COBie Explained: The Complete Guide to BIM Asset Data Handover

COBie Explained: The Complete Guide to BIM Asset Data Handover

Somewhere in the world, at this moment, a person is re-typing a manufacturer’s serial number from a nameplate into a spreadsheet. The nameplate is attached to a fan, which is above a ceiling, in a building that was designed in a sophisticated three-dimensional model by a team of professionals and built by another. The serial number was known to the supplier, recorded in the delivery note and photographed at installation. And yet here it is, being copied by hand, by someone who has been hired to recreate information that existed and was lost.

The name of the format that was created to prevent exactly this is COBie, the Construction Operations Building information exchange. It is not a modeling method or a software product. It is a standardized way of delivering the data that an owner needs to operate and maintain a facility: a structured set of tables describing the facility’s spaces, the maintainable equipment in them, the systems they belong to, the attributes of each, the documents that describe them and (in later versions) the jobs and risks associated with maintaining them. According to its steward, COBie was first published by the US Army Corps of Engineers in 2007, with support from NASA and the White House Office of Science and Technology Policy; the National Institute of Building Sciences has curated it since 2013; version 2.4 was adopted into the US National BIM Standard in 2015; and a version 3 is the latest.

COBie has been widely adopted, widely misunderstood and widely over-specified. Some projects deliver beautiful, useful COBie. Others deliver forty thousand rows of unvalidated data that no system can use. This guide explains what COBie is, how it is structured, what changed in version 3, how data are created and validated, how COBie relates to IFC, ISO 19650 and the AIM, how to specify it sensibly, how to receive and use it, the typical problems and the mistakes to avoid. It supports BIM for Facility Management: The Complete Guide and Asset Information Models (AIM): Creation and Management. COBie is a data format. What to require in it depends on the owner’s needs and systems.


The Short Answer

COBie is a non-graphic data format for delivering maintainable asset information at handover, organized in related tables that an owner specifies.

COBie: the families of tables

FamilyTables (indicative)Purpose
OverallCompany, Facility (Scope in version 3)Who and what the deliverable covers
SpatialFloor (Level), Zone, SpaceType, Space, CoordinateWhere things are
AssetType, Component, System, AttributeWhat is maintained and how it is organized
ProcessPackage, Job, Event, Instruction, RiskHow maintenance is organized and risks managed
SupportDocument, Resource, PickListDocuments, resources and allowed values

In one sentence:

COBie lets a project deliver asset data in a standard, structured form so that an owner can load it into maintenance systems quickly and accurately.


What COBie Is, and Is Not

COBie isCOBie is not
A data exchange specification for operations informationA modeling method
A subset of BIM information: non-graphic dataA 3D model
Table-based, usable in spreadsheets and databasesA software product
Owner-specified: the owner decides what is requiredA fixed, complete list of everything that could be asked
A way to deliver maintainable assetsA list of every building element
A deliverable that can be generated at any project phaseOnly a handover format
Applicable to buildings and also to infrastructureLimited to buildings

The official description puts the maintainable assets at the heart of COBie: the items that the owner of a facility will manage in an operations and maintenance system, such as mechanical and electrical equipment and plumbing fixtures. COBie addresses the period between handover and the moment when the facility management system can begin operating and maintaining those assets, aiming to reduce or even eliminate the delay.


The Structure

Overall and Spatial Tables

TableContent (indicative)
CompanyOrganizations involved: manufacturers, contractors, designers; contact information in versions that include it
Facility (Scope in version 3)The facility, structure or group of structures covered, with name, project and site information, units; in version 3 renamed to accommodate infrastructure
Floor (Level in version 3)Levels of the facility, including roof and site levels
ZoneGroupings of spaces for a purpose; spaces may belong to more than one zone
SpaceType (new in version 3)Categories of space to organize spaces
SpaceRooms and spaces with names, categories, areas and heights; components are located in spaces
CoordinatePositions for floors, spaces and components

