I once facilitated a kickoff workshop for a large commercial project, and began by asking a deceptively simple question: “What do you want BIM to do for this project?” The architect said, “Produce coordinated drawings.” The contractor said, “Give us quantities and a construction sequence.” The client’s facility manager said, “Give me an asset register I can load on day one.” The cost consultant said, “Give me reliable areas and quantities at every stage.” The engineer said, “Do not make us model things nobody will use.”
Every answer was reasonable. Every answer implied different models, different level of detail, different properties and different deliverables. And none of them had been written down. Had we gone straight to the BEP, standards and templates, we would have produced a plan that satisfied nobody, because the team had not agreed what the plan was for.
That workshop is why I now insist that every BIM project starts with three connected decisions: goals (why we use BIM), uses (what we do with it) and deliverables (what we produce and hand over). Get these right and the rest of the planning, from the level of information need to the responsibility matrix, follows naturally. Get them wrong and the project drifts into a model-making exercise with no particular purpose. This guide gives you a practical method, drawing on the structured approach of the widely used Penn State BIM Project Execution Planning Guide and on ISO 19650’s idea that information should be requested for a purpose.
The Short Answer

| Concept | Question it answers | Example |
|---|---|---|
| BIM goal | Why will we use BIM on this project? | “Reduce on-site clashes between structure and services.” |
| BIM use | What will we do with BIM to achieve that? | “Design coordination using clash detection.” |
| Information needed | What objects, data and documents does that use require, and when? | “Structural and MEP models with defined detail at design freeze.” |
| Deliverable | What will be produced and handed over? | “Federated model, clash reports, coordination issue log.” |
| Check | How will we know it was achieved? | “No unresolved hard clashes above tolerance at the milestone.” |
In one sentence:
Start from the end: decide what the information will be used for, and only then decide what to model, how detailed and what to deliver.
The Penn State guide expresses the same principle: a core concept of its planning procedure is to identify appropriate uses of BIM by beginning with the potential end-uses of the information in the model.
Why This Step Matters
| If you skip it | What happens |
|---|---|
| Models are built “because we do BIM” | Effort on detail that nobody uses |
| Different parties assume different purposes | Conflicting requirements; disputes about scope |
| Standards are invented without a reason | Rules without purpose; low compliance |
| Handover data does not match operations | The owner cannot use what it receives |
| Success cannot be measured | No baseline, no benefits |
| Costs grow | Every model and property has a cost; unfocused work wastes it |
ISO 19650 and ISO 7817-1 reinforce the same discipline: information requirements are expressed for purposes, milestones and actors. See ISO 7817-1: Level of Information Need Explained.
Step 1: Define BIM Goals
What a Good Goal Looks Like
A BIM goal states the value BIM should bring, in terms the project or the organization cares about. It is not a task (“create a model”) and not a technology (“use cloud platform”). Good goals are:
| Quality | Meaning |
|---|---|
| Linked to project or organizational objectives | Tied to the brief, the PIR, the OIR or the team’s own aims |
| Specific | Clear enough to know what it means |
| Measurable | There is a way to tell if it was met |
| Realistic | Achievable with the team’s capability and budget |
| Owned | Someone is accountable for it |
| Few | Three to five; a long list dilutes attention |
Categories of Goals
Goals usually fall into a few groups. A workshop prompt list helps.
| Category | Example goals |
|---|---|
| Design quality | Improve coordination; evaluate more options early; improve compliance checking |
| Cost and quantity | Reliable quantities at each stage; early cost feedback; fewer change orders |
| Time and programme | Better sequencing; shorter coordination periods; prefabrication readiness |
| Safety and risk | Identify hazards early; reduce on-site rework and conflicts |
| Sustainability | Energy and carbon analysis; material tracking; waste reduction |
| Communication and stakeholders | Visualization for users and authorities; faster decisions |
| Construction and delivery | Fabrication models, logistics planning, field verification |
| Handover and operation | Asset data for maintenance; digital handover; operational readiness |
| Capability and learning | Develop team skills; test a new process; build a data library |
How to Run the Goals Workshop
- Invite the right people: client, designers, contractor if known, cost consultant, facility manager, key specialists.
- Start with the project’s objectives (brief, budget, programme, risks) and the organization’s OIR.
- Ask each participant what problem or opportunity BIM could address for them. Capture without judgment.
- Group and merge similar items.
- Prioritize by value and feasibility, perhaps with simple voting.
- Write each selected goal with a measure and an owner.
- Record what is out of scope, to manage expectations.
Step 2: Select BIM Uses
What Is a BIM Use?
A BIM use is a method of applying BIM during a project or an asset’s life to achieve one or more goals. Examples used in the Penn State guide include design authoring, 4D modeling, cost estimating, space management and record modeling. The list is broad: design reviews, existing conditions modeling, site analysis, structural and energy analysis, code validation, 3D coordination, site utilization planning, digital fabrication, asset management and more. See BIM Uses Explained: What Is BIM Actually Used For?.
