How to Build a BIM Project Template

How to Build a BIM Project Template

If you want to know how mature a design office really is, ask to see its project template. I have done this in dozens of offices, and the answers are instructive. In the best, a template is a carefully maintained product with an owner, a version number, a change log and a short guide. In the worst, it is a file called Template_NEW_final2.rvt that somebody once saved from a successful project, with a hundred unused families, forty view types no one understands and the previous client’s logo still in the title block.

The template is the most leveraged asset in a BIM office. Every project starts from it. Every decision embedded in it, units, levels, parameters, view settings, export mappings, is repeated, automatically, across every model, every discipline and every new starter’s first day. A good decision made once in the template saves hours on a hundred projects. A bad one multiplies in the same way. When I discovered, on that earlier project, that thirty-seven errors came from four systematic mistakes, all four lived in the template.

This guide shows how to build a template that earns its place. It covers what a template is (and is not), its layers, a step-by-step method to build one, the data and export settings that most templates forget, how to test, version and govern it, how to distribute and upgrade it and how to avoid the classic failures. It is written to be tool-neutral: the file formats and menus differ between authoring software, but the decisions are the same. Where it helps, I mention typical concepts such as project template files and shared parameters. For how a template fits into the project start, see How to Set Up a Successful BIM Project from Day One.


The Short Answer

A BIM project template is a starter file (or set of files) that contains the standard settings, content, data structure, views and export configuration an organization or project uses, so that every new model begins in line with the standards.

What a BIM project template contains

A good template carries decisions, not just content. It does the following:

BenefitHow
ConsistencyEvery model starts with the same units, levels logic, parameters, naming and views
QualityCorrect settings prevent whole categories of errors
SpeedLess setup; faster onboarding
InteroperabilityExport and mapping settings are ready and tested
ComplianceStandards from the BEP and EIR are built in
LearningLessons are captured once and benefit every project

In one sentence:

A template is your standards turned into a file: the way to make the right way of working the default way.


What a Template Is, and What It Is Not

It isIt is not
A clean starter with only what projects needA copy of the last project
Versioned and ownedAn orphan file on a shared drive
Tested on real exports and checksA collection of untested settings
Documented with a short guideSelf-explanatory by magic
Part of a system: with libraries, standards and guidesA substitute for training or standards
Specific to a discipline and purpose where neededOne giant file for everybody

Office Template vs. Project Template

TypeOwnerContentWhen
Office (or discipline) templateThe BIM managerOrganization-wide standards for a discipline: units, content, parameters, view standards, export presetsMaintained continuously
Project templateThe project BIM manager, derived from the office templateOffice template plus project-specific items: coordinates, levels, naming codes, client requirements, project parametersCreated at project start. See How to Set Up a Successful BIM Project from Day One

The office template carries stable decisions; the project template adds specific ones.


The Layers of a Template

I organize a template into six layers. Use them as a checklist.

1. Model Setup

The technical foundations of the model.

ItemNotes
Units and precisionAs specified in the BEP; consistent across disciplines
Coordinates and orientationMechanism to adopt project shared coordinates; base point conventions. See BIM Georeferencing: Coordinate Systems and Model Positioning
Levels and gridsA convention for naming and elevations; usually received from the reference model, not invented per discipline
Phases and optionsStandard phase names if used
Worksharing setupWorksets or equivalent standard set; naming; default visibility
Links and referencesStandard approach to linking reference models
Project information fieldsProject code, originator, discipline, status and revision fields
Starting file size and performancePurged; no hidden junk

2. Content

The objects and materials the model uses.

ItemNotes
Core families or objectsA small set of approved, tested, well-parameterized content for common types; others loaded from the library as needed
Types and namingType names follow the convention; product data at type level. See BIM Objects, Families, and Parameters Explained
MaterialsStandard list with appearance and, where used, physical and classification properties
Annotation contentSymbols, tags, text styles, dimension styles
Library connectionLink or instructions for the content library

Keep the template lean. Load what most projects need and leave the rest in the library. An overloaded template is slow and confusing.

