BIM Project Risk Management: Common Risks and Mitigation Strategies

BIM Project Risk Management: Common Risks and Mitigation Strategies

There is an exercise I run at the start of every BIM project, and it always makes people slightly uncomfortable. I call it the pre-mortem. I ask the team to imagine it is eighteen months in the future and that the project’s information management has failed badly. Then I ask them to write down, on sticky notes, why. Within ten minutes, the wall is covered. “The client changed the brief three times and we kept modeling the old one.” “The mechanical subcontractor turned out not to be able to produce IFC.” “We lost the structural modeler in month four and nobody else knew the setup.” “The platform went down the week before the milestone.” “The model got so heavy that nobody could open it.”

What strikes me every time is that nobody has trouble listing the risks. They know them. They have lived through them. The failure is that, in most projects, those risks stay in people’s heads, unrecorded, unowned and unmanaged until one of them happens. A risk that is written down, assessed and given an owner is a manageable item. A risk that is only a feeling in someone’s stomach becomes a crisis.

BIM project risk management is the discipline of moving risks from stomachs to registers. It is not complicated, and it needs no special software. This guide explains how to do it: what a risk is in an information management context, how ISO 19650 expects risk to be handled, which risks recur most often, how to assess and treat them, how to build a useful risk register and how to keep it alive. It includes a worked register with a dozen typical risks and mitigations. For the planning context, see BIM Project Planning: Milestones, Deliverables, and Coordination.


The Short Answer

A risk is the effect of uncertainty on objectives: something that might happen and, if it did, would affect what you are trying to achieve. BIM project risk management identifies, assesses, treats, monitors and communicates the risks to the delivery of information and to the benefits expected from BIM.

A simple BIM risk matrix

The general process follows the widely used structure of risk management standards such as ISO 31000, which describes a cycle of establishing scope, context and criteria; assessing risk (identification, analysis, evaluation); treating risk; monitoring and review; communication and consultation; and recording and reporting.

In one sentence:

Write down what could go wrong, decide how much it matters, assign someone to deal with it and keep looking.


How ISO 19650 Treats Risk

ISO 19650-2 makes risk part of the delivery process.

  • During the tender response, the prospective lead appointed party prepares a risk register for the delivery team, alongside the pre-appointment BEP, the draft MIDP and the mobilization plan. The register captures the risks to information management that the team has identified.
  • After appointment, the register is maintained as the project proceeds, and the lead appointed party’s information management function reports on it.
  • The appointing party also considers risks in its assessment and need activity, including the security triage and risks relating to information. See ISO 19650-5: Security-Minded BIM Information Management.

The standard does not prescribe a method. It expects the parties to apply a recognized approach proportionate to the project. See ISO 19650-2: BIM Information Management During Project Delivery.


What Kinds of Risk Does a BIM Project Face?

I group them into eight families. Use them as a prompt list in workshops.

FamilyExamples
1. Requirements and scopeUnclear or changing EIR; requirements that cannot be verified; scope creep; mismatch between brief, PIR and EIR
2. People and capabilitySupplier cannot deliver what is required; skills shortage; key person leaves; resistance to new methods; insufficient client review capacity
3. Process and planningUnrealistic MIDP; missed dependencies; late reference information or client decisions; no freeze dates; coordination breakdown
4. Technology and infrastructureSoftware version mismatches; poor interoperability; model size and performance; CDE outage; hardware limits
5. Information and data qualityMissing or wrong properties; poor classification; unstable identifiers; unreliable survey data; handover data incomplete
6. Commercial and contractualBIM obligations unclear in contracts; liability for models and data unclear; intellectual property; fee does not match scope
7. Security and governanceUnauthorized access; leaks of sensitive information; non-compliant data handling; leaver access not removed. See BIM Information Security, Access Control, and Data Governance
8. External and organizationalRegulatory change; client reorganization; supply chain disruption; changes in standards or mandates

A single event can touch several families. A late client decision (family 3) may create scope changes (1) and cost disputes (6).