How the Penn State Method Handles It
The planning guide (in its current version, a five-step procedure that separates goals from uses) provides a BIM Use analysis worksheet. It lists potential uses with fields to review the value, the responsible party, the capabilities needed, notes and the team’s decision on whether to implement each use. The point of the worksheet is to consider each use against the goals and the team’s capability, rather than adopting a use because it is fashionable.
Selection Criteria
For each candidate use, ask:
| Criterion | Question |
|---|---|
| Contribution to goals | Which goal does it serve, and how strongly? |
| Value | What benefit, to whom? |
| Capability | Do the responsible parties have the skills, tools and time? |
| Cost and effort | What does it require in modeling, data and coordination? |
| Risk | What could go wrong? What are the dependencies? |
| Timing | At which stages is it applied? |
| Client and contract requirements | Is it required or expected? |
A Goals-to-Uses Matrix
A simple matrix connects goals and uses and reveals gaps and overlaps. This is a fictional example.
| Goal | Uses selected | Stage | Responsible |
|---|---|---|---|
| Reduce site clashes between structure and services | Design coordination (3D clash detection); model-based review | Design and pre-construction | BIM coordinator; discipline leads |
| Reliable quantities and early cost feedback | Quantity takeoff from models; cost estimating | Concept to tender | Cost consultant; architect and structural engineer |
| Asset data available at handover | Asset data capture in models; handover data verification | Design to completion | MEP engineer; contractor; client’s facility team |
| Faster approval by stakeholders | Design reviews with visualization | Concept and design | Architect |
| Improve construction planning | 4D sequencing | Pre-construction and construction | Contractor |
Notice that some uses serve several goals, and some goals need several uses. Both are normal.
Keep the List Short
A project that tries ten uses at once usually does none well. Select the three to six that matter most, and treat others as options if capacity allows.
Step 3: Define the Information Each Use Needs
For each selected use, define what information it requires. This is where the level of information need applies. For each use, work through these questions.
| Question | Why it matters |
|---|---|
| Which objects or elements? | Not every object needs the same treatment |
| Which geometry? | Detail, dimensionality, location, appearance, parametric behavior, as needed. See ISO 7817-1: Level of Information Need Explained |
| Which data? | Properties, quantities, classification, identification |
| Which documents? | Specifications, calculations, certificates, reports |
| At which milestone? | Information grows over time |
| Who provides it? | The responsible party |
| Who receives and uses it? | The consumer of the information |
| In which format? | Native, IFC and view, document formats |
| How is it checked? | Criteria and tools |
Information Exchanges
The Penn State procedure calls this step defining information exchanges: for each exchange between parties in the process, specifying the model elements and the information. In ISO 19650 terms, this is the content of the EIR and the TIDPs. See Exchange Information Requirements (EIR): Complete Guide.
An Example: 3D Coordination
| Item | Specification |
|---|---|
| Use | Design coordination between architecture, structure and MEP |
| Objects | Walls, floors, columns, beams, ducts, pipes, cable trays, major equipment, ceilings |
| Geometry | Accurate envelope dimensions and positions; connections and insulation thickness where relevant to clearance |
| Data | Unique identifiers, discipline, level, system, classification |
| Documents | Clearance and access rules; clash tolerances |
| Milestones | Before each coordination cycle; frozen at design approval |
| Provider and consumer | Each task team provides; coordinator consumes |
| Format | Native models and IFC4 Reference View for federation |
| Checks | Clash matrix; clearance rules; identifier uniqueness |
Step 4: Define the Deliverables
From Information to Deliverables
A deliverable is something produced and handed over: a model, a drawing set, a report, a schedule, a data file. Define each one by:
| Field | Description |
|---|---|
| Name and description | What it is |
| Purpose (use and goal) | Why it exists |
| Responsible party | Who produces it |
| Recipient | Who uses or accepts it |
| Milestone and date | When |
| Content | Reference to the level of information need |
| Format and version | File format; schema and view |
| Check and acceptance criteria | How it will be verified and accepted |
Typical Deliverables by Stage (Illustrative)
| Stage | Typical deliverables |
|---|---|
| Concept | Massing and option models; area and cost indications; visualizations |
| Developed design | Coordinated discipline models; quantity extracts; analysis reports; coordination reports |
| Technical design / tender | Coordinated federated model; quantity schedules; specifications linked to model objects; issued drawings |
| Construction | Fabrication and shop models; sequencing models; field-verified models; progress information |
| Handover | As-built models; asset register data; manuals and certificates linked to assets; commissioning data |
| Operation | Updated asset information model after trigger events |
Align names and milestones with the MIDP. See Master Information Delivery Plan (MIDP): Complete Guide and BIM Project Planning: Milestones, Deliverables, and Coordination.
Beyond Models
Deliverables include documents and data, not just models. A project whose deliverable list contains only “BIM model” has not finished thinking. Ask what else each use needs: reports, registers, certificates, dashboards.
