How to Define BIM Goals, Uses, and Project Deliverables

How to Define BIM Goals, Uses, and Project Deliverables

I once facilitated a kickoff workshop for a large commercial project, and began by asking a deceptively simple question: “What do you want BIM to do for this project?” The architect said, “Produce coordinated drawings.” The contractor said, “Give us quantities and a construction sequence.” The client’s facility manager said, “Give me an asset register I can load on day one.” The cost consultant said, “Give me reliable areas and quantities at every stage.” The engineer said, “Do not make us model things nobody will use.”

Every answer was reasonable. Every answer implied different models, different level of detail, different properties and different deliverables. And none of them had been written down. Had we gone straight to the BEP, standards and templates, we would have produced a plan that satisfied nobody, because the team had not agreed what the plan was for.

That workshop is why I now insist that every BIM project starts with three connected decisions: goals (why we use BIM), uses (what we do with it) and deliverables (what we produce and hand over). Get these right and the rest of the planning, from the level of information need to the responsibility matrix, follows naturally. Get them wrong and the project drifts into a model-making exercise with no particular purpose. This guide gives you a practical method, drawing on the structured approach of the widely used Penn State BIM Project Execution Planning Guide and on ISO 19650’s idea that information should be requested for a purpose.


The Short Answer

From goals to deliverables

ConceptQuestion it answersExample
BIM goalWhy will we use BIM on this project?“Reduce on-site clashes between structure and services.”
BIM useWhat will we do with BIM to achieve that?“Design coordination using clash detection.”
Information neededWhat objects, data and documents does that use require, and when?“Structural and MEP models with defined detail at design freeze.”
DeliverableWhat will be produced and handed over?“Federated model, clash reports, coordination issue log.”
CheckHow will we know it was achieved?“No unresolved hard clashes above tolerance at the milestone.”

In one sentence:

Start from the end: decide what the information will be used for, and only then decide what to model, how detailed and what to deliver.

The Penn State guide expresses the same principle: a core concept of its planning procedure is to identify appropriate uses of BIM by beginning with the potential end-uses of the information in the model.


Why This Step Matters

If you skip itWhat happens
Models are built “because we do BIM”Effort on detail that nobody uses
Different parties assume different purposesConflicting requirements; disputes about scope
Standards are invented without a reasonRules without purpose; low compliance
Handover data does not match operationsThe owner cannot use what it receives
Success cannot be measuredNo baseline, no benefits
Costs growEvery model and property has a cost; unfocused work wastes it

ISO 19650 and ISO 7817-1 reinforce the same discipline: information requirements are expressed for purposes, milestones and actors. See ISO 7817-1: Level of Information Need Explained.


Step 1: Define BIM Goals

What a Good Goal Looks Like

A BIM goal states the value BIM should bring, in terms the project or the organization cares about. It is not a task (“create a model”) and not a technology (“use cloud platform”). Good goals are:

QualityMeaning
Linked to project or organizational objectivesTied to the brief, the PIR, the OIR or the team’s own aims
SpecificClear enough to know what it means
MeasurableThere is a way to tell if it was met
RealisticAchievable with the team’s capability and budget
OwnedSomeone is accountable for it
FewThree to five; a long list dilutes attention

Categories of Goals

Goals usually fall into a few groups. A workshop prompt list helps.

CategoryExample goals
Design qualityImprove coordination; evaluate more options early; improve compliance checking
Cost and quantityReliable quantities at each stage; early cost feedback; fewer change orders
Time and programmeBetter sequencing; shorter coordination periods; prefabrication readiness
Safety and riskIdentify hazards early; reduce on-site rework and conflicts
SustainabilityEnergy and carbon analysis; material tracking; waste reduction
Communication and stakeholdersVisualization for users and authorities; faster decisions
Construction and deliveryFabrication models, logistics planning, field verification
Handover and operationAsset data for maintenance; digital handover; operational readiness
Capability and learningDevelop team skills; test a new process; build a data library

How to Run the Goals Workshop

  1. Invite the right people: client, designers, contractor if known, cost consultant, facility manager, key specialists.
  2. Start with the project’s objectives (brief, budget, programme, risks) and the organization’s OIR.
  3. Ask each participant what problem or opportunity BIM could address for them. Capture without judgment.
  4. Group and merge similar items.
  5. Prioritize by value and feasibility, perhaps with simple voting.
  6. Write each selected goal with a measure and an owner.
  7. Record what is out of scope, to manage expectations.

Step 2: Select BIM Uses

What Is a BIM Use?

A BIM use is a method of applying BIM during a project or an asset’s life to achieve one or more goals. Examples used in the Penn State guide include design authoring, 4D modeling, cost estimating, space management and record modeling. The list is broad: design reviews, existing conditions modeling, site analysis, structural and energy analysis, code validation, 3D coordination, site utilization planning, digital fabrication, asset management and more. See BIM Uses Explained: What Is BIM Actually Used For?.

