans and responsibilities for delivery?
  6. Do we check information before sharing it?
  7. Do we record what was delivered and accepted?
  8. Do we have a security approach proportionate to the risk?
  9. Do we hand over information in the structure the owner needs?
  10. Do we review and improve after each project?

Frequently Asked Questions

What is BIM information management?

The set of roles, processes, standards and tools used to specify, produce, check, share, deliver and keep information about an asset across its life cycle, as described in the ISO 19650 series.

What is the difference between BIM and information management?

BIM is the use of a shared digital representation of an asset. Information management is the discipline that governs how the information in that representation is requested, produced, shared and kept.

Who is responsible for information management?

Each appointment has an information management function on the appointing party’s side and the delivery team’s side. The people carrying it may be called information managers, BIM managers or document controllers.

Do I need a CDE?

For any project with several parties, yes: a controlled, shared environment with defined states. It can be a simple, well-governed platform on a small project. See Common Data Environment (CDE): The Complete Guide.

What is an information container?

A named, persistent set of information that can be retrieved: a model, a drawing, a document, a schedule or a data set, identified with an ID, status and revision.

What is the difference between OIR, AIR, PIR and EIR?

Information requirements at four levels: organization, asset, project and exchange (appointment). See ISO 19650 Information Requirements Explained: OIR, AIR, PIR, and EIR.

Is information management only for large projects?

No. The principles scale. Size the documents and tools to the project, but keep the thinking.

Where should I start?

With an inventory of your information, a naming convention with status and revision, and a simple controlled environment. Then add requirements, plans and checks.


Final Thoughts

Years after that humbling “latest set of drawings” episode, I visited the same client for a different project. At the start of the meeting, they asked a question I had never heard from a client before: “Which information would you like us to confirm for you today?” I realized, with some pride, that the culture had changed. Not because of a tool, but because someone had taken the trouble to say, project after project, what would be asked, produced, checked and kept.

That is what good information management feels like from the outside: calm. Questions have owners, answers have names and versions, and nobody has to remember where things are. It is not glamorous work, and it is the foundation on which every other BIM benefit stands. Start small, write the rules down, assign someone to look after them, and let the habits grow.

Where to go next: to understand the core tool, read Common Data Environment (CDE): The Complete Guide. To start from the requirements side, continue with ISO 19650 Information Requirements Explained: OIR, AIR, PIR, and EIR, and for the delivery side, Master Information Delivery Plan (MIDP): Complete Guide.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.