BIM Issue Tracking and Resolution Using BCF

BIM Issue Tracking and Resolution Using BCF

Before BCF, the standard way to report a model problem was to take a screenshot, paste it into an email, circle the problem in red and write: “Please fix.” Multiply that by five hundred issues, twenty people and six different software tools, and you have the original coordination problem in its purest form. Each email was clear to its writer and ambiguous to its reader. Each screenshot showed a view that nobody could reproduce. Each answer was a reply to a thread that someone else had forked. When I asked a project team once how many open issues they had, the answer was: “We would have to search our inboxes.” That is not issue management. That is archaeology.

BIM Collaboration Format (BCF) was created to end it. BCF is an open standard that lets issues travel between different software tools: each issue carries a title, a description, a status, an assignee, a viewpoint (the camera position and the visible and selected elements) and comments, and any BCF-capable tool can open it, show the view and let the user respond. It does not matter whether the issue was raised in a federation tool, a model checker or an authoring tool, or whether the recipient uses a different one. The issue keeps its context.

This guide explains how to track and resolve issues using BCF. It covers the main ideas of BCF (the file format and the API), how an issue is structured, a lifecycle with statuses, good practice for writing, assigning, resolving and verifying issues, integrating BCF with clash detection, model checking and meetings, organizing the issue register, metrics and common mistakes. For the standard itself, see BIM Collaboration Format (BCF): The Complete Guide; this guide focuses on how to run an issue process with it.


The Short Answer

An effective issue process turns each problem into a tracked topic with a view, an owner, a due date and a status that moves through a defined lifecycle until it is verified and closed.

The life of an issue

StageMeaning
OpenIssue created with a viewpoint and a clear description
AssignedAn owner accepts responsibility
In progressThe fix is being made in the source model
ResolvedThe owner says it is done
VerifiedThe coordinator confirms in the new model
ClosedRecorded with the reason and date

In one sentence:

A good issue is clear on its own: anyone can open it, see the problem, know who owns it and know when it is done.


What BCF Provides

BCF is maintained by buildingSMART. It exists in two main forms.

FormWhat it isTypical use
BCF-XMLA file format (zipped XML) for exchanging issues (“topics”) between tools. Versions 2.1 and 3.0 existSending issues between desktop tools; archiving; offline exchange
BCF-APIA web API specification (version 3.0) for creating, reading and updating issues on a serverCloud platforms, integrations and automated workflows

Both rely on the same idea: a topic with metadata, comments, and one or more viewpoints. Support in software varies, and different tools and versions may implement different parts, so test the exchange in your toolchain before relying on it. BCF also forms part of the openCDE concept, in which BCF-API is one of the APIs used to connect platforms. See BIM Collaboration Format (BCF): The Complete Guide and openBIM Explained: Principles, Standards, and Benefits.


Anatomy of a Good Issue

FieldPurposeGood practice
TitleQuick identificationShort, specific, with location and kind: “L3 west corridor: chilled water vs supply duct (H)”
DescriptionThe problem, the requirement and the proposed decisionState what is wrong, why it matters and what decision is needed
Type or kindClassificationHard, clearance, workflow, information, missing; see Hard Clashes vs. Soft Clashes vs. Workflow Clashes
PriorityImportanceBy consequence, not by count
StatusLifecycle stateFrom the agreed list
AssigneeWho must actA person or role, never “everyone”
Due dateWhenAligned with the next cycle or milestone
Viewpoint(s)The camera and visible and selected elementsClear view of the problem, with relevant elements isolated or highlighted
Referenced elementsIdentifiers of the elements involvedSo the assignee can find them in the native model
CommentsDiscussion and updatesConcise, factual, dated
Labels or tagsFilteringDiscipline, level, zone, system
LinksTo documents, specifications, previous issuesContext
Creation and modification metadataAudit trailAutomatic

What Makes an Issue Clear

WeakStrong
Title: “Clash.”Title: “L3 W corridor: CHW main vs supply duct (H, 84 results).”
“Please fix.”“Decision needed: CHW main moves below supply duct with revised hangers. Mechanical to update model by Friday; structure not affected.”
A screenshot without elementsA viewpoint with isolated systems and element identifiers
Assigned to “MEP”Assigned to the mechanical modeling lead, with the coordinator as reviewer

Choosing Statuses

Keep the list short and defined. The sequence below is a common starting point.