How the Penn State Method Handles It

The planning guide (in its current version, a five-step procedure that separates goals from uses) provides a BIM Use analysis worksheet. It lists potential uses with fields to review the value, the responsible party, the capabilities needed, notes and the team’s decision on whether to implement each use. The point of the worksheet is to consider each use against the goals and the team’s capability, rather than adopting a use because it is fashionable.

Selection Criteria

For each candidate use, ask:

CriterionQuestion
Contribution to goalsWhich goal does it serve, and how strongly?
ValueWhat benefit, to whom?
CapabilityDo the responsible parties have the skills, tools and time?
Cost and effortWhat does it require in modeling, data and coordination?
RiskWhat could go wrong? What are the dependencies?
TimingAt which stages is it applied?
Client and contract requirementsIs it required or expected?

A Goals-to-Uses Matrix

A simple matrix connects goals and uses and reveals gaps and overlaps. This is a fictional example.

GoalUses selectedStageResponsible
Reduce site clashes between structure and servicesDesign coordination (3D clash detection); model-based reviewDesign and pre-constructionBIM coordinator; discipline leads
Reliable quantities and early cost feedbackQuantity takeoff from models; cost estimatingConcept to tenderCost consultant; architect and structural engineer
Asset data available at handoverAsset data capture in models; handover data verificationDesign to completionMEP engineer; contractor; client’s facility team
Faster approval by stakeholdersDesign reviews with visualizationConcept and designArchitect
Improve construction planning4D sequencingPre-construction and constructionContractor

Notice that some uses serve several goals, and some goals need several uses. Both are normal.

Keep the List Short

A project that tries ten uses at once usually does none well. Select the three to six that matter most, and treat others as options if capacity allows.


Step 3: Define the Information Each Use Needs

For each selected use, define what information it requires. This is where the level of information need applies. For each use, work through these questions.

QuestionWhy it matters
Which objects or elements?Not every object needs the same treatment
Which geometry?Detail, dimensionality, location, appearance, parametric behavior, as needed. See ISO 7817-1: Level of Information Need Explained
Which data?Properties, quantities, classification, identification
Which documents?Specifications, calculations, certificates, reports
At which milestone?Information grows over time
Who provides it?The responsible party
Who receives and uses it?The consumer of the information
In which format?Native, IFC and view, document formats
How is it checked?Criteria and tools

Information Exchanges

The Penn State procedure calls this step defining information exchanges: for each exchange between parties in the process, specifying the model elements and the information. In ISO 19650 terms, this is the content of the EIR and the TIDPs. See Exchange Information Requirements (EIR): Complete Guide.

An Example: 3D Coordination

ItemSpecification
UseDesign coordination between architecture, structure and MEP
ObjectsWalls, floors, columns, beams, ducts, pipes, cable trays, major equipment, ceilings
GeometryAccurate envelope dimensions and positions; connections and insulation thickness where relevant to clearance
DataUnique identifiers, discipline, level, system, classification
DocumentsClearance and access rules; clash tolerances
MilestonesBefore each coordination cycle; frozen at design approval
Provider and consumerEach task team provides; coordinator consumes
FormatNative models and IFC4 Reference View for federation
ChecksClash matrix; clearance rules; identifier uniqueness

Step 4: Define the Deliverables

From Information to Deliverables

A deliverable is something produced and handed over: a model, a drawing set, a report, a schedule, a data file. Define each one by:

FieldDescription
Name and descriptionWhat it is
Purpose (use and goal)Why it exists
Responsible partyWho produces it
RecipientWho uses or accepts it
Milestone and dateWhen
ContentReference to the level of information need
Format and versionFile format; schema and view
Check and acceptance criteriaHow it will be verified and accepted

Typical Deliverables by Stage (Illustrative)

StageTypical deliverables
ConceptMassing and option models; area and cost indications; visualizations
Developed designCoordinated discipline models; quantity extracts; analysis reports; coordination reports
Technical design / tenderCoordinated federated model; quantity schedules; specifications linked to model objects; issued drawings
ConstructionFabrication and shop models; sequencing models; field-verified models; progress information
HandoverAs-built models; asset register data; manuals and certificates linked to assets; commissioning data
OperationUpdated asset information model after trigger events

Align names and milestones with the MIDP. See Master Information Delivery Plan (MIDP): Complete Guide and BIM Project Planning: Milestones, Deliverables, and Coordination.

Beyond Models

Deliverables include documents and data, not just models. A project whose deliverable list contains only “BIM model” has not finished thinking. Ask what else each use needs: reports, registers, certificates, dashboards.


Step 5: Build the Traceability Chain

Link goals, uses, information, deliverables and checks in a single table. It becomes the backbone of the BEP, the EIR response and the acceptance process.

