Asset Information Requirements (AIR): Complete Guide

Asset Information Requirements (AIR): Complete Guide

Years ago, I sat in on the handover of a large office building. The contractor had assembled an impressive “operation and maintenance package”: forty-three lever-arch files and a hard drive containing 14,000 documents. The facility manager received it with a polite smile, and then asked the question that every facility manager asks sooner or later: “Where is the list of the pumps?” There was no list of the pumps. There were pump manuals, pump drawings, pump test certificates and pump purchase orders, scattered across the package. But nowhere was there a single table saying: these are the nineteen pumps in the building, this is where each one is, and this is what each one is. He spent the first three months of his tenure building that list by hand, walking the plant rooms with a clipboard.

That building had a BIM model. It was a superb model. It contained, in fact, every pump, correctly placed. But nobody had told the design and construction teams that the owner needed a structured asset register, with specific fields, in a specific format, linked to the owner’s maintenance system. The information existed. It had simply never been requested in a usable form.

The Asset Information Requirements (AIR) exist to prevent exactly this. They are the owner’s statement of what it needs to know about each asset in order to operate and maintain it, written in a form that can be passed to a design team, a contractor and a software system. This guide explains what an AIR is, what it contains, how to design one for a real organization, how it connects to COBie and the asset information model and how to check that what is delivered is what was asked for. For the higher-level needs behind it, see Organizational Information Requirements (OIR): Complete Guide.


The Short Answer

Asset Information Requirements (AIR) specify the information needed to operate and maintain a specific asset (or type of asset), in support of the organization’s OIR. They are written by the asset owner or operator, and they define the asset data and documents that the owner expects to receive and to keep in its asset information model (AIM).

Anatomy of an AIR

In ISO 19650, the AIR:

  • belong to the owner or operator (the appointing party for operation);
  • are asset-oriented, in contrast to the OIR (organization-oriented) and the PIR (project-oriented);
  • inform the PIR and EIR of any project that creates or changes the asset, so that the right data is produced during delivery;
  • define the target content of the AIM and the information needed after trigger events in operation.

In one sentence:

The AIR are the owner’s shopping list for asset data: which assets, which information, in which form, to which quality and for which use.


Why AIR Matter

Without AIRWith AIR
The contractor delivers what is convenient: manuals and PDFsThe contractor delivers structured data that loads into the owner’s systems
The owner builds its asset register by hand after handoverThe register is populated by the project
Design teams model what looks right, not what operation needsModels carry the properties the maintenance team will use
Handover is a dump of foldersHandover is checked against clear criteria
Information costs more to produce than it is worthEffort is focused on information that is used
Different projects deliver different structuresAll projects feed the same asset information model

The AIR also make a business case possible. When an owner can say “this information lets us plan maintenance and avoid failures”, it can justify the effort of producing it.


The Relationship to OIR, PIR, EIR and the AIM

ItemRelationship to the AIR
OIRThe AIR derive from and support the OIR: they translate organization-wide needs into asset-level information. See Organizational Information Requirements (OIR): Complete Guide
PIRA project’s PIR include the information needed to deliver the AIR content at handover. See Project Information Requirements (PIR): Complete Guide
EIRThe AIR are carried into EIR so that suppliers produce and deliver the data. See Exchange Information Requirements (EIR): Complete Guide
PIM and AIMThe relevant content of the PIM feeds the AIM at handover, in the structure the AIR defines. See Project Information Models (PIM) vs. Asset Information Models (AIM)
Trigger eventsDuring operation, events such as refurbishment or failure update the AIM according to the AIR. See ISO 19650-3: Information Management During Asset Operations

What an AIR Contains

An AIR should be concrete enough to be delivered and checked, and short enough to be read. These are its building blocks.

1. Scope: Which Assets

Define the asset types to be covered and how they are broken down. Not every item in a building needs the same attention.