Asset Tables

TableContent (indicative)
TypeProduct or equipment types: manufacturer, model, category, warranty durations, expected life, replacement information, specifications; a type describes many identical components
ComponentIndividual instances of types: name, space, serial number, tag number, barcode, asset identifier, installation date, warranty start date
SystemGroups of components working together (for example a supply air system); components may belong to more than one system
AttributeAdditional properties for any record: name, value, unit, allowed values

Process and Support Tables

TableContent (indicative)
PackageA grouping of work items
JobMaintenance and operation jobs for types or components: tasks, frequencies, durations, resources
EventA single occurrence of a task as part of a job
InstructionInstructions for tasks
RiskRisks associated with assets or tasks
DocumentDocuments (manuals, certificates, drawings, photographs), by reference or location
ResourceResources used in jobs (tools, materials, skills)
PickListLists of allowed values for fields, to keep data consistent

Relationships

COBie is a relational structure: components belong to types; components are located in spaces; spaces are on floors; components belong to systems; attributes and documents attach to records. Each record has a name, and many have external identifiers linking back to the source model and systems. Required fields on some tables are prerequisites for using others.


Versions and What Changed

VersionNotes
COBie 2.4Widely implemented; adopted into the US National BIM Standard (NBIMS-US V3) in 2015; spreadsheet and IFC-based exchange; defined in an IFC model view for design deliverables
COBie version 3The latest version according to its steward, announced for inclusion in NBIMS-US V4. Per published summaries, it incorporates dozens of updates grouped under ease of use, capabilities, modernization and workflow. Examples include: replacing the Facility table with a Scope table, and the Floor table with a Level table, to accommodate infrastructure; adding a SpaceType table; adding a PartOf field on asset tables to better capture relationships; supporting JSON for machine-to-machine exchange; removing personally identifiable information fields; and adding tables (Package, Job, Event, Instruction, Risk) to better document the activities of a facility, particularly useful when ownership changes
National variantsSome countries have national guidance or code of practice documents for COBie; the UK, for example, had a code of practice for COBie that predated ISO 19650. Check current national documents

Check which version your client, tools and systems support. Specify the version explicitly.


Formats

FormatUse
SpreadsheetThe classic COBie deliverable: workbook with one sheet per table
IFC-basedCOBie data can be carried within IFC, using a model view definition defined for COBie in the IFC 2×3 era. See Model View Definitions (MVD): Understanding IFC Exchange Requirements
Database or system exportsCMMS and CAFM systems often import COBie spreadsheets or equivalent structured tables
JSONMachine-to-machine exchange in version 3
Other mappingsProperty sets and tables derived from model parameters

Whatever the format, the owner’s systems decide what can be loaded. Test.


How COBie Data Are Created

The Process

StepPractice
1. SpecifyThe owner defines the tables and fields required, the version, identifiers, classification and timing. COBie provides the best results when the owner specifies what they require
2. PlanWho populates which tables, from which sources
3. Capture during designSpaces, systems, types and design data from the model and specifications
4. Capture during procurement and constructionManufacturers, models, product data, serial numbers, installation dates, documents
5. Capture during commissioningTest data; job and instruction information
6. CompileCombine data from models, supplier data and field records into COBie tables
7. ValidateCheck structure, required fields, relationships and values
8. VerifyCheck against the building
9. DeliverAt agreed milestones, with final delivery at handover
10. Load and testInto the owner’s systems

Sources of Data

DataTypical source
Spaces and floorsThe architectural model
Systems and componentsMEP and other models; equipment schedules
Types and product dataSpecifications, submittals, supplier data sheets
Serial numbers, installation datesInstallers’ records, delivery documentation
Warranty and maintenance informationManufacturers’ documentation, O&M manuals
DocumentsO&M manuals, certificates, drawings
CoordinatesModel positions

Model authoring tools offer COBie export features, plug-ins or mappings, and dedicated tools can compile COBie from multiple sources. The model alone rarely holds all COBie data, particularly serial numbers and installation records. Plan capture beyond the model.


