The worst clash report I ever received was a spreadsheet of 4,812 rows. Each row had an ID, two element names, a distance and a status that read “New.” There was no summary, no grouping, no indication of which rows mattered, no names beside any of them and no mention of which models, versions or tolerances had been used. I was the mechanical coordinator, and I stared at it for some time, trying to decide what, if anything, I was being asked to do. The report was accurate in every cell and useless as a whole. It was a data dump, not a report.
A good clash report is the opposite: short, structured and aimed at decisions. It tells the reader what was tested (and what was not), how the situation has changed since the last cycle, which issues matter most, who must act and by when. It carries enough evidence (viewpoints, element identifiers, locations) for the owner to find the problem in thirty seconds. It leaves a trail so that, weeks later, anyone can see what was found, what was decided and when it was closed. The report is the interface between the clash software and the people, and its quality determines whether the software’s output turns into fixed models.
This guide provides a clash detection report template with instructions for each section, a step-by-step method for producing it from any clash tool, a grouping and prioritization approach, a worked fictional example for the invented Harbor View Clinic, distribution and follow-up practices, metrics and the mistakes to avoid. It works with BIM Clash Detection: The Complete Guide, How to Create a BIM Clash Detection Matrix, Navisworks Clash Detection: Step-by-Step Guide and BIM Coordination Meeting Checklist and Report Template. A clash report reports what was tested. It does not prove that a design is free of problems.
Free Download
Download: BIM clash detection report template (ZIP with Word file)
The download is a ZIP archive containing a Word document with every section of the clash report, from scope and summary to priority issues, exceptions and limits. It is free to use and adapt for your own projects. Adapt it to your contract, client requirements and standards; it supports professional judgment and is not legal advice.
The Short Answer

| Part | Content |
|---|---|
| Header | Project, date, cycle, models and versions |
| Scope | Tests, tolerances, rules and exclusions |
| Summary | Counts by status, trend and top groups |
| Issues | Grouped by cause, location and owner |
| Evidence | Viewpoints, images and element identifiers |
| Actions | Owner, decision needed and due date |
| Verification | Re-test results and closure |
| Limits | What was not tested |
In one sentence:
A clash report turns raw test results into grouped, owned, evidenced issues with decisions needed, and records what was and was not tested.
How to Produce the Report: Step by Step
| Step | Action |
|---|---|
| 1. Confirm the inputs | Models, versions, statuses, alignment verified; clash matrix and tolerances agreed. See How to Create a BIM Clash Detection Matrix |
| 2. Run the tests | By matrix, with recorded settings; keep the project file |
| 3. Sanity-check the results | Counts plausible; no systematic error (misalignment, missing tolerance, empty set) |
| 4. Compare with the previous cycle | New, active (still open), resolved (no longer found) |
| 5. Group the results | By cause, location, system pair and owner; one issue per decision |
| 6. Prioritize | Safety and structure first; then program and cost impact; then convenience |
| 7. Prepare evidence | A viewpoint per issue; element identifiers; a short description |
| 8. Create or update issues | In the tracker, linked to groups, with owners and due dates. See BIM Issue Tracking and Resolution Using BCF |
| 9. Write the report | Header, scope, summary, issues, limits |
| 10. Review before sending | A second pair of eyes; check owners and dates |
| 11. Distribute | To owners, project team and (summary) management |
| 12. Follow up and verify | At the next cycle: re-test; close with evidence |
The Template
Header
| Field | Content |
|---|---|
| Project | [Harbor View Clinic] |
| Report title and number | [Clash report, cycle 14] |
| Date and author | [Date; coordinator name] |
| Cycle and period | [Cycle 14, 1 to 8 March] |
| Distribution | [Team list; CDE location] |
Section 1: Scope
1.1 Models Tested
| Model | Author | Version | Status | Date received | Alignment verified |
|---|---|---|---|---|---|
| [Architecture] | [ARC] | [v14] | [S1] | [Date] | [Yes] |
| [Structure] | [STR] | [v13] | [S1] | [Date] | [Yes] |