Step 5: Build the Traceability Chain
Link goals, uses, information, deliverables and checks in a single table. It becomes the backbone of the BEP, the EIR response and the acceptance process.
| Goal | Use | Information needed | Deliverable | Responsible | Milestone | Check |
|---|---|---|---|---|---|---|
| Reduce site clashes | Design coordination | Structure and MEP objects with defined geometry and identifiers | Federated model; clash reports | Coordinator; task teams | Each cycle; freeze at design approval | Zero unresolved hard clashes above tolerance |
| Reliable quantities | Quantity takeoff | Elements with quantities and classification | Quantity schedules | Cost consultant; designers | Each design stage | Reconciliation within agreed tolerance |
| Asset data at handover | Asset data capture | Critical plant with manufacturer, model, serial number, location, maintenance data | Asset register; linked documents | MEP engineer; contractor | Completion | 100% completeness for required fields |
Test the chain in both directions. For every deliverable, ask which goal it serves. For every goal, ask which deliverable proves it. Gaps and orphans show where the plan needs work.
Using the Results
The goals, uses and deliverables feed the rest of the planning.
| Output | Feeds |
|---|---|
| Goals and uses statement | Section 2 of the BEP. See BIM Execution Plan (BEP): How to Create and Implement One |
| Information needs per use | EIR; level of information need tables |
| Deliverables list | MIDP and TIDPs |
| Responsible parties | Responsibility matrix. See How to Create a BIM Responsibility Matrix |
| Checks | Quality plan. See BIM Quality Management: Processes, Metrics, and Best Practices |
| Measures | Performance indicators. See How to Measure BIM Performance, ROI, and Project Success |
| Capability gaps | Training and supply chain actions |
Who Writes What
| Party | Role in defining goals, uses and deliverables |
|---|---|
| Appointing party | Defines its goals, PIR and requirements; states required uses and deliverables in the EIR |
| Lead appointed party | Proposes additional uses and a delivery approach in the pre-appointment BEP; confirms in the post-appointment BEP |
| Task teams | Confirm feasibility; define their deliverables in the TIDP |
| Operators | Define operational uses and asset data needs. See Asset Information Requirements (AIR): Complete Guide |
The best results come from doing this together, early, in a facilitated session.
Common Mistakes
- Starting from software or standards instead of purpose.
- Too many goals or too many uses.
- Goals that cannot be measured.
- Uses adopted without checking capability of the team.
- Deliverables limited to models.
- No link between uses and the level of information need.
- Ignoring operation: no asset data goal.
- Not involving the people who will use the information.
- No traceability, so deliverables cannot be justified.
- Treating the list as fixed when the project changes.
See also Common BIM Mistakes Beginners Should Avoid.
A Short Checklist
- Have we run a goals workshop with the right people?
- Are there three to five measurable goals with owners?
- Have we evaluated BIM uses against goals, value, capability and cost?
- Are the selected uses few and clear?
- For each use, have we defined the information needed (objects, geometry, data, documents) and milestones?
- Are deliverables defined with owners, recipients, formats and acceptance criteria?
- Is there a traceability chain from goals to checks?
- Do the results feed the BEP, EIR, MIDP and matrix?
- Is there a review point when the project changes?
Frequently Asked Questions
What is the difference between a BIM goal and a BIM use?
A goal says why BIM is used (the value). A use says what is done with BIM to achieve it.
What are examples of BIM uses?
Design authoring, design reviews, 3D coordination, quantity takeoff and cost estimating, energy and structural analysis, 4D sequencing, digital fabrication, record modeling, space management and asset management. See BIM Uses Explained: What Is BIM Actually Used For?.
How many BIM uses should a project have?
As many as the goals and capabilities justify, usually three to six prioritized uses.
What is a BIM deliverable?
Something produced and handed over: a model, drawing set, report, schedule, data file or document, defined by purpose, owner, milestone, format and acceptance criteria.
How do goals relate to the EIR?
The appointing party’s goals and PIR shape the EIR, which specify the information and deliverables suppliers must provide.
Who decides the BIM uses?
The appointing party states required uses in the EIR; the delivery team proposes and confirms others in the BEP. Ideally the decision is made jointly.
What is the Penn State BIM Project Execution Planning Guide?
An openly available guide that provides a structured procedure and templates for planning BIM on a project, including goals, uses, process maps, information exchanges and infrastructure. Version 3.0 uses a five-step procedure.
Should goals change during the project?
They can, through controlled change, if objectives change. Review at milestones.
Final Thoughts
After that kickoff workshop, we wrote five goals on a flip chart and chose six uses. The engineer’s request, “do not make us model things nobody will use”, became a design principle: every object we model must serve a use on the list. When someone later proposed adding detailed furniture to the structural coordination model, the answer was simple: which use does that serve? There was no answer, and the furniture stayed out.
That is the power of defining goals, uses and deliverables first. It gives the project a filter. It makes it easy to say yes to what matters, and to say no, politely and with a reason, to what does not. Spend a morning on it. It will save weeks.
Where to go next: to carry the results into the plan, read BIM Execution Plan (BEP): How to Create and Implement One. For the information detail behind each use, continue with ISO 7817-1: Level of Information Need Explained, and for allocating the work, How to Create a BIM Responsibility Matrix.