The best CDE setup I ever did took three days, and none of those days was spent clicking in the platform. On day one, six of us sat in a room with a whiteboard and a stack of coffee cups and argued about words: what exactly counts as “shared”? Who may move a model from work in progress? What does “suitable for coordination” allow a structural engineer to do with an architect’s model? On day two, we turned the answers into a naming convention, a permission matrix and a one-page workflow. On day three, finally, we configured the tool, which took about four hours, because every decision had already been made.
The worst CDE setup I ever saw took three weeks and started the other way round. The client bought a platform, a consultant configured it with the default folders and everybody was told to “start uploading”. By the second month, nobody was sure what the folders meant, files were arriving with five different naming habits, and the information manager spent her days moving things to where they should have been.
The difference is not talent or budget. It is sequence. A CDE is a solution plus a workflow, and the workflow has to be designed before the solution is configured. This guide gives you that sequence in eight steps, with the decisions to make, the outputs to produce and the tests to run at each step. It is tool-neutral, because platforms differ and change, but the logic is the same everywhere. For the concept, read Common Data Environment (CDE): The Complete Guide first.
The Short Answer
Setting up a CDE takes eight steps.

- Define scope and requirements. What must the CDE do, for whom and under which standards?
- Choose the platform. Select a solution that fits the requirements.
- Design areas and folders. Structure the environment around the states and the project.
- Define roles and permissions. Who may see and do what, in each state.
- Define naming, metadata and status codes. Make every container identifiable.
- Design workflows and templates. Turn the gates into procedures people can follow.
- Mobilize: test and train. Prove it with real information and real users.
- Operate, audit and archive. Run it, review it and close it properly.
In one sentence:
Decide the rules on paper, configure the tool to match, test with real files, and only then ask everybody to start.
Step 1: Define Scope and Requirements
Decisions to Make
| Question | Why it matters |
|---|---|
| Who provides the CDE? The appointing party, the lead appointed party, or both | Determines responsibility and cost. See ISO 19650-2: BIM Information Management During Project Delivery |
| What goes in it? Models, drawings, documents, correspondence, issues, reports | Determines the features needed |
| Which phases? Delivery only, or delivery plus handover to operation | Determines retention and handover design |
| Who uses it? Number of organizations, users, locations, mobile and site users | Determines scale, licensing, support |
| Which standards apply? ISO 19650, national annex, client information standard | Determines naming, status and revision rules |
| What is sensitive? Results of the security triage | Determines access control and hosting. See ISO 19650-5: Security-Minded BIM Information Management |
| Which integrations? Authoring tools, coordination tools, issue tracking, client systems | Determines technical requirements |
| Which open formats and APIs? IFC, BCF, OpenCDE | Avoids lock-in |
Outputs
- A one-to-two-page CDE requirements statement, included in the EIR or the BEP.
- A list of users and organizations with roles.
- A security note summarizing sensitivity and consequences.
Common Mistake at This Step
Skipping it and letting the platform’s feature list define the requirements. Features you do not need still cost money and add complexity.
Step 2: Choose the Platform
If the client has already specified a platform, skip to Step 3. Otherwise, assess candidates against the requirements. The detailed criteria and a comparison of well-known platforms are in Best CDE Platforms Compared: ACC, Trimble Connect, Dalux, BIMcollab, and More. In short:
- Shortlist two or three candidates that match your requirements and your market.
- Score them on workflow, naming and metadata enforcement, permissions, open standards, model handling, integration, security and cost.
- Run a pilot with a small set of real files and a few real users.
- Check the exit: can you export everything with metadata and history?
- Record the decision and its reasons.
Outputs
- A platform decision with a brief justification.
- A list of configuration constraints: what the platform can and cannot enforce, so the workflow design is realistic.
Step 3: Design Areas and Folders
Now design the structure of the environment. The four states of ISO 19650 are the backbone. The structure must make it obvious where information belongs and what may be done with it.