Specifying COBie Sensibly

COBie is flexible, and that is both a strength and a trap.

PrinciplePractice
Start from the owner’s needsWhat decisions will asset data support?
Specify tables and fieldsNot “COBie”, but “COBie version X: these tables, these fields for these asset types”
Tier by criticalityCore fields for all maintainable assets; more for critical assets; less for minor ones
Define which assets are in scopeMaintainable assets, not every building element
Define identifiersAsset tags and space numbers following the owner’s scheme
Define classificationWhich system, which edition
Define the pick listsControlled values for categories, units, statuses
Define milestonesDraft at design stages; verified at completion
Define quality checksValidation rules and acceptance criteria
Define the loading testInto the owner’s system
Allow for the owner’s data needs not in COBieUse attributes or other formats

An Illustrative Specification Extract (Fictional)

ItemRequirement
Version and formatCOBie, version as agreed, as a spreadsheet workbook
Scope of assetsAir handling units, fan coil units, pumps, boilers, chillers, fire dampers, fire alarm devices (by type), fire doors (by type), lighting control panels
Required Type fieldsName, manufacturer, model number, category (classification code), warranty duration, expected life
Required Component fieldsName, type, space, serial number, tag number (owner scheme), installation date, warranty start date
Required System fieldsName, category, components
Required Space fieldsNumber, name, category, floor, area (per the agreed standard)
DocumentsO&M manual per type, linked by type name; commissioning certificate per component
MilestonesDraft at technical design; update at procurement; verified at practical completion
ValidationNo empty required fields; unique tags; valid pick list values; every component in a space and a system

Validation and Quality

CheckWhat to look for
StructureRequired tables and columns present; names correct
Required fieldsNot empty
UniquenessTags and names unique where required
RelationshipsEvery component has a type and a space; systems reference existing components; spaces reference floors
Pick list valuesValid
Data types and unitsDates, numbers and units correct
ConsistencyCounts match schedules; model and COBie agree
CompletenessAll in-scope assets present
VerificationSample checks against the building
Load testData loads into the owner’s system

Validation tools and checkers exist (open and commercial). Pair them with human sampling against the physical building. See BIM Model Handover Checklist and Requirements and Information Delivery Specification (IDS): The Complete Guide.


COBie in the ISO 19650 World

TopicRelationship
AIR and EIRThe AIR defines the asset information the owner needs; the EIR specifies what projects deliver; COBie can be one format for non-graphical asset data
AIMCOBie data can populate the AIM’s asset register; the AIM is broader. See Asset Information Models (AIM): Creation and Management
PIM to AIMCOBie is a typical vehicle for transferring asset data. See Project Information Models (PIM) vs. Asset Information Models (AIM)
Alternatives and complementsIFC with property sets, IDS for machine-checkable requirements, bSDD for definitions, owner-specific templates. See buildingSMART Data Dictionary (bSDD) Explained
Information container metadataCOBie files are information containers with status and revision

COBie is not required by ISO 19650; it is a widely used asset data format. Your AIR determines whether and how to use it.


Using COBie Data After Handover

UsePractice
Loading the CMMS or CAFMImport types, components, spaces, systems; map fields; test
Planned maintenanceUse Job information and manufacturers’ data to set up schedules. See BIM for Asset Tracking and Preventive Maintenance
Warranty managementUse warranty dates and durations
Space managementSpaces and areas
Document accessLinks to manuals and certificates
UpdatingAdd, change and retire records through trigger events. See Asset Information Models (AIM): Creation and Management
Linking to the modelUse external identifiers to connect records to model elements

Many owners find the initial load the main benefit; keeping it updated is the larger challenge.


