BIM Protocol and Contract Addendum Template

BIM Protocol and Contract Addendum Template

Contracts and models have a difficult relationship. Contracts are written in words, in a tradition that treats the document as the authoritative record: a drawing is signed, a specification is issued, a certificate is dated. Models are digital, change continuously, belong to many authors and exist, in a meaningful sense, in no single place. When the two meet, questions appear that traditional contracts did not ask. Which prevails if the model and the drawing disagree? Who owns the information in a federated model? May the client reuse the model to extend the building? Who is responsible if the coordinator’s clash test missed a problem? Is the model a contract document at all?

Left unanswered, these questions generate disputes, and the disputes tend to arrive at the worst possible time. For this reason, standard-form contract publishers have developed BIM protocols and addenda: supplementary documents that are incorporated into the main contract (or appointment) and that address, in one place, the obligations, rights, liabilities and limits that apply to the use of building information models and digital information. The best-known examples include the CIC BIM Protocol in the United Kingdom (first commissioned in 2013; the second edition published in April 2018, closely aligned with PAS 1192-2 and therefore applying to information, not just models), the AIA digital practice documents in the United States (E203–2013 Building Information Modeling and Digital Data Exhibit, with G201–2013 and G202–2013 protocol forms, updated in a 2017 release) and the ConsensusDocs 301 BIM Addendum. Sources note that the CIC protocol states that its wording should not be amended and that it takes precedence over existing agreements; in 2021, the UK BIM Framework published an information protocol intended to support ISO 19650 contexts and replace the CIC protocol, so check the current document for your jurisdiction.

This guide is a practical template and checklist for the content of a BIM protocol or contract addendum: what topics to cover, the decisions each requires, options, illustrative plain-language clause drafts to show the type of language involved, schedules to attach, how the protocol relates to the EIR, BEP and appointments, how to use it in practice and the mistakes to avoid. This is not legal advice and the illustrative clauses are not suitable for use as drafted. Contract terms, liability, insurance, intellectual property and dispute resolution depend on jurisdiction and circumstances. Have a qualified lawyer prepare or review any protocol or addendum, and prefer established standard forms.


Free Download

Download: BIM protocol topic and decision checklist (ZIP with Word file)

The download is a ZIP archive containing a Word checklist of the ten protocol topics with a column to record each decision, the schedules to attach and a review checklist; it is a preparation tool for your lawyer, not a contract. It is free to use and adapt for your own projects. Adapt it to your contract, client requirements and standards; it supports professional judgment and is not legal advice.


The Short Answer

Where a BIM protocol sits

LayerRole
Contract or appointmentCreates the main obligations and rights
BIM protocol or addendumSets specific obligations, liability, rights and precedence for information and models
EIR and BEPState requirements and plans for information delivery
Standards and templatesNaming, coordinates, quality rules and tools

In one sentence:

A BIM protocol or addendum, drawn up with legal advice, states in the contract how models and information are to be produced, used, owned and relied on, and which document prevails if they conflict.


What a Protocol Does

FunctionExplanation
Incorporates information management obligationsRequires compliance with the EIR, BEP and standards
Allocates responsibilitiesInformation manager, model authors, coordination
Defines status and relianceWhat may be relied upon, and for what purpose
Sets order of precedenceWhich prevails among contract, protocol, drawings, models and the BEP
Addresses intellectual propertyOwnership and licences for models and data
Limits and allocates liabilityClarifies that modeling does not alter design responsibility or add unintended duties
Covers security and dataConfidentiality, access, data protection
Provides schedulesModel production and delivery table, level of information need, software, responsibilities
Manages changeHow the protocol and plans are updated
Addresses end of the relationshipReturn, retention and archive of information

When to Use One

SituationPractice
Projects with BIM requirements in the EIRIncorporate a protocol into every appointment, so obligations are consistent
Multi-party projectsA common protocol across the supply chain
Public-sector and standard-form contextsUse the recommended protocol
Small projectsA short addendum may suffice, but cover the core topics
International projectsAdapt to local law; use legal advice in each jurisdiction
Operational-phase appointmentsA protocol for information in operation, aligned with the asset information model. See ISO 19650-3: Information Management During Asset Operations

The Template: Topics, Decisions and Options

For each topic, record the decision the parties must make, the options and who decides. Illustrative wording follows in the next section.

1. Definitions and Interpretation

DecisionOptions and notes
Defined termsInformation, model, information container, federated model, common data environment, EIR, BEP, MIDP, TIDP, appointing party, lead appointed party, information manager, level of information need, status codes
Alignment with standardsState the standards and editions that terms follow (for example ISO 19650)
Digital termsDefine “model” and “digital data” broadly enough to cover future formats

2. Order of Precedence

DecisionOptions and notes
Between the protocol and the main contractThe protocol usually prevails on BIM matters; state this explicitly
Between models and other documentsDecide which document type prevails: for example, signed drawings and specifications prevail over models, or a specified model prevails for stated purposes
Between the EIR, BEP and standardsState the hierarchy
Conflicts within the modelProcess for resolving discrepancies

Ambiguity here is the single most common source of BIM disputes. State it clearly.