A Typical Structure
| Area | Purpose | Typical content |
|---|---|---|
| Work in progress | Private working areas, one per organization or task team | Draft models, drawings and documents under development |
| Shared | Information approved for sharing | Models and documents suitable for coordination, information, review |
| Published | Information authorized for use | Issued drawings, authorized models, deliverables accepted by the appointing party |
| Archive | Record of superseded and historical information | Previous revisions, milestone snapshots |
| Reference information and shared resources | Information provided to the delivery team | Surveys, existing models, libraries, templates, standards |
| Management and records | Project management information | Plans, standards, meeting minutes, transmittals, issue logs |
Design Principles
- Keep it shallow. Too many folder levels make navigation hard. Use metadata for classification instead of deep trees.
- Mirror the information standard. Use the same terms in folders and in naming codes.
- One home per container. If the platform allows multiple locations, define a primary one.
- Separate organizations in WIP. Each organization works in its own area, and the platform enforces who can see it.
- Make the states real. Where the platform has workflow features, use them to move containers between states, not manual dragging.
- Plan for scale. Think about large projects with many buildings, zones and disciplines, and decide whether sub-areas by building or zone are needed.
Outputs
- A structure diagram and short descriptions of each area.
- A mapping between ISO 19650 states and the platform’s features.
Step 4: Define Roles and Permissions
Permissions are where the CDE enforces the rules. A permission matrix is the single most useful document in the setup.
Define the Roles
| Role | Typical rights |
|---|---|
| Administrator (information manager) | Configure, manage users, override with audit |
| Task team member | Create and edit in own WIP; request sharing |
| Task team lead | Approve sharing of the team’s containers |
| Coordinator | Read shared; create issues; run coordination |
| Lead appointed party representative | Authorize publication |
| Appointing party representative | View published; accept deliverables |
| Reviewer | View and comment on shared information |
| Read-only stakeholder | View specific published information |
| External or temporary user | Narrow, time-limited access |
Example Permission Matrix (Simplified)
| Area | Task team member | Task team lead | Coordinator | Lead appointed party | Appointing party | Administrator |
|---|---|---|---|---|---|---|
| Own WIP | Read, write | Read, write, approve for sharing | No access | No access | No access | Manage |
| Other teams’ WIP | No access | No access | No access | No access | No access | Manage |
| Shared | Read | Read | Read, comment | Read, comment | Read | Manage |
| Published | Read | Read | Read | Read, authorize | Read, accept | Manage |
| Archive | No access or read | Read | Read | Read | Read | Manage |
| Reference information | Read | Read | Read | Read, write | Read, write | Manage |
Adapt to your project. Security-sensitive projects will narrow it further.
Principles
- Least privilege. Give the minimum access needed for the role.
- Need-to-know for sensitive information. See BIM Information Security, Access Control, and Data Governance.
- Use groups and roles, not individual permissions, so that changes are manageable.
- Define joiner, mover and leaver procedures: how access is granted, changed and removed. Removing access when people leave a project is the most neglected control in the industry.
- Review permissions at each milestone.
Outputs
- The permission matrix.
- A user register with organization, role and access groups.
- Joiner, mover, leaver procedures.
Step 5: Define Naming, Metadata and Status Codes
This is the heart of the information standard, and it must be settled before the first upload.
Container Identification
Define the fields of the identifier, their order, delimiter and code lists, following ISO 19650-2 and the national annex where one exists. See BIM File Naming Conventions and ISO 19650.
Metadata Fields
Decide which metadata every container must carry in the platform, for example:
- Status (suitability) and revision;
- Classification where required;
- Originator, discipline, zone, level;
- Document type;
- Date, author;
- Purpose or milestone.
See BIM Metadata, Attributes, and Property Sets Explained.
Status and Revision Code Lists
Define the status codes and their meanings, which state each belongs to and what can be done with information at each status. Define the revision scheme (for example preliminary and contractual series) and when it changes.
Enforcement
Configure the platform to enforce naming and mandatory metadata where it can: rejecting uploads that do not comply, or at least flagging them. Where the platform cannot enforce, define spot-check procedures and responsibilities.