StatusDefinitionWho sets it
OpenCreated; not yet acceptedCreator
AssignedOwner has acceptedOwner or coordinator
In progressWork underwayOwner
ResolvedOwner states the fix is made in the source modelOwner
VerifiedCoordinator confirms in a later modelCoordinator
ClosedIssue completed; record keptCoordinator
Rejected / not an issueOwner or reviewer explains why no action is neededReviewer, with reason
DeferredDecision postponed with date and reasonCoordinator
ReopenedProblem persists or recursCoordinator

Rules

  • Only the right role can set certain statuses: for example, only the coordinator can verify and close.
  • A reason is required for rejection, deferral and approval of deviations.
  • Statuses are not decoration: they drive dashboards and decisions.

BCF supports configurable statuses, priorities and labels through its extension mechanisms, so you can align it with your process. Agree the list in the BEP and set up the platform accordingly.


Running the Process

Creating Issues

SourceHow
Clash detection resultsGroup clashes by cause; create one issue per decision with a viewpoint. See BIM Clash Detection: The Complete Guide
Model checking resultsGroup findings by rule or cause; create issues for items that need action. See BIM Model Checking: Geometric and Information Validation
Design reviewsReviewers create issues with viewpoints during walkthroughs
Authoring usersRaise issues from within the modeling tool when they find a problem in another discipline’s model
Site and constructionRaise issues from site observations with photos and viewpoints
Audit findingsConvert significant findings into issues

Assigning

  • Assign to the party who owns the element or the decision.
  • If ownership is unclear, assign to the coordinator to establish it quickly.
  • Add a reviewer where design approval is needed (for example an engineer).
  • Set a due date based on the cycle, not “as soon as possible”.

Responding and Resolving

StepPractice
AcknowledgeAccept the assignment quickly, or reject with a reason
AnalyzeDecide the fix; check design implications; consult others if needed
Fix at the sourceUpdate the native model. See How to Identify and Fix BIM Model Errors
CommentState what was done and in which model revision
Set ResolvedOnly when the change is in the shared model, not only intended

Verifying and Closing

The coordinator re-runs tests or checks the updated model. If the fix is confirmed, set Verified, then Closed with a short reason. If not, Reopen with a comment and a viewpoint.

Escalating

Define escalation rules: for example, issues open beyond the due date are escalated to the discipline manager; issues beyond two cycles to the design or project manager.


Integrating BCF With the Rest of Coordination

IntegrationHow
Clash detection toolsExport grouped clash results as BCF topics, or create issues directly; keep traceability between results and issues
Model checkersSame: findings as topics
Authoring toolsOpen BCF topics to jump to the viewpoint and elements; fix; update status
Federation viewersReview viewpoints and comment
CDEStore BCF files or connect via API; record issues with the CDE status and revision. See Common Data Environment (CDE): The Complete Guide
MeetingsReport from the tracker; update live in meetings. See BIM Coordination Meetings: Planning, Reporting, and Best Practices
DashboardsMetrics from the tracker

Round-Tripping Cautions

Different tools may interpret viewpoints, element identifiers and comments differently. Test round trips (create in tool A, open in tool B, update, return) with your actual tools. Typical problems include lost viewpoints, mismatched element identifiers after model updates and statuses that do not map. Agree element identification (for example by stable global identifiers) so that issues continue to point at the right elements after model changes.


Organizing the Issue Register

PracticeBenefit
Naming convention for titlesSort and search; include location and kind
Consistent labelsFilter by discipline, level, zone, system, kind
One issue, one decisionAvoid multi-problem threads
Link duplicatesMerge or reference duplicates
Archive closed issuesKeep the record; keep the working list short
Backup and exportPeriodic BCF exports for the archive and for portability
RetentionFollow the project’s information retention rules. See BIM Information Security, Access Control, and Data Governance
Reporting viewsStandard filters: open by owner, overdue, by priority, by zone

Metrics From the Tracker

MetricWhat it shows
Open issues by status, priority and ownerWorkload and bottlenecks
Age of open issuesResponsiveness
Time from creation to assignment, resolution, verificationProcess speed
Issues opened and closed per cycleConvergence
Reopened issuesQuality of fixes and verification
Issues by kind and disciplineWhere problems arise
Overdue issuesFollow-through
Issues escalatedDecision problems

Use these to improve the process, not to rank people. See How to Measure BIM Performance, ROI, and Project Success.


