Ask a project team a simple question: “When will the structural model for level 3 be ready for coordination?” On a project without an information delivery schedule, the answers will be a polite chorus of “soon,” “next week, probably,” “depends on the architect” and, from the one person who has actually looked at their own workload, “Thursday, if nobody changes anything.” On a project with a schedule, the answer is a date, a name and a status, visible to everyone, tied to a milestone and checked against the dependencies that feed it. The difference is not optimism. It is planning made visible.

ISO 19650-2 calls the planning documents for information delivery the master information delivery plan (MIDP) and the task information delivery plans (TIDPs). Each task team prepares a TIDP listing the information containers it will deliver, when, in what form and who is responsible. The lead appointed party consolidates them into the MIDP, which shows the whole project’s information deliverables, their dates and their dependencies, aligned with the project’s stages and the appointing party’s information exchanges. In practice, the MIDP and TIDPs are usually spreadsheets or CDE-linked registers, and what makes them valuable is not their format but that they are specific, owned, dated and kept up to date.

This guide provides a practical information delivery schedule template: field definitions, the MIDP and TIDP layouts, a worked fictional example for the invented Harbor View Clinic with arithmetic, guidance on setting dates and dependencies, how to track and report progress, how to link the schedule to the BEP, the CDE and checks, and the mistakes to avoid. It supports BIM Execution Plan (BEP) Template: Complete Guide and Example and Exchange Information Requirements (EIR) Template and Example. Adapt the template to your appointment, your EIR and your standard. It is a planning tool, not a contractual instrument unless your documents make it one.


Free Download

Download: BIM information delivery schedule template (ZIP with Excel file)

The download is a ZIP archive containing an Excel workbook with MIDP and TIDP registers, status drop-downs, days-late formulas and a milestone summary with on-time and acceptance rates. It is free to use and adapt for your own projects. Adapt it to your contract, client requirements and standards; it supports professional judgment and is not legal advice.


The Short Answer

An information delivery schedule across stages

ElementPurpose
MIDPThe consolidated list of all information deliverables, with dates and owners
TIDPEach task team’s list of its own deliverables and dates
MilestonesStage gates and information exchanges that drive the dates
DependenciesWhich deliverables need which others first
TrackingStatus and progress against dates

In one sentence:

An information delivery schedule lists every information container the project will produce, with owner, date, form and dependencies, so that delivery can be planned, tracked and checked.


How to Build the Schedule

StepAction
1. Start from the EIR and BEPRequired deliverables, exchange points, formats and levels of information need
2. Fix the milestonesStage gates, client exchanges, approvals, tender and construction dates
3. Ask each task team to draft its TIDPContainers, forms, dates, dependencies, checks
4. Consolidate into the MIDPOne register; remove duplicates; align dates
5. Map dependenciesWho needs what, and when; find critical paths
6. Set exchange cycles and cut-offsRhythm of model sharing and coordination
7. Assign owners and reviewersResponsible for production and for checks
8. Add acceptance criteriaWhat “ready” means for each deliverable
9. Issue, baseline and trackVersion the schedule; monitor status
10. Update at stage gates and when scope changesKeep it current

Field Definitions

FieldMeaningExample
IDUnique schedule line IDD-014
Container IDName per the convention. See BIM Model Naming Convention Template and GuidelinesHVC-STR-V1-ZZ-M3-S-0001
TitleDescriptionStructural model, main building
TypeModel, drawing, schedule, report, specification, asset dataModel
Originator and responsible personOrganization and named author or leadSTR; [name]
Task teamThe team whose TIDP includes itStructure
StageProject stageDeveloped design
Milestone or exchangeThe exchange or gate it supportsDeveloped design coordination exchange
Planned dateThe date by which it must be in the CDE in the target state[Date]
Target state and suitabilityState and status codeShared, suitable for coordination
FormatNative, IFC version, PDF, otherNative model and IFC 4
Level of information needReference to the LOIN tableLOIN-DD-STR
DependenciesContainers or decisions needed firstD-003 shared levels and grids; D-009 architectural model
Checks and acceptanceQuality checks required before issueAuthor checklist; automated rule checks
Reviewer or approverWho accepts itLead designer
StatusNot started, in progress, delivered, accepted, lateIn progress
Actual dateWhen delivered
NotesRisks, comments