Outputs
- The project information standard: naming, metadata, codes.
- Code lists in a form the platform can import.
- A short user guide with examples.
Step 6: Design Workflows and Templates
Now turn the gates into procedures.
Define the Workflows
| Workflow | Steps (typical) | Who |
|---|---|---|
| Share | Author checks; team lead reviews; approves; container moves to shared with a status and revision | Task team |
| Publish | Lead appointed party reviews against requirements; authorizes; where required, appointing party accepts | Lead appointed party, appointing party |
| Supersede and archive | New revision replaces the old; old moves to archive | Information manager |
| Issue / transmittal | Formal issue of selected containers to named recipients, with a record | Information manager |
| Comment and review | Reviewers comment on shared information; authors respond | Reviewers, authors |
| Issue management | Coordination issues created, assigned, resolved and closed. See BIM Collaboration Format (BCF): The Complete Guide | Coordinator |
| Exception handling | How to handle urgent or out-of-process needs, with a record | Information manager |
Set Targets
Agree turnaround times for reviews and approvals, so the gates do not become bottlenecks. Put them in the MIDP. See Master Information Delivery Plan (MIDP): Complete Guide.
Prepare Templates
- Transmittal template.
- Check report template for the author’s quality assurance before sharing.
- Gate review checklists.
- Project templates for models and documents that carry the right metadata and naming from the start. See How to Build a BIM Project Template.
- Meeting and issue templates.
Outputs
- Workflow diagrams and procedures, one page each.
- Templates loaded into the platform or the project standards.
- Service levels for reviews.
Step 7: Mobilize, Test and Train
ISO 19650-2 includes a mobilization activity precisely because nothing should reach production untested. For the CDE, mobilization is the step that separates good setups from bad ones.
The Mobilization Test
Run a trial with real information and real users.
- Each task team uploads sample containers with proper names and metadata.
- The information manager checks that naming and metadata are accepted or correctly rejected.
- Teams move containers through the gates: WIP to shared, shared to published, then supersede and archive.
- The coordinator federates models and creates a test issue.
- Users test permissions: can they see what they should, and not see what they should not?
- Test mobile and site access if relevant.
- Test integrations with authoring tools.
- Test export: download a set with metadata and history.
- Test notifications and transmittals.
- Record problems and fix them.
Training
- Role-based training: short sessions per role (authors, reviewers, coordinators, approvers).
- A one-page guide with screenshots of the real configuration.
- A hotline or channel for questions during the first weeks.
- Champions in each organization.
Outputs
- A mobilization test report with results and corrective actions.
- Trained users and a support route.
Step 8: Operate, Audit and Archive
Daily and Weekly Operation
- The information manager monitors uploads for naming and metadata compliance, and corrects or rejects.
- Gates are processed within the agreed times.
- Transmittals are recorded.
- Issues are tracked.
- Access changes (joiners, movers, leavers) are processed promptly.
Periodic Review
At each milestone, and at least quarterly on long projects:
- Audit a sample of containers for correct ID, status and revision.
- Review permissions and remove access that is no longer needed.
- Review the audit trail for anomalies.
- Review metrics (see below).
- Update the workflow and standards if needed, under change control.
Metrics Worth Tracking
| Metric | What it shows |
|---|---|
| Share of containers with correct ID, status and revision | Naming and metadata discipline |
| Gate turnaround time | Bottlenecks |
| Number of containers rejected at upload or at a gate | Quality of submissions |
| Number of out-of-process exchanges (email, other channels) | Adoption |
| Open and overdue issues | Coordination health |
| Number of access exceptions | Control effectiveness |
Handover and Close-Out
- Plan the handover to the owner’s environment at the start: formats, structure, metadata, what is transferred and how.
- Archive the final state with history, according to the contract and retention rules.
- Export the audit trail and key records.
- Remove access that is no longer needed and decommission according to the agreement.
- Capture lessons learned about the CDE and update the standards.
See ISO 19650-3: Information Management During Asset Operations and BIM Model Handover Checklist and Requirements.