3. Data

The information structure. This layer is where templates most often fail.

ItemNotes
Shared parameters or propertiesThe organization’s standard set, defined once, with consistent names, types and groups. See BIM Metadata, Attributes, and Property Sets Explained
Property catalogue linkEach parameter traceable to the catalogue, with definition and allowed values
ClassificationParameters and, where possible, pre-loaded classification tables or lookup
SchedulesStandard schedules that expose data for checks: element counts, missing properties, areas
Unique identifiers and tagsConventions for marks, tags and asset identifiers
QuantitiesConfiguration so that required quantities can be exported

Typical authoring tools store shared parameters in an external definition file, so that identical parameters can be reused across projects. Whatever your tool’s mechanism, define the data once, centrally, and version it.

4. Views and Sheets

How the model is displayed and documented.

ItemNotes
View templates and filtersStandard graphics by discipline and purpose; coordination views for checks
View naming and organizationConsistent, with prefixes; project browser organization
Sheet standardsTitle block, sizes, numbering aligned with the container identification convention
Line styles, patterns, fillsStandard set
Annotation defaultsScale-aware text and dimension styles
Output settingsPrinting and PDF presets

See also BIM Model Naming Convention Template and Guidelines and BIM File Naming Conventions and ISO 19650.

5. Export and Checks

The settings for exchange and quality.

ItemNotes
IFC export setupSaved settings per purpose: schema version, view, geometry, property sets, classification, quantities, coordinates. See How to Export and Import IFC Models Correctly
Category-to-class mappingMapping files stored with the template
Parameter-to-property mappingMapping to property sets and properties
Other exportsFormats for cost, analysis and fabrication
Check setsModel checker rule sets, IDS files and checklists. See BIM Quality Management: Processes, Metrics, and Best Practices and Information Delivery Specification (IDS): The Complete Guide
Warning and health checksStandard views or schedules for self-checks

6. Documentation

A template without documentation is a mystery.

ItemNotes
Quick guideOne to three pages: how to start a project, what is in the template, what to change
Version and change logWhat changed, when, why
Owner and support contactWho to ask
Known limitationsWhat the template does not cover
Link to standardsThe BEP, naming and modeling standards

How to Build a Template: A Step-by-Step Method

Step 1: Define Scope and Audience

Decide:

  • Which discipline and purpose (architecture, structure, MEP, infrastructure, coordination, documents).
  • Which project types it will serve; do not try to cover all.
  • Which software and version.
  • Who will use it and what they know.

Several templates, one per discipline and tool, are better than one compromise.

Step 2: Gather Requirements

Collect:

  • Your BIM standards and BEP template.
  • Client requirements and EIR from recent projects.
  • Lessons learned and the list of recurring errors.
  • Existing templates and what users like and dislike about them.
  • Exchange needs: IFC views, cost and analysis formats.

Step 3: Start Clean

Start from a new, empty template or the vendor default, not from an old project. Add deliberately. Importing a project brings hidden baggage: unused styles, broken links, legacy parameters.

Step 4: Build Layer by Layer

Work through the six layers above, in order. For each decision, ask: Which standard does this serve? Which error does it prevent? If neither, leave it out.

Step 5: Build the Data Layer Carefully

  • Define shared parameters from the property catalogue.
  • Use consistent names, data types and units.
  • Group parameters logically.
  • Include only what the standards require, and a small set of useful extras.
  • Link parameters to IFC property mappings.

Step 6: Configure Export and Mapping

Create and save export setups for each purpose. Store mapping files with the template. Test exports with real content (see testing below).

Step 7: Create Views, Sheets and Schedules

Build the view templates teams need, including coordination and check views. Create schedules for quality checks: missing parameters, duplicate tags, element counts by category.