TierExamplesTypical approach
Critical assetsLife-safety systems, critical plant, medical gases, power suppliesFull data, documents, maintenance regime
Significant assetsMajor building services, lifts, key fabric componentsCore data and key documents
General assetsStandard fittings, furnitureGroup-level data, or none
SpacesRooms, zones, departmentsIdentification, area, use, links to assets

Criticality-based tiering is the most effective way of keeping the AIR proportionate. See Level of Information Need vs. LOD vs. LOI: Key Differences.

2. The Asset Breakdown and Identification Scheme

How will assets be named, numbered and tagged? Decide:

The identifier is the glue between the model, the asset register, the CAFM or CMMS system and the physical tag on the equipment. Weak identification is the most common reason asset data fails to connect.

3. The Information per Asset Type

For each asset type (or tier), list the information needed. Typical categories:

CategoryExamples
IdentificationAsset ID, name, type, classification, barcode or tag
LocationSite, building, floor, room, system served
Product dataManufacturer, model, serial number, product reference
Technical dataCapacity, rating, dimensions, performance values
Installation and commissioningInstaller, installation date, commissioning date and results
MaintenanceMaintenance tasks, intervals, spare parts, suppliers
Warranty and contractsWarranty start and end, service contract references
Compliance and safetyCertificates, inspection requirements, safety information. See ISO 19650-6: Health and Safety Information Management
Life cycleExpected life, replacement cost estimate, end-of-life information
DocumentsManuals, drawings, test reports, certificates, linked to the asset

Use the level of information need principle: for each asset type, specify purpose, milestone, actors, and content (data and documents). Geometry is usually minimal for operation, often limited to location and access. See ISO 7817-1: Level of Information Need Explained.

4. Format and Structure

Say how the information must be delivered, in a way that can be loaded into the owner’s systems.

ItemTypical choices
Data structureA defined asset register template; COBie; IFC with defined property sets; a database schema
PropertiesStandard property sets and project properties, defined in a property catalogue. See BIM Metadata, Attributes, and Property Sets Explained
Document linksDocuments stored in the CDE or document system and linked by asset ID
File formatsOpen formats for long-term preservation
Language and unitsDefined

5. Quality Criteria and Verification

Define how the owner will check what is delivered:

  • completeness against the AIR (every in-scope asset has all required fields);
  • validity (data types, units, allowed values);
  • consistency (identifiers unique, locations exist);
  • accuracy (sampling against the installed equipment);
  • timing (when drafts and final versions are due).

State the acceptance criteria so that delivery is not a matter of opinion.

6. Use and Systems

Describe how the information will be used: which systems consume it (asset register, CAFM, CMMS, energy management), which processes depend on it (planned maintenance, compliance, space planning, renewal planning) and which users will access it. This is what keeps the AIR focused on value.

7. Governance and Security

Define ownership, access and retention of the asset information, including treatment of sensitive information. See BIM Information Security, Access Control, and Data Governance.

8. Maintenance of the AIM

State how the AIM will be updated after handover: responsibilities, trigger events and procedures.


COBie and the AIR

COBie (Construction-Operations Building information exchange) is a widely used data structure for handing over asset information in a spreadsheet-like or structured form. It organizes information into related tables, including facility, floors, spaces, zones, types, components, systems, documents, attributes and others, designed so that the data can be loaded into facility management systems.

How COBie relates to the AIR:

  • COBie is one way of delivering the asset information the AIR specify. It is not the AIR itself.
  • The AIR should state which COBie fields are required for which asset types, and any additional attributes, since COBie provides a structure, not a list of required values for your estate.
  • Check how your authoring tools export COBie, and test the result against your asset register.
  • If your systems do not use COBie, define an alternative structure in the AIR.

See COBie Explained: The Complete Guide to BIM Asset Data Handover.


A Worked Example: AIR for Air Handling Units

To make this concrete, here is a condensed AIR entry for one asset type. It is a teaching example.