| [MEP] | [MEP] | [v14] | [S1] | [Date] | [Yes, after correction] |
1.2 Tests Run
| Test | Selection A | Selection B | Type | Tolerance | Rules applied |
|---|---|---|---|---|---|
| [T01] | [Structure frame] | [Supply ducts] | [Hard] | [10 mm] | [Ignore same-file items] |
| [T02] | [Ducts] | [Sprinkler pipes] | [Hard] | [10 mm] | |
| [T03] | [Equipment] | [Architecture] | [Clearance] | [600 mm access] |
1.3 Exclusions and Assumptions
| Item | Detail |
|---|---|
| Not modeled or not tested | [Hangers and supports; insulation not modeled in MEP v14] |
| Zones excluded | [Level R plant room pending equipment selection] |
| Assumptions | [Tolerances per the matrix; models at the information level for developed design] |
Section 2: Summary
| Item | Content |
|---|---|
| Headline | [Three sentences: overall situation; main risks; what is needed] |
2.1 Counts by Status
| Status | Previous cycle | This cycle | Change |
|---|---|---|---|
| New (found for the first time) | |||
| Active (found before, still open) | |||
| Resolved (not found now) | |||
| Reviewed or approved (accepted exceptions) | |||
| Total open groups |
2.2 Trend
| Metric | Cycle 12 | Cycle 13 | Cycle 14 |
|---|---|---|---|
| Raw clash count | |||
| Open issue groups | |||
| Average age of open groups (days) | |||
| Groups resolved |
Section 3: Priority Issues
For each priority issue, one block:
| Field | Content |
|---|---|
| Issue ID and group | [CI-031; Group G-07] |
| Title | [Supply duct crosses primary beam, level 2 corridor] |
| Location | [Grid C to D, level 2; coordinates] |
| Systems and elements | [Supply air duct SA-203 and beam B-2C-14; element identifiers] |
| Number of raw clashes in the group | [12] |
| Cause | [Duct route ignores beam depth; no sleeve agreed] |
| Impact | [Prevents ceiling build-up at corridor; program risk for services first fix] |
| Decision needed | [Reroute duct below beam, or approve a structural opening] |
| Options | [A: lower duct by 200 mm and reduce ceiling height; B: sleeve through web, subject to structural approval] |
| Owner | [MEP lead (action); structural engineer (consulted)] |
| Due date | [Date] |
| Evidence | [Viewpoint link; image] |
| Status | [Open] |
Section 4: Other Groups and Observations
| ID | Title | Location | Owner | Due | Status |
|---|---|---|---|---|---|
| [CI-032] | [Fire damper access] | [L1] | [MEP] | [Date] | [Open] |
Section 5: Resolved and Verified Since Last Cycle
| ID | Title | Resolved by | Verified how | Date |
|---|---|---|---|---|
| [CI-020] | [Pipe vs slab edge] | [MEP] | [Re-test: no result in T02; viewed in model] | [Date] |
Section 6: Accepted Exceptions
| ID | Description | Reason accepted | Approved by | Date |
|---|---|---|---|---|
| [CI-011] | [Pipe touches ceiling hanger, tolerance exceeded by 3 mm] | [No functional impact; confirmed by contractor] | [Coordinator and MEP lead] | [Date] |
Section 7: Limits of This Report
| Limit | Statement |
|---|---|
| Coverage | [The report covers only the tests in Section 1.2] |
| Model maturity | [Results reflect model content at the date received] |
| Tolerance | [Clashes below the tolerance are not reported] |
| Interpretation | [Clash tests identify geometric conflicts; they do not assess design adequacy, safety or compliance] |
Section 8: Next Steps
| Item | Date |
|---|---|
| [Next model cut-off] | [Date] |
| [Next clash run] | [Date] |
| [Next coordination meeting] | [Date] |
Appendices
| Appendix | Content |
|---|---|
| A | Full test list and settings |
| B | Clash matrix |
| C | Complete issue list (export) |
| D | Viewpoint index |
Grouping and Prioritizing
| Technique | How |
|---|---|
| Group by cause | Many raw clashes share one cause (for example a duct crossing a row of beams) |
| Group by location | A corridor, a riser, a plant room |
| Group by system pair | Chilled water against sprinklers |
| Group by element | One pipe against many hangers |
| Group by owner | The party who must act |
| One group, one decision | If it needs two decisions, split it |
A Simple Priority Scheme
| Priority | Criteria | Response |
|---|---|---|
| P1 Critical | Structural integrity, life safety, fire compartmentation, major program risk | Resolve this cycle; escalate if blocked |
| P2 High | Prevents installation or access; significant cost or program impact | Resolve within two cycles |
| P3 Medium | Affects clearances, maintenance or finishes | Resolve before the stage gate |
| P4 Low | Minor, cosmetic or tolerance-level | Resolve when convenient or accept as exception |
Prioritize by consequence, not by the number of raw clashes.