Template A: MIDP Layout

IDContainer IDTitleTypeOriginatorStagePlanned dateTarget stateFormatLOIN refDepends onReviewerStatus
[D-001][HVC-ARC-V1-ZZ-M3-A-0001][Architectural model, main building][Model][ARC][Developed design][Date][Shared, S1][Native, IFC 4][LOIN-DD-ARC][D-000 levels and grids][Lead designer][In progress]
[D-002][HVC-STR-V1-ZZ-M3-S-0001][Structural model][Model][STR][D-001]
[D-003][HVC-MEP-V1-ZZ-M3-M-0001][Mechanical model][Model][MEP][D-001; D-002]
[D-004][HVC-IMG-ZZ-ZZ-RP-Z-0001][Clash report][Report][IMG][D-001 to D-003]

Milestone Summary Block

MilestoneDateDeliverables dueGate decision by
[Concept exchange][Date][List or count][Client]
[Developed design exchange][Date]
[Technical design exchange][Date]
[Construction stage exchange][Date]
[Handover][Date]

Template B: TIDP Layout (Per Task Team)

IDContainer IDTitleTypePlanned dateFormatResponsibleChecks before issueDepends onStatus
[S-001][HVC-STR-V1-ZZ-M3-S-0001][Structural model][Model][Date][Native, IFC][Name][Author checklist; rule checks][D-001][In progress]
[S-002][HVC-STR-V1-ZZ-DR-S-0101][Foundation plan][Drawing][Date][PDF, DWG]
[S-003][HVC-STR-XX-XX-CA-S-0001][Structural calculations][Calculation][Date][PDF]

Each TIDP also records team resources (names, availability), assumptions and risks.


Setting Dates Sensibly

RulePractice
Work backwards from milestonesFix the gate date, then allow time for checks, review and approval
Allow for checks and correctionA deliverable “due” at the gate cannot be checked after it
Respect dependenciesStructure after architecture’s shared levels and grids; MEP after structure’s main frame
Use a regular exchange rhythmWeekly or fortnightly cycles with a fixed cut-off day
Phase the workDraft, shared and issued states at defined points
Build in floatBuffers for late changes
Use relative dates“Gate minus 10 working days” helps when gates move
Check capacityDo not schedule more than teams can deliver
Align with the client’s decision timesApprovals take time

A Worked Illustration (Fictional)

For the Harbor View Clinic, the developed design gate is the reference. The team plans: shared levels and grids (T minus 30 working days), architectural model shared for coordination (T minus 20), structural model shared (T minus 15), MEP model shared (T minus 12), clash report issued (T minus 8), corrections republished (T minus 4), final checks and issue (T minus 2). The sequence respects dependencies: each model is shared after the one it depends on, with at least three working days between. Counting the planned deliverables for the gate:

TeamDeliverables for the developed design gate
Architecture8
Structure6
MEP7
Information management3
Total24

Arithmetic check: 8 + 6 + 7 + 3 = 24. The MIDP shows 24 lines for that gate; if the consolidated register shows 22 or 26, something has been dropped or duplicated. (Figures are invented for illustration.)


Dependencies and the Critical Path

Dependency typeExampleAction
Reference informationShared levels, grids, coordinatesIssue first; lock after agreement
Model dependenciesStructure needs architecture; MEP needs structureOrder exchanges accordingly
Decision dependenciesEquipment selection before plant room layoutAdd decision milestones to the schedule
Information dependenciesProduct data needed for asset informationLink to procurement dates
Approval dependenciesClient approval needed before the next stageInclude approval time
External dependenciesSurvey, ground informationTrack as risks

Mark the critical path: the chain of deliverables whose delay delays the gate. Review it weekly.


Tracking and Reporting

PracticeWhy
Update status weeklyThe schedule is a living document
Use a simple status codeNot started; in progress; delivered; accepted; late; at risk
Compare planned and actual datesSlippage trends
Report percentage delivered per milestoneExecutive view
Flag at-risk items earlyIntervene
Link to the CDEDelivered containers visible in the right state
Link to checksDelivered items include check results
Escalate persistent latenessThrough the project structure

Metrics

MetricDefinition
On-time delivery rateDeliverables delivered by planned date ÷ deliverables due
First-time acceptance rateDeliverables accepted without rework ÷ deliverables delivered
Average delay (days)For late items
Scope change rateLines added or removed since baseline
Milestone readinessShare of gate deliverables accepted by gate minus a buffer

A fictional illustration: if 20 of 24 deliverables due this month were delivered by their planned dates, the on-time delivery rate is 20 ÷ 24 = 0.833, or about 83%; if 17 of the 20 delivered were accepted without rework, the first-time acceptance rate is 17 ÷ 20 = 85%. (Figures are invented for illustration.) See BIM Data Analytics: Dashboards, KPIs, and Automated Reporting.