3. Information Management Obligations

DecisionOptions and notes
Duty to comply with the EIR, BEP and standardsMake compliance an obligation
Information managerWho holds the function; whether it is a contractual role; limits of authority
Information delivery plansMIDP and TIDPs binding or indicative
Standards for naming, coordinates, formatsReference the BEP or attach as schedule
Cooperation and coordinationDuty to cooperate with other parties and with the information manager; what this does not include

4. Model Production and Delivery

DecisionOptions and notes
Model production and delivery tableList the models each party must produce, the stages, level of information need and format (a key schedule in the CIC protocol)
Level of information needBy element group and stage; reference the standard
Exchange formatsNative, IFC version and view; other formats
Delivery times and statusReference the delivery schedule
AcceptanceHow information is accepted or rejected

5. Status, Reliance and Use of Models

DecisionOptions and notes
Purpose of each statusState what each status means and for what it may be relied on
RelianceWhether and how third parties may rely on models; typical positions limit reliance to the stated purpose and status
No unintended warrantyState that sharing a model does not warrant its fitness for other purposes
Responsibility for checkingWho must check information received before use

6. Roles, Responsibilities and Liability

DecisionOptions and notes
Design responsibilityState that the protocol does not change design responsibility under the appointment
Model authorship and accuracyEach party is responsible for its own information
Integration and coordination responsibilityWho is responsible for coordinating, and what is not included
Information manager liabilityScope and limits
Errors and notificationDuty to notify errors discovered, and to correct
Limits on liabilityIf any, per the main contract
InsuranceWhether the protocol affects insurance; consult insurers and brokers

7. Intellectual Property and Licences

DecisionOptions and notes
OwnershipEach party retains ownership of its models and information; the client’s rights as agreed
Licence to useScope: use for the project, and for operation, maintenance, alteration, extension, repair and sale; whether for future projects
Licence to third partiesWhether the client may share models with others (for example subsequent designers, contractors, facility managers)
Third-party contentManufacturers’ objects and licensed content; who is responsible for licences
Moral rights and attributionAs law and contract allow
SurvivalLicences continue after termination, subject to conditions

8. Common Data Environment, Security and Data Protection

DecisionOptions and notes
CDE provision and rulesWho provides it; access; states and workflows; ownership of data in the CDE
Security obligationsConfidentiality; access control; incident reporting; alignment with ISO 19650-5
Data protectionCompliance with privacy law for personal data in models or CDE
Use of external tools, including AI servicesWhether sending project information to external or cloud services requires approval; confidentiality and licensing implications. See BIM Information Security, Access Control, and Data Governance
Cross-border data transferIf relevant
Retention and archiveHow long information is kept and in what formats

9. Software, Technology and Interoperability

DecisionOptions and notes
Software and versionsListed in a schedule; change procedure
Interoperability obligationsExchange via open formats; export settings
Costs of software and trainingWho bears them
Obsolescence and long-term accessArchive formats for long-term readability

10. Changes, Disputes and Termination

DecisionOptions and notes
Change to the protocol or plansProcedure; notice; effect on price and program
Disputes about informationHow disputes about models or information are raised and resolved, consistent with the main contract’s dispute process
TerminationReturn and transfer of information; continuing licences; archive
Assignment and novationEffect on protocol obligations

Schedules to Attach

ScheduleContent
AModel production and delivery table
BLevel of information need tables
CEIR (or reference)
DBEP (or reference)
EResponsibility matrix. See BIM Responsibility Matrix Template: Roles and Deliverables
FSoftware and versions
GSecurity requirements
HInformation delivery plans. See BIM Information Delivery Schedule Template

Illustrative Clause Language (Not Legal Advice)

The following examples show the kind of plain language that protocols use. They are not drafted for use and omit definitions, qualifications and jurisdiction-specific terms. Do not copy them into a contract. A lawyer should draft or adapt the clauses.

TopicIllustrative idea
Precedence“If there is a conflict between this Protocol and the Appointment on matters concerning information and models, this Protocol shall prevail.”
Information management“The Consultant shall produce, exchange and manage information in accordance with the EIR, the BEP and the standards stated in Schedule D.”
Status and reliance“Information shared in a state other than published may be relied upon only for the purpose stated by its status code.”
Design responsibility“Nothing in this Protocol changes the Consultant’s responsibility for design under the Appointment.”
Coordination“Each party is responsible for the content of its own information. The Information Manager’s role in coordination does not relieve any party of responsibility for its own information.”
Errors“A party that becomes aware of an error in information it has produced or received shall notify the Information Manager promptly and correct the error in the next exchange.”
Licence“Each party grants the Employer a non-exclusive licence to use the information it produces for the purposes of the Project and its subsequent operation, maintenance, alteration, extension and repair.”
Security“Parties shall handle information in accordance with the security requirements in Schedule G and shall notify the Information Manager of any security incident without delay.”
External tools“A party shall not upload Project information to an external service without the prior approval of the Employer, where that service may store or use the information outside the Project environment.”
Archive“At completion, the project information model shall be archived in the formats stated in Schedule A and retained for the period stated.”