Common Problems and Remedies

ProblemCauseRemedy
Thousands of rows nobody usesNo scope; everything exportedDefine maintainable assets; tier by criticality
Required fields emptyData not captured at sourceCapture during procurement and installation; validation
Tags inconsistent or duplicatedNo tagging schemeOwner’s scheme; generation; uniqueness checks
Data do not loadFormat or mapping mismatchTest early; agree version and mapping
Model and COBie disagreeSeparate maintenanceGenerate from the model where possible; reconcile
COBie delivered at the endLate planningDraft deliveries at milestones
Serial numbers missingNot part of the install processInstallation checklists; supplier data
Documents unlinkedDelivered as a dumpLink by type or component; document naming
Owner not involvedContractor-driven specOwner defines requirements
Version confusionSeveral versions in useSpecify and verify version

Common Mistakes

  1. “Deliver COBie” without a specification.
  2. Asking for every element.
  3. No owner scheme for tags.
  4. Leaving data capture to the end.
  5. No validation or verification.
  6. No load test.
  7. No version stated.
  8. Treating COBie as the AIM.
  9. Assuming the model holds all the data.
  10. No update process.
  11. No pick lists or controlled values.
  12. Ignoring documents.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we defined the owner’s needs and systems that COBie data must serve?
  2. Is the COBie version, format, tables, fields and asset scope specified?
  3. Are tags, space numbers, classification and pick lists defined?
  4. Is data capture planned across design, procurement, installation and commissioning?
  5. Are milestones for draft and final deliveries set?
  6. Is there validation (structure, fields, relationships) and verification against the building?
  7. Has a load test into the owner’s system been done with a sample?
  8. Are documents linked to types and components?
  9. Is there an update process for operation?
  10. Is COBie placed within the AIR, EIR and AIM framework?

Frequently Asked Questions

What is COBie?

The Construction Operations Building information exchange: a standardized data format for delivering the information owners need to operate and maintain facilities.

Who created COBie?

It was first published by the US Army Corps of Engineers in 2007, with support from NASA and the White House Office of Science and Technology Policy, and has been curated by the National Institute of Building Sciences since 2013.

What are the COBie tables?

Families covering overall information, spatial information (floors, zones, spaces), assets (types, components, systems, attributes), processes (jobs, events, instructions, risks, packages) and supporting information (documents, resources, pick lists).

What is new in COBie version 3?

Per published summaries: broader infrastructure support (Scope and Level tables), a SpaceType table, a PartOf field, JSON support, removal of personal information fields and additional process tables, among other updates.

Is COBie a 3D model?

No. It is a non-graphic data format, derived from BIM information.

Does ISO 19650 require COBie?

No. COBie is one possible format for asset data; the AIR and EIR decide what is required.

How is COBie created?

From models, specifications, supplier data and field records, compiled into tables, validated, verified and delivered at milestones.

Can I use COBie for infrastructure?

Yes; version 3 changes explicitly aim to accommodate infrastructure projects.


Final Thoughts

I once helped an owner replace a COBie requirement that said, in full, “The contractor shall deliver COBie.” The new version ran to two pages. It listed eleven asset types, the fourteen fields required for each, the owner’s tag scheme, the milestones and a one-page validation checklist. The first project delivered under the new requirement delivered, at completion, a workbook of just over two thousand components. The maintenance team loaded it into their system on a Monday morning and began scheduling work on Tuesday. “The funny thing,” the facility manager told me, “is that the new specification asked for less than the old one would have produced. But we could use every row.”

That is the lesson of COBie. It is a good format, designed to solve a real problem, and it works best when specified with purpose, populated at source, validated and loaded. Define the assets that matter, the fields that serve decisions and the checks that prove quality. The person with the nameplate and the spreadsheet will then be doing something more useful with their afternoon.

Where to go next: for the context, read BIM for Facility Management: The Complete Guide and Asset Information Models (AIM): Creation and Management. For the requirements, continue with Asset Information Requirements (AIR): Complete Guide, and for connecting data to maintenance, BIM and Computerized Maintenance Management Systems (CMMS).

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.