Step 1: Establish Scope, Context and Criteria

Before listing risks, agree the frame.

  • Scope: which objectives are at risk? Typically the information deliverables, milestones, quality, cost and the benefits expected from BIM. See How to Define BIM Goals, Uses, and Project Deliverables.
  • Context: the project’s size, complexity, parties, timeline, technology and client requirements.
  • Criteria: how will you rate likelihood and impact? Define scales that suit the project.

A Simple Scale

LevelLikelihood (example)Impact on information delivery (example)
LowUnlikely during the projectMinor rework; no effect on milestones
MediumPossible; has happened on similar projectsNoticeable rework; milestone at risk; some cost
HighLikely or already occurringMilestone missed; significant cost; contractual consequences; safety or security impact

Three levels are enough for most projects. Larger projects may use five levels with numeric scoring. Define the scales in the BEP so that everyone rates consistently.


Step 2: Identify Risks

Methods That Work

MethodHow
Pre-mortem workshopImagine failure and ask why; capture every cause on sticky notes
Prompt-list workshopWalk the eight families above; ask “what could go wrong here?”
Lessons-learned reviewRead lessons from previous projects
Document reviewRead the EIR, contract, programme and BEP looking for gaps and conflicts
InterviewsAsk task team leads, the client, the facility manager
Process walk-throughFollow a deliverable from request to acceptance, noting weak points
Capability assessmentReview suppliers’ capability and capacity evidence

Write Risks Well

A risk statement should say cause, event and consequence.

WeakBetter
“Supplier problems.”“Because the MEP subcontractor has no experience producing IFC with the required property sets, it may deliver incomplete data at the design milestone, causing rework and a late asset register.”
“Software.”“Because disciplines use different versions of the coordination software, models may open incorrectly, causing misleading clash results.”
“Client.”“Because the client has not fixed the room layouts, late changes may invalidate coordinated models, causing rework and missed milestones.”

Step 3: Analyze and Evaluate

For each risk, estimate:

  1. Likelihood: how probable is it?
  2. Impact: how bad if it happens?
  3. Proximity: when might it occur?
  4. Controllability: how much can you influence it?
  5. Owner: who can best manage it?

Plot on the matrix and rank. Act first on high-likelihood, high-impact items, and consider proximity: a medium risk that could occur next week may need earlier action than a high risk six months away.

Be honest about uncertainty. Estimates are judgments. Their value lies in comparing risks and focusing effort, not in precision.


Step 4: Treat the Risks

For each prioritized risk, choose a response. Common options:

ResponseMeaningExample
AvoidChange the plan to remove the riskDo not rely on a tool the supplier cannot support; choose another exchange format
Reduce likelihoodMake it less likely to happenPilot the exchange early; train; provide templates
Reduce impactMake the consequence smallerKeep backups; plan contingency time; use stage gates
Transfer or shareMove or share the risk with another partyContractual allocation; insurance where appropriate; shared responsibility in the matrix
AcceptDecide to live with it, knowinglyLow-impact risks; document the decision
ExploitWhere a risk is an opportunity, increase its chanceEarly engagement with a supplier who offers added capability

For each response, define actions, owners, deadlines and cost. A mitigation with no owner is a wish.

Residual Risk

After treatment, some risk remains. Record the residual rating, and decide whether it is acceptable. If not, treat further or escalate.


Step 5: Build and Keep the Risk Register

The register is a simple table, but a living one.

FieldContent
IDUnique reference
Risk statementCause, event, consequence
Family / categoryFor grouping
Likelihood, impact, ratingCurrent assessment
ProximityWhen it could occur
OwnerPerson accountable for managing it
Response and actionsWhat will be done, by whom, by when
Residual ratingAfter actions
StatusOpen, mitigated, closed, occurred
Early warning indicatorWhat would tell you it is materializing
Date and historyDates of review and changes

A Worked Example

Here is an extract from a fictional BIM risk register. The ratings are illustrative.