Scaling the Setup: Small vs. Large Projects
| Element | Small project | Large project |
|---|---|---|
| Platform | A single, simple platform or well-structured server | Enterprise platform plus specialist tools |
| Areas | Four states and a reference area | Sub-areas by building, zone or package |
| Roles | A handful of roles; one administrator | Many roles; administrator team |
| Permissions | A one-page matrix | Detailed matrix and group management |
| Naming and metadata | Short convention, a few fields | Full convention, many fields, enforcement |
| Workflows | Simple approval steps | Multi-step approvals, transmittals, automation |
| Mobilization | A one-hour dry run | A structured test with multiple organizations |
| Reviews | At milestones | Regular audits, dashboards |
The principle: never skip a step; size each step to the project.
Common Mistakes
- Configuring first, deciding later.
- Copying default folders without mapping them to states and permissions.
- No naming enforcement.
- Giving everyone broad access “to keep it simple”.
- No joiner, mover, leaver procedure.
- Skipping mobilization and discovering problems under deadline pressure.
- No training, or training only the administrators.
- Gates without turnaround times, creating bottlenecks.
- Starting uploads before the information standard is agreed.
- No plan for handover and exit.
- Allowing parallel channels such as email for deliverables.
- No audit, so drift goes unnoticed.
See also Common BIM Mistakes Beginners Should Avoid.
A Setup Checklist
Scope and decisions
- CDE requirements written and agreed.
- Responsibilities for providing and administering the CDE assigned.
- Security triage done and consequences recorded.
Design
- Platform chosen and constraints known.
- Areas and folders mapped to the states.
- Permission matrix and joiner, mover, leaver procedures agreed.
- Naming, metadata and code lists defined.
- Workflows, turnaround times and templates prepared.
Mobilization
- Configuration matches the design.
- Mobilization test run and problems fixed.
- Users trained and support route in place.
Operation
- Monitoring, audits and reviews scheduled.
- Handover and archive plan written.
Frequently Asked Questions
How do I set up a CDE for a BIM project?
Define the requirements, choose the platform, design the areas around the four states, define roles and permissions, agree naming, metadata and status codes, design workflows and templates, test with real information and train users, then operate, audit and archive.
How long does it take?
The decisions can take a few days for a small project and several weeks for a large multi-company one. Configuration itself is usually the shortest part.
Who should set up the CDE?
The party that provides it (often the appointing party for the project CDE), with the information management function of the delivery team, and input from IT and security.
Do I need to buy a new platform?
Not necessarily. Many existing platforms can be configured to meet the requirements. Decide the workflow first, then check whether your tool can support it.
How should I structure the folders?
Around the states (WIP, shared, published, archive), plus reference information and management records, with shallow hierarchies and metadata for detail.
How do I enforce naming conventions?
Use the platform’s naming and metadata enforcement where available, and supplement with spot checks and an administrator who corrects or rejects non-compliant uploads.
What should I test before production?
Uploads with naming and metadata, the gates, permissions, federation and issues, integrations, mobile access, export and notifications.
How do I handle people who leave the project?
Through a leaver procedure that removes access promptly, with a record. Review access at each milestone.
Final Thoughts
That three-day setup stays in my memory because of what happened afterward. The project was complicated, with five companies and a demanding client. In eighteen months, I received exactly two phone calls about the CDE. Both were about forgotten passwords. When I asked the information manager why it had been so quiet, she said: “Because everyone knew what they were allowed to do, and the system said so.”
That is the aim of a good setup: a system that answers the questions before anyone has to ask them. Spend your time on the decisions, write them down, configure the tool to match and test it with the people who will use it. The result will not be exciting. It will be reliable, which is far better.
Where to go next: to choose a platform, read Best CDE Platforms Compared: ACC, Trimble Connect, Dalux, BIMcollab, and More. To define identifiers and codes, continue with BIM File Naming Conventions and ISO 19650, and for protecting what the CDE holds, BIM Information Security, Access Control, and Data Governance.