Special Uses

UseNotes
Design review and client commentsReviewers create BCF topics with viewpoints; designers respond
Site queries and RFIsLink queries to model elements and views; respond with decisions and updated information
Snagging and handoverDefects as topics with locations; track closure
Authority commentsRecord and respond to approvals comments linked to model views
Model quality findingsAudit and checking findings tracked to closure
Lessons learnedTag issues that reveal systemic problems

Common Problems and Remedies

ProblemCauseRemedy
Issues unclearPoor titles; no viewpointsTemplates; examples; training
Thousands of issuesOne issue per raw clashOne issue per decision; grouping
Nobody respondsUnclear assignment; no due datesNamed assignee; due dates; escalation
Issues marked resolved but not fixedNo verificationVerification step by the coordinator
Viewpoints breakModels updated; identifiers changedStable identifiers; recreate viewpoints for changed elements
Tools do not exchange properlyDifferent BCF versions or implementationsTest; agree a version and settings
Statuses inconsistentNo agreed listDefine in the BEP; configure platform
Email still usedNo habit or trainingMake the tracker the single source; stop answering email issues
Issues lost at the endNo archiveExport and archive

Common Mistakes

  1. Issues without viewpoints or elements.
  2. One issue per raw clash.
  3. No named assignee or due date.
  4. Too many statuses, or undefined ones.
  5. Anyone can close issues.
  6. No verification.
  7. Not testing BCF between tools.
  8. Email alongside the tracker.
  9. No escalation rules.
  10. No archive of closed issues.
  11. Metrics used to blame.
  12. No link between issues and decisions.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we agreed statuses, priorities, labels and roles in the BEP?
  2. Does every issue have a clear title, description, viewpoint, referenced elements, assignee and due date?
  3. Is one issue equal to one decision?
  4. Is the process (create, assign, fix at source, resolve, verify, close) followed?
  5. Is escalation defined?
  6. Have we tested BCF exchange between our tools?
  7. Are element identifiers stable enough for issues to survive model updates?
  8. Are clash and checking results converted into grouped issues?
  9. Are metrics used for process improvement?
  10. Are closed issues archived and exported?

Frequently Asked Questions

What is BCF?

BIM Collaboration Format, an open buildingSMART standard for exchanging issues between software tools, with viewpoints, comments, statuses and assignments.

What is the difference between BCF-XML and BCF-API?

BCF-XML is a file format for exchanging issues; BCF-API is a web interface for managing issues on a server.

What should a BCF issue contain?

A clear title, description, type, priority, status, assignee, due date, viewpoint, referenced elements and comments.

How many statuses should I use?

As few as you need: typically open, assigned, in progress, resolved, verified and closed, with rejected and deferred where useful.

Who should close an issue?

The coordinator or reviewer, after verifying the fix in the updated model.

Can issues be exchanged between different software?

Yes, if both support BCF, but implementations vary. Test the exchange in your tools.

How do I link clash results to issues?

By grouping results into issues with viewpoints and references, creating topics from the clash tool or exporting to BCF.

Should I still use email for issues?

No. Use the tracker as the single source of truth, and use email only for notifications.


Final Thoughts

The team that had to search their inboxes eventually adopted a single rule: if it is not in the tracker, it does not exist. For two weeks, the coordinator answered every emailed issue with a polite message: “Please raise this in the tracker.” People grumbled. Then someone raised an issue with a good viewpoint, and the owner opened it directly in the modeling tool, jumped to the elements, fixed the problem and set the status in two minutes. After that, the grumbling stopped.

BCF does not make coordination easier by magic. It makes the context travel: the view, the elements, the owner, the status, the history. Combine that with a short lifecycle, one issue per decision, verification before closure and a few metrics, and you have an issue process that people trust, which is the only kind they will use.

Where to go next: for the standard in depth, read BIM Collaboration Format (BCF): The Complete Guide. For generating issues, continue with BIM Clash Detection: The Complete Guide and BIM Model Checking: Geometric and Information Validation, and for using them in meetings, BIM Coordination Meetings: Planning, Reporting, and Best Practices.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.