#Risk (cause, event, consequence)RatingResponseOwnerEarly warning
1Because EIR requirements are written in prose, the team may interpret them differently, causing disputes at acceptanceHighTranslate key requirements into verifiable checks (IDS); review the EIR with the client in week 2BIM managerQuestions about requirements in meetings
2Because the MEP subcontractor has limited IFC experience, asset data may be incomplete at the design milestone, causing reworkHighCapability assessment; provide property templates and a sample deliverable; trial export in week 3MEP task team lead; BIM coordinatorFailed trial export
3Because client decisions on layouts are expected late, coordinated models may become obsolete, causing reworkHighPut decisions in the MIDP; set freeze dates; record impact of slippageProject managerDecision date slipping
4Because disciplines use different software versions, models may open incorrectly, causing false clash resultsMediumFix versions in the BEP; test in mobilization; control updatesBIM managerInconsistent results between users
5Because models are large, performance may degrade, delaying coordinationMediumFederation and volume strategy; modeling detail rules; hardware checkBIM coordinatorFile open times increasing
6Because the structural modeler is the only person who knows the setup, a departure may delay deliveryMediumDocument the setup; train a deputy; pair workStructural task team leadKey person leave notice
7Because export settings are not controlled, identifiers may change, breaking issue linksMediumSave and control export settings; test identifier stabilityInformation managerIssues losing element links
8Because there is no leaver procedure, former staff may retain access to sensitive informationHighImplement joiner, mover, leaver procedure; quarterly access reviewsInformation managerStale accounts in CDE
9Because the survey is incomplete, models may be based on unreliable reference informationMediumRequest a verified survey; label reference information with reliability; plan verificationProject managerDiscrepancies on site
10Because the CDE may be unavailable, delivery on a milestone date could be missedLowCheck service levels; backup access route; avoid last-day uploadsInformation managerOutages or slow performance
11Because BIM liability is unclear in appointments, disputes may arise over model errorsMediumAlign BEP and appointments; obtain legal advice; clarify the role of the modelsProject manager; legal adviserDisagreement over responsibilities
12Because handover data is planned late, the asset register may not be ready at completionHighPlan asset data milestones from design; draft checks at technical designMEP lead; contractor; client’s FMAsset data not in plan

This is a typical twelve-line register for a medium project. A register of twelve well-managed risks beats one of ninety forgotten ones.


Step 6: Monitor, Review and Communicate

Review Rhythm

  • Weekly or fortnightly in coordination or project meetings: top risks, new risks, changes.
  • At each milestone: full review; close mitigated risks; add new ones.
  • After events: when a risk occurs or a change happens.

Early Warning Indicators

For each important risk, define an indicator that tells you early. Examples:

RiskIndicator
Supplier capabilityFailed trial exports; late TIDP
Late decisionsDecision log slipping; unresolved questions
QualityFalling first-time pass rate
SecurityStale accounts; unusual downloads
PerformanceIncreasing model open time

Communication

Report to the project manager and client in plain language: top five risks, what changed, what help is needed. Escalate risks that exceed the team’s authority.

Record Lessons

When a risk occurs, record what happened and what worked, and add it to the organization’s lessons. See How to Measure BIM Performance, ROI, and Project Success.


Risk in the Tender and Appointment

MomentRisk activity
Assessment and need (client)Identify risks in requirements, the supply chain market and security; set evaluation criteria for risk management
Tender response (bidder)Prepare the delivery team’s risk register with the pre-appointment BEP; show how risks will be managed. See How to Respond to BIM Requirements in Tenders
AppointmentConfirm the register; align contractual allocation of responsibility with legal advice. See BIM Contracts and Legal Considerations
MobilizationTest the highest risks (exports, CDE, capability) before production
Production and deliveryMonitor and review regularly
Close-outCapture lessons

From the client’s side, ask bidders for their risk registers and judge quality of thinking, not the length of the list.