ItemSpecification
Asset typeAir handling units (critical plant, tier 1)
PurposePlanned maintenance, compliance inspection, renewal planning
MilestonesDraft data at the end of technical design; final data at practical completion; verified data within thirty days after commissioning
Provider / userProvided by the contractor, with design team support. Used by the facility management team and the asset manager
IdentificationUnique asset ID following the estate scheme; classification code from the agreed system
LocationBuilding, floor, plant room; systems and spaces served
Product dataManufacturer, model, serial number
Technical dataAirflow, motor power, filter types, controls reference
Installation and commissioningInstallation date, commissioning certificate reference and test results
MaintenanceTask list, intervals, spare parts list, approved suppliers
WarrantyStart date, end date, supplier
ComplianceApplicable certificates and inspection requirements
DocumentsManufacturer manual, commissioning report and maintenance procedure, linked by asset ID, in an open document format
Delivery formatStructured asset register template, populated and delivered through the CDE; model carrying the same identifiers
VerificationCompleteness check of all fields for every unit; sample verification of 10% of units on site; identifier uniqueness check
AcceptanceDelivery accepted when completeness is 100% for required fields and sample verification shows no errors

Multiply this by the handful of asset types that really matter, and you have an AIR that a contractor can price and an owner can check.


How to Write an AIR: A Step-by-Step Method

Step 1: Start From the OIR and the Operating Model

Review the OIR priorities and how the asset is actually operated: who maintains it, with which systems, under which regulations.

Step 2: Involve the People Who Operate the Assets

Run a workshop with facility managers, maintenance technicians, asset managers and compliance officers. Ask: “Which information do you need in the first week of operating a new building? In the first year? When something breaks?” These are your requirements in embryo.

Step 3: Define Tiers and Asset Types

Agree which assets are critical, significant or general, and list the asset types to be covered. Focus on the 20% of asset types that matter for 80% of operations.

Step 4: Specify the Information for Each Tier

Use the categories above. For each asset type, define the minimum set. Remove anything nobody will use.

Step 5: Define Identification, Classification and Structure

Agree the asset ID scheme, the classification, the location structure and the data structure for delivery. Align with your existing asset register and systems.

Step 6: Define Quality, Verification and Acceptance

Write checkable criteria. Where possible, express them as IDS specifications or as rules in a checker. See Information Delivery Specification (IDS): The Complete Guide.

Step 7: Define the Handover Process

Decide when information is delivered, in drafts and final form, and how it is loaded into the AIM and the operational systems. Include who loads it and how errors are corrected.

Step 8: Test With a Pilot

Apply the AIR to a recent or small project. Check whether the delivered data actually loads into your systems and answers your questions. Improve.

Step 9: Publish and Maintain

Publish the AIR, give it an owner and a version, and review it at least annually, and after each project.


Handover Quality: Checking Against the AIR

The AIR are worth little unless delivery is checked. A practical sequence for verifying asset data:

  1. Completeness check: for every in-scope asset, are all required fields filled?
  2. Validity check: do values follow data types, units and allowed lists?
  3. Uniqueness check: are asset IDs unique, and do they match the tags that will be fixed to the equipment?
  4. Relationship check: does every asset have a location, a system and a type?
  5. Document check: are documents linked and accessible?
  6. Load test: import a sample into the asset system. Do fields map correctly?
  7. Site verification: sample assets on site against the data.
  8. Report and correct, and re-check.

Do this progressively, not only at the end. Checking draft data at the end of design, and again during construction, catches problems while they are cheap to fix. See BIM Model Handover Checklist and Requirements, BIM Model Checking: Geometric and Information Validation and How to Validate IFC Models for Data Quality and Compliance.


AIR and the Asset Information Model in Operation

After handover, the AIR continue to govern the AIM.

  • Planned trigger events (refurbishment, replacement, periodic review) generate updates to the AIM according to the AIR.
  • Unplanned events (failures, incidents) create information that must be recorded.
  • New projects use the AIM as an input and the AIR as the target for new data.
  • Quality of the AIM is audited against the AIR from time to time.

See Asset Information Models (AIM): Creation and Management and BIM for Building Operations and Maintenance.