GoalUseInformation neededDeliverableResponsibleMilestoneCheck
Reduce site clashesDesign coordinationStructure and MEP objects with defined geometry and identifiersFederated model; clash reportsCoordinator; task teamsEach cycle; freeze at design approvalZero unresolved hard clashes above tolerance
Reliable quantitiesQuantity takeoffElements with quantities and classificationQuantity schedulesCost consultant; designersEach design stageReconciliation within agreed tolerance
Asset data at handoverAsset data captureCritical plant with manufacturer, model, serial number, location, maintenance dataAsset register; linked documentsMEP engineer; contractorCompletion100% completeness for required fields

Test the chain in both directions. For every deliverable, ask which goal it serves. For every goal, ask which deliverable proves it. Gaps and orphans show where the plan needs work.


Using the Results

The goals, uses and deliverables feed the rest of the planning.

OutputFeeds
Goals and uses statementSection 2 of the BEP. See BIM Execution Plan (BEP): How to Create and Implement One
Information needs per useEIR; level of information need tables
Deliverables listMIDP and TIDPs
Responsible partiesResponsibility matrix. See How to Create a BIM Responsibility Matrix
ChecksQuality plan. See BIM Quality Management: Processes, Metrics, and Best Practices
MeasuresPerformance indicators. See How to Measure BIM Performance, ROI, and Project Success
Capability gapsTraining and supply chain actions

Who Writes What

PartyRole in defining goals, uses and deliverables
Appointing partyDefines its goals, PIR and requirements; states required uses and deliverables in the EIR
Lead appointed partyProposes additional uses and a delivery approach in the pre-appointment BEP; confirms in the post-appointment BEP
Task teamsConfirm feasibility; define their deliverables in the TIDP
OperatorsDefine operational uses and asset data needs. See Asset Information Requirements (AIR): Complete Guide

The best results come from doing this together, early, in a facilitated session.


Common Mistakes

  1. Starting from software or standards instead of purpose.
  2. Too many goals or too many uses.
  3. Goals that cannot be measured.
  4. Uses adopted without checking capability of the team.
  5. Deliverables limited to models.
  6. No link between uses and the level of information need.
  7. Ignoring operation: no asset data goal.
  8. Not involving the people who will use the information.
  9. No traceability, so deliverables cannot be justified.
  10. Treating the list as fixed when the project changes.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we run a goals workshop with the right people?
  2. Are there three to five measurable goals with owners?
  3. Have we evaluated BIM uses against goals, value, capability and cost?
  4. Are the selected uses few and clear?
  5. For each use, have we defined the information needed (objects, geometry, data, documents) and milestones?
  6. Are deliverables defined with owners, recipients, formats and acceptance criteria?
  7. Is there a traceability chain from goals to checks?
  8. Do the results feed the BEP, EIR, MIDP and matrix?
  9. Is there a review point when the project changes?

Frequently Asked Questions

What is the difference between a BIM goal and a BIM use?

A goal says why BIM is used (the value). A use says what is done with BIM to achieve it.

What are examples of BIM uses?

Design authoring, design reviews, 3D coordination, quantity takeoff and cost estimating, energy and structural analysis, 4D sequencing, digital fabrication, record modeling, space management and asset management. See BIM Uses Explained: What Is BIM Actually Used For?.

How many BIM uses should a project have?

As many as the goals and capabilities justify, usually three to six prioritized uses.

What is a BIM deliverable?

Something produced and handed over: a model, drawing set, report, schedule, data file or document, defined by purpose, owner, milestone, format and acceptance criteria.

How do goals relate to the EIR?

The appointing party’s goals and PIR shape the EIR, which specify the information and deliverables suppliers must provide.

Who decides the BIM uses?

The appointing party states required uses in the EIR; the delivery team proposes and confirms others in the BEP. Ideally the decision is made jointly.

What is the Penn State BIM Project Execution Planning Guide?

An openly available guide that provides a structured procedure and templates for planning BIM on a project, including goals, uses, process maps, information exchanges and infrastructure. Version 3.0 uses a five-step procedure.

Should goals change during the project?

They can, through controlled change, if objectives change. Review at milestones.


Final Thoughts

After that kickoff workshop, we wrote five goals on a flip chart and chose six uses. The engineer’s request, “do not make us model things nobody will use”, became a design principle: every object we model must serve a use on the list. When someone later proposed adding detailed furniture to the structural coordination model, the answer was simple: which use does that serve? There was no answer, and the furniture stayed out.

That is the power of defining goals, uses and deliverables first. It gives the project a filter. It makes it easy to say yes to what matters, and to say no, politely and with a reason, to what does not. Spend a morning on it. It will save weeks.

Where to go next: to carry the results into the plan, read BIM Execution Plan (BEP): How to Create and Implement One. For the information detail behind each use, continue with ISO 7817-1: Level of Information Need Explained, and for allocating the work, How to Create a BIM Responsibility Matrix.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.