Treating Typical Risks: Practical Measures

A short catalog of measures that work across many risks.

MeasureRisks it addresses
Pilot exchange in mobilizationInteroperability, supplier capability, software mismatch, export problems
Capability assessment and supportSupplier capability, skills gaps
Verifiable requirements (IDS and checks)Disputes, acceptance problems, data quality
MIDP with dependencies and freezesLate information, rework, coordination failures
Templates and controlled contentQuality, inconsistency, training load
Deputies and documentationKey person dependency
Federation and volume strategyModel size, performance
Joiner, mover, leaver and access reviewsSecurity, leaks
Early asset data planningHandover failures
Change controlScope creep, rework
Contractual clarity with legal adviceLiability and responsibility disputes

Common Mistakes

  1. No risk register.
  2. A register written at tender and never updated.
  3. Risks too vague to act on.
  4. No owners.
  5. Mitigations without actions or deadlines.
  6. Too many risks, so nothing is managed.
  7. Ignoring low-probability, high-impact risks such as security incidents.
  8. No early warning indicators.
  9. Treating risk as negative only, missing opportunities.
  10. Not testing high risks in mobilization.
  11. Not communicating to the client and project manager.
  12. Not capturing lessons.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we agreed scales and criteria for rating risk?
  2. Have we run a pre-mortem or similar workshop with the team?
  3. Are risks written as cause, event, consequence?
  4. Is there a register with owners, responses, residual ratings and indicators?
  5. Are the top risks actively managed, with actions and dates?
  6. Are high risks tested in mobilization?
  7. Is the register reviewed at a defined rhythm?
  8. Is it communicated to the project manager and client?
  9. Are contract and legal risks reviewed with legal advice?
  10. Are lessons captured at close-out?

Frequently Asked Questions

What is risk management in BIM?

Identifying, assessing, treating and monitoring the risks to information delivery and to the benefits expected from BIM, using a register and a regular review.

What are the most common BIM project risks?

Unclear or changing requirements, supplier capability gaps, late decisions and reference information, software and interoperability problems, poor data quality, model size, unclear contract responsibility, security failures and late handover planning.

Does ISO 19650 require a risk register?

ISO 19650-2 includes a risk register for the delivery team in the tender response and expects it to be maintained as the project proceeds.

How many risks should a register have?

Enough to cover the important ones, usually ten to thirty. A short, active register is better than a long, ignored one.

Who owns BIM risks?

Each risk has a named owner who can act on it. The BIM manager or information management function maintains the register.

How do I assess BIM risks?

Rate likelihood and impact on a simple scale, consider proximity, rank them and act first on the highest.

What is a pre-mortem?

A workshop exercise in which the team imagines that the project has failed and lists the reasons, to surface risks early.

How do contracts affect BIM risk?

They allocate responsibilities and liabilities. Align the BEP and appointments, and take legal advice on contractual terms.

How do I manage supplier capability risk?

Assess capability at tender, provide templates and training, test a sample exchange early and monitor deliveries.


Final Thoughts

When I run the pre-mortem now, the wall of sticky notes still fills up in ten minutes. But something has changed in how teams respond. They no longer see the exercise as pessimism. They see it as relief. A designer once told me: “I have been worrying about three of these for months and nobody ever asked.” Writing the risks down turned private anxieties into shared problems with owners, and a shared problem is half-solved.

That is what good risk management feels like. It is not a spreadsheet, though a spreadsheet helps. It is a habit of saying out loud what might go wrong, deciding what to do and checking back. Start with a pre-mortem and a twelve-line register. Review it every week. The risks will not disappear, but they will stop being surprises.

Where to go next: to plan around the risks, read BIM Project Planning: Milestones, Deliverables, and Coordination. For controls that reduce them, continue with BIM Quality Management: Processes, Metrics, and Best Practices, and for the measure of results, How to Measure BIM Performance, ROI, and Project Success.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.