Linking to Other Documents

DocumentLink
EIREvery required exchange and deliverable appears in the schedule. See Exchange Information Requirements (EIR) Template and Example
BEPThe schedule is Section 4 and an appendix. See BIM Execution Plan (BEP) Template: Complete Guide and Example
Responsibility matrixOwners match accountable and responsible parties. See BIM Responsibility Matrix Template: Roles and Deliverables
Naming conventionContainer IDs follow the standard
CDEStates and workflows align with target states
Coordination cycleCut-offs align with meetings. See BIM Coordination Meeting Checklist and Report Template
HandoverAsset data deliverables included. See BIM Model Handover Checklist and Requirements

Common Mistakes

  1. No schedule, or a schedule that is a list of dates without containers.
  2. Dates set at the gate itself with no time for checks.
  3. Ignoring dependencies.
  4. No owners.
  5. Teams not involved in drafting their TIDPs.
  6. Never updated.
  7. Too detailed to maintain, or too vague to use.
  8. No link to naming, states or checks.
  9. Missing asset information deliverables.
  10. No tracking or reporting.
  11. No process for scope changes.
  12. Treating the schedule as a contract instrument when it is not one.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Does the schedule cover every deliverable required by the EIR and BEP?
  2. Do milestones and exchanges drive the dates?
  3. Does each line have container ID, type, owner, date, format, target state, LOIN and dependencies?
  4. Did each task team draft its TIDP, and is the MIDP consolidated?
  5. Are checks, review and approval time built in?
  6. Is the critical path identified and reviewed?
  7. Is status updated weekly and reported?
  8. Are changes controlled and the schedule versioned?
  9. Is it linked to the CDE, naming convention and coordination cycle?

Frequently Asked Questions

What is a MIDP?

The master information delivery plan: the consolidated plan of all information containers the project will deliver, with dates and responsibilities.

What is a TIDP?

A task information delivery plan: a task team’s list of its own deliverables, dates and responsibilities.

Who prepares them?

Each task team prepares its TIDP; the lead appointed party consolidates the MIDP.

What format should it take?

Any clear register: a spreadsheet, a database or a CDE-integrated list. Consistency matters more than tool.

How detailed should it be?

Detailed enough to track each container to a milestone; avoid excessive granularity.

How often should it be updated?

Weekly for status; formally at stage gates and when scope changes.

Is the delivery schedule a contract document?

Not by itself; its status depends on the appointment and protocol. See BIM Protocol and Contract Addendum Template.

How does it relate to the program?

It aligns with the project programme and shows information deliverables in detail; it should not conflict with it.


Final Thoughts

I once inherited a project where the only information schedule was a single line on the programme: “BIM models issued: end of stage.” The team was surprised, at the end of the stage, to discover that “end of stage” meant five different things to five different people. We replaced the line with a register of thirty-one containers, each with a date, an owner and a dependency. It took two days to write. In the first week of using it, three problems appeared that had previously stayed hidden: the structural model could not start because the architect’s shared grids were not yet issued; the MEP team had planned its delivery for a day before it would receive the structure; and nobody had assigned the asset data deliverable. All three were fixed before they became delays.

That is the value of an information delivery schedule: it makes the plan visible while there is still time to change it. Build it from the EIR and BEP, let each team draft its own part, respect dependencies, allow time for checks and track it weekly. Then “when will it be ready?” has an answer, and the answer has a name beside it.

Download the template: BIM information delivery schedule template (ZIP with Excel file).

Where to go next: for the plan it belongs to, read BIM Execution Plan (BEP) Template: Complete Guide and Example. For requirements and responsibilities, continue with Exchange Information Requirements (EIR) Template and Example and BIM Responsibility Matrix Template: Roles and Deliverables, and for names, BIM Model Naming Convention Template and Guidelines.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.