How the Protocol Relates to Other Documents

DocumentRelationship
EIRSets requirements; the protocol makes them obligations. See Exchange Information Requirements (EIR) Template and Example
BEPThe plan for meeting the EIR; the protocol makes compliance with it an obligation. See BIM Execution Plan (BEP) Template: Complete Guide and Example
Appointments and scopes of servicesThe protocol must be consistent with them, particularly on responsibilities
Responsibility matrixA working document; align it with the protocol and scopes
Delivery scheduleReferenced by the protocol
Standards and templatesReferenced; stated with versions
Insurance and professional indemnityCheck coverage for BIM-related responsibilities
Dispute resolutionFollow the main contract’s process

See BIM Contracts and Legal Considerations for the broader legal context.


Using the Protocol in Practice

PracticeWhy
Include it in every appointment on the projectConsistent obligations
Brief the team at the kickoffContracts that are not understood are not followed. See BIM Project Kickoff Checklist: Complete Guide
Keep it short and aligned with the BEPAvoid contradictions
Do not duplicate technical detailReference the BEP and schedules
Ensure schedules are completedAn empty model production table protects nobody
Keep versions and dates under controlThe version in force must be clear
Review at stage gatesResponsibilities and tools change
Use the order of precedence in disputesThat is its purpose
Seek legal advice on changesDo not edit informally
Learn from disputesUpdate standard forms

Common Mistakes

  1. No protocol or addendum on a BIM project.
  2. Copying a protocol without adapting it, or amending standard wording carelessly.
  3. No order of precedence.
  4. Contradictions between the protocol, BEP and appointments.
  5. Empty or missing schedules.
  6. Silence on reliance and status.
  7. Silence on intellectual property and licences.
  8. Assuming the information manager takes on design liability.
  9. Ignoring security and the use of external tools.
  10. No archive or termination provisions.
  11. Not briefing the team.
  12. Treating a template as legal advice.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we involved a qualified lawyer and considered an established standard form?
  2. Does the protocol include definitions, order of precedence, information management obligations, model production and delivery, status and reliance, roles and liability, intellectual property, CDE, security and data protection, technology, changes and termination?
  3. Are schedules completed (model production table, level of information need, EIR and BEP references, responsibilities, software, security)?
  4. Is the protocol consistent with appointments, scopes, insurance and the main contract?
  5. Is the hierarchy among models and other documents stated?
  6. Is it incorporated into every appointment?
  7. Has the team been briefed?
  8. Is there a review and change procedure?

Frequently Asked Questions

What is a BIM protocol?

A supplementary contract document that sets out obligations, liabilities, rights and limits relating to the use of models and information on a project.

What is the CIC BIM Protocol?

A UK protocol first commissioned in 2013, with a second edition published in April 2018 aligned with PAS 1192-2, intended to be incorporated into appointments; a successor information protocol was published by the UK BIM Framework in 2021 for ISO 19650 contexts. Check the current document.

What are the US equivalents?

The AIA digital practice documents (such as E203, G201 and G202) and the ConsensusDocs 301 BIM Addendum, among others.

Is the BIM model a contract document?

It depends on how the contract and protocol define it. Many protocols state which documents prevail and for what purposes. Decide this explicitly.

Does the protocol change design liability?

Usually protocols state that design responsibility is not changed by the protocol; check the actual wording with a lawyer.

Who owns the models?

Typically each author retains ownership and grants licences for stated purposes; the details are for the contract. Decide explicitly.

Can I write my own protocol?

You can, but prefer established forms and legal advice; informal drafting risks conflicts and gaps.

How is the protocol related to the BEP?

The protocol makes obligations contractual; the BEP details how information will be managed. They must be consistent.


Final Thoughts

A construction lawyer who has spent her career on BIM disputes told me what she sees in nearly every one. “They are never about technology,” she said. “They are about assumptions: one party assumed the model prevailed, another assumed the drawing did; one assumed the information manager checked everything, another assumed nobody did; one assumed the client could reuse the model, another that it could not. A protocol’s job is to turn assumptions into sentences.” She reads the first draft of any protocol with a pencil and writes in the margin, over and over, the same question: “Who decides?”

Use the template as a checklist of the questions a protocol should answer, record the decisions, adopt or adapt an established standard form with a lawyer’s help, attach the schedules, brief the team and keep the protocol consistent with the EIR, BEP and appointments. The protocol will then do what contracts exist to do: let people work together on shared information with their rights and limits agreed in advance.

Download the template: BIM protocol topic and decision checklist (ZIP with Word file).

Where to go next: for the legal context, read BIM Contracts and Legal Considerations. For the documents the protocol incorporates, continue with Exchange Information Requirements (EIR) Template and Example, BIM Execution Plan (BEP) Template: Complete Guide and Example and BIM Responsibility Matrix Template: Roles and Deliverables, and for security, BIM Information Security, Access Control, and Data Governance.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.