Step 8: Write the Guide

Write the quick guide while the details are fresh. Include screenshots and a ten-step start-up procedure.

Step 9: Test It

Testing is what separates a template from a hope.

TestWhat to do
Fresh start testA person who did not build the template starts a model from it, following only the guide. Note every point of confusion
Content testPlace typical objects; check parameters, schedules, tags
Export testExport IFC and other formats with the saved settings; validate; open in receiving tools; check properties, classification and coordinates
Check testRun the model checker and IDS on the test model; confirm checks work as expected
Coordinates testAdopt a sample shared coordinate system; confirm alignment with a reference model
Performance testCheck file size, open time and sync time
Upgrade testOpen in the next software version if relevant

Fix what fails. Repeat.

Step 10: Release and Version

  • Name it following the convention, with a version number.
  • Publish through a controlled location (the CDE or a standards library), read-only for users.
  • Announce with a short note on what is in it and what changed.
  • Archive previous versions.

Step 11: Pilot

Use it on one or two projects with support, record feedback and update. See How to Develop a BIM Implementation Strategy for the role of pilots in rollout.


Governance: Keeping the Template Alive

A template ages the moment it is released. Software updates, new client requirements and lessons from projects all change what it should contain.

Governance elementPractice
OwnerA named person responsible for each template
Change requestsA simple route: anyone can propose; the owner decides
Review rhythmAfter each project, and at least annually; after each major software update
Version controlSemantic versioning (for example 2.1) and a change log
Release processTest, document, announce
DeprecationWithdraw old versions; define how existing projects update
Feedback loopA channel for users to report issues
MetricsWhich errors recur in projects; template compliance rate

Project Updates

When the template changes mid-project, do not update projects automatically. Decide case by case, with a clear procedure for any migration, because changing parameters or mappings mid-project can break links and schedules.

Software Upgrades

Each major software release can change defaults, parameters, graphics and export behavior. Plan an upgrade cycle: test the template in the new version, update, document, then release for new projects. Existing projects normally stay on their version until a milestone permits upgrade.


Templates Beyond the Model File

BIM projects depend on other templates. Treat them with the same care.

TemplatePurposeRelated guide
BEP templateStandard structure and text for BEPsBIM Execution Plan (BEP): How to Create and Implement One
Responsibility matrixPre-filled with standard activitiesHow to Create a BIM Responsibility Matrix
MIDP and TIDP templatesConsistent planning documentsMaster Information Delivery Plan (MIDP): Complete Guide, Task Information Delivery Plan (TIDP): Complete Guide
EIR response templateTender response structureHow to Respond to BIM Requirements in Tenders
Meeting and issue templatesCoordination agendas, minutes, issue formsBIM Coordination Meetings: Planning, Reporting, and Best Practices
Quality checklistsSharing and gate checklistsBIM Quality Management: Processes, Metrics, and Best Practices
IDS and check set libraryReusable requirement checksInformation Delivery Specification (IDS): The Complete Guide
Document templatesReports, specifications, transmittals

A well-run office keeps these in a standards library with owners and versions.


Template Contents: A Starter Specification

Here is a condensed specification for an architectural model template. Adapt it for other disciplines. It is an illustration.

LayerContents
Model setupMillimeter units; project info fields for code, originator, discipline; shared coordinates procedure; level and grid placeholders replaced by reference model; standard worksets (shell, interior, furniture, links, reference); standard phases
ContentCore wall, floor, roof, door, window and ceiling types named to convention; standard material list; annotation family set; library link
DataShared parameter set for identification, classification, fire rating, acoustic, thermal, finish, manufacturer, model, asset tag; schedules for missing parameters and duplicates; room data parameters
Views and sheetsView templates for plans, sections, elevations, coordination and checking; filters for fire-rated and external elements; sheets with title block fields aligned to container ID
Export and checksSaved IFC setups (coordination reference view; handover); category and parameter mapping files; model checker rule set; IDS for doors, windows and rooms
DocumentationThree-page guide; change log; owner and contact