Existing Assets: Writing AIR When There Is No Model

Most owners manage assets built before BIM. The AIR still apply, with a pragmatic approach.

  • Start with the critical tier, and capture information through surveys, inspections and laser scanning where useful. See Scan-to-BIM: Converting Point Clouds into Intelligent Models.
  • Use the same data structure for existing and new assets, so that the AIM is consistent.
  • Build progressively, populating the AIM through each maintenance and refurbishment event.
  • Do not over-model. For many operational purposes, structured data and documents matter more than detailed geometry.

Common Mistakes

  1. Never writing an AIR, and discovering the data gap after handover.
  2. Asking for everything for every asset, creating cost and noise.
  3. No criticality tiers.
  4. No asset identification scheme, so data cannot be linked.
  5. Requiring documents but not links to assets.
  6. Not involving maintenance staff.
  7. Writing the AIR without checking the target systems, so data does not load.
  8. No quality criteria, so delivery is subjective.
  9. Checking only at the end.
  10. Treating COBie as the AIR instead of as a delivery format.
  11. Forgetting how the AIM will be maintained.
  12. Never reviewing the AIR after projects.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Do the AIR trace to the OIR and to operational processes?
  2. Have operators and maintainers contributed?
  3. Are assets tiered by criticality, with asset types defined?
  4. Is there an identification scheme and a location and classification structure?
  5. Is the information per asset type limited to what is used?
  6. Are format and structure compatible with our systems?
  7. Are quality criteria and acceptance checkable?
  8. Is delivery timing defined, with progressive checks?
  9. Is governance and security addressed?
  10. Is the maintenance of the AIM defined?
  11. Have we piloted the AIR on a project?

Frequently Asked Questions

What are AIR in ISO 19650?

Asset Information Requirements: the information needed to operate and maintain an asset, supporting the OIR and defining the content of the asset information model.

Who writes the AIR?

The asset owner or operator, with its facility management, asset management and compliance staff.

What is the difference between AIR and EIR?

AIR describe what the owner needs to know about the asset. EIR describe what a supplier must deliver under an appointment. The AIR content is carried into the EIR.

Is COBie the same as the AIR?

No. COBie is a data structure for delivering asset information. The AIR say which information, for which assets, to which quality.

How detailed should an AIR be?

As detailed as the operational use requires for each asset tier, and no more. Focus on critical assets.

Do AIR include geometry?

Usually minimal: location and sometimes access or clearance. Operation relies more on data and documents than on detailed geometry.

When should the AIR be written?

Before design starts, so the design and construction teams produce the right data. If they do not exist, write a first version at the start of the project.

How do I check that AIR information has been delivered?

With completeness, validity, uniqueness and relationship checks, ideally automated, plus a load test into the asset system and sample verification on site.

What happens when an asset changes?

The change is a trigger event that updates the AIM according to the AIR.

Can I have one AIR for several assets?

Yes: a single AIR can cover an asset type or class across many assets, with variations by tier.


Final Thoughts

I eventually saw the facility manager from the pump story again, years later, in a different building. At the handover, he opened a laptop and showed me a table. It listed every pump in the building: where it was, what it was, when it had been commissioned, when it would next be serviced. It had been delivered by the project team, in his format, checked against his criteria, with his identifiers. “I did nothing,” he said, grinning. “I just wrote down what I needed, once, and they gave it to me.”

That is the quiet miracle of a good AIR. It does not require advanced technology. It requires an owner who is willing to state what it needs, in a structure that machines and people can both use, and then insists on checking it. Write yours small, test it on one project, and let your maintenance team be the judge. They will tell you quickly whether you got it right.

Where to go next: to see how asset requirements enter projects, read Project Information Requirements (PIR): Complete Guide and Exchange Information Requirements (EIR): Complete Guide. For the asset side after handover, continue with Asset Information Models (AIM): Creation and Management and COBie Explained: The Complete Guide to BIM Asset Data Handover.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.