Common Problems and Remedies

ProblemCauseRemedy
Template is huge and slowBuilt from an old project; many unused familiesRebuild clean; keep core content only; use a library
Teams change the templateSettings not locked; no guideLock critical settings; document what may be changed
Parameters differ between projectsNo central definitionMaintain a shared parameter file and catalogue under version control
Exports differ between usersExport settings not savedSave setups and mappings; distribute with the template
Template out of dateNo owner or reviewName an owner; review after each project
Template ignores client requirementsWritten once, genericMaintain a project template layer with client-specific items
People start projects from old filesTemplate hard to find or unlovedMake it easy to find; show benefits; check at audits
Updates break running projectsMid-project changeFreeze versions per project; plan migrations carefully
Too many templatesProliferationConsolidate; define which template for which purpose

Common Mistakes

  1. Starting from an old project file.
  2. Putting everything in instead of what is needed.
  3. No data layer: no shared parameters or mappings.
  4. No export settings in the template.
  5. No guide.
  6. No testing with a fresh user and real exports.
  7. No version number or change log.
  8. No owner.
  9. Locking nothing, so settings drift.
  10. Never updating after projects or software upgrades.
  11. Mid-project template changes without a plan.
  12. Ignoring non-model templates such as the BEP and checklists.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Is the scope defined: discipline, purpose, software version, audience?
  2. Was it built clean, from requirements and standards?
  3. Does it cover all six layers: setup, content, data, views, export and checks, documentation?
  4. Is the data layer defined from a property catalogue?
  5. Are IFC export setups and mappings saved with it?
  6. Is there a quick guide and change log?
  7. Has it been tested by a fresh user, with real exports and checks?
  8. Is it versioned, owned and published from a controlled location?
  9. Is there a review rhythm and a feedback route?
  10. Are non-model templates (BEP, matrix, plans, checklists) maintained too?

Frequently Asked Questions

What is a BIM project template?

A starter file containing the standard settings, content, data structure, views and export configuration that an organization or project uses, so new models start in line with the standards.

What should a Revit or Archicad template include?

The same layers in any tool: model setup, content, data parameters, views and sheets, export and mapping settings, and documentation. Details such as file types and menus differ by software.

How big should a template be?

As small as possible while including what most projects need. Large templates slow down and confuse.

Should I have one template for all disciplines?

Usually no. Use a template per discipline and tool, sharing common elements through the property catalogue and libraries.

What is the difference between a template and a library?

The template is the starter file with settings and core content. The library holds the wider set of approved objects loaded as needed.

How often should the template be updated?

After each project, after major software updates and when standards or client requirements change, with versioning and a change log.

Should existing projects be updated when the template changes?

Not automatically. Decide case by case, with a migration procedure, because mid-project changes can break links and schedules.

How do I get people to use the template?

Make it easy to find, short to learn, reliable and visibly useful, and check usage in audits.

Who owns the template?

A named BIM manager or standards owner, with input from discipline leads and users.

How does the template relate to the BEP?

The BEP states the project’s standards. The template implements many of them in the working files.


Final Thoughts

After that project with the thirty-seven errors, I rebuilt our templates from scratch. It took six weeks and felt like a lot of effort for something users would never notice. And that is exactly what happened: nobody noticed. Errors that used to appear in every project simply stopped. New starters produced correct models in their first week. Exports worked the first time. The only evidence of the template’s value was an absence of complaints, which, in my business, is the highest praise.

That is the template’s quiet power. Build it clean, build it in layers, test it with someone who did not make it, give it an owner and keep it alive. It is the closest thing the BIM world has to compound interest.

Where to go next: to see how the template fits the project start, read How to Set Up a Successful BIM Project from Day One. For the data it carries, continue with BIM Metadata, Attributes, and Property Sets Explained, and for the standards behind it, BIM Quality Management: Processes, Metrics, and Best Practices.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.