A Worked Illustration (Fictional)
Cycle 14 of the Harbor View Clinic returns 412 raw clashes across three tests. After alignment and tolerance checks and the removal of same-file items, 318 remain. Grouping by cause and location produces 27 issue groups. (Arithmetic: 412 − 94 removed = 318 raw clashes carried forward; 318 raw clashes in 27 groups is an average of 318 ÷ 27 ≈ 11.8 raw clashes per group.) The report presents five priority groups (P1 and P2) for decision in the meeting, lists the other 22 groups in a table for offline resolution and notes that 94 raw clashes were excluded by documented rules. The reader sees five decisions, not 412 problems. (Figures are invented for illustration.)
Distribution and Follow-up
| Practice | Why |
|---|---|
| Send a short summary to management and the full report to owners | Different audiences |
| Link issues in the tracker | Owners work in the tracker, not the report |
| Share viewpoints | Fast orientation |
| Publish the report in the CDE | One source |
| State the response time expected | Expectation |
| Review at the coordination meeting | Decisions |
| Chase between meetings | Do not wait |
| Verify fixes in the next run | Re-test |
| Archive the report and the test file | Record |
Metrics from the Report
| Metric | Use |
|---|---|
| Open groups and age | Whether hard issues are being resolved |
| New versus resolved per cycle | Flow |
| Raw clashes per thousand elements (or per area) | Model maturity |
| First-time resolution rate | Quality of fixes |
| Issues by discipline and cause | Where to improve |
| Share of clashes caused by late or misaligned models | Process quality |
| Exceptions accepted | Control |
See BIM Data Analytics: Dashboards, KPIs, and Automated Reporting.
Tool-Specific Notes
The template is tool-independent. In practice:
| Tool type | Notes |
|---|---|
| Desktop clash tools | Export reports and viewpoints; group results; use statuses (new, active, reviewed, approved, resolved) to track progress; save the project file with settings. See Navisworks Clash Detection: Step-by-Step Guide |
| Rule-based checkers | Clash results with matrix and responsibilities; BCF export. See Solibri: BIM Model Checking and Validation Guide |
| Cloud and coordination platforms | Automatic tests and issues; check how results are exported. See Revizto: BIM Coordination and Issue Management Guide and Autodesk Construction Cloud: BIM Collaboration and Data Management |
| BCF-based tools | Create issues with viewpoints and exchange them across tools. See BIMcollab: BCF-Based Coordination and Issue Tracking |
Whatever the tool, record the settings so that the next run is comparable.
Common Mistakes
- Sending raw clash exports as the report.
- No record of models, versions and tolerances.
- Reporting counts without grouping.
- No owners or due dates.
- No priorities.
- Treating every clash as equal.
- No evidence (viewpoints, identifiers).
- Hiding exclusions and limits.
- Closing groups without verification.
- No trend or comparison with the previous cycle.
- Too long to read.
- Reports that nobody acts on.
See also Common BIM Mistakes Beginners Should Avoid.
A Short Checklist
- Are models, versions, statuses and alignment recorded?
- Are tests, tolerances, rules and exclusions listed?
- Did we sanity-check the results?
- Are results grouped by cause, location and owner, with priorities?
- Does each priority issue have evidence, a decision needed, options, owner and date?
- Does the report show trend and changes since last cycle?
- Are exceptions, resolved items and limits documented?
- Are issues in the tracker and the report distributed?
- Will we verify fixes in the next run?
Frequently Asked Questions
What should a clash report include?
Models and versions, tests and tolerances, a summary with trends, grouped priority issues with evidence, owners and dates, exceptions, limits and next steps.
How long should a clash report be?
One to three pages for the main body, with appendices for detail.
Should I send the full list of clashes?
Provide it as an appendix or export; the report should present grouped issues and decisions.
How do I decide which issues are priorities?
By consequence: safety and structure, then program and cost, then convenience.
What is the difference between a clash and an issue?
A clash is a raw test result; an issue is a decision-oriented grouping of one or more clashes with an owner and action.
Should I include accepted exceptions?
Yes, with reasons and approvals, so the record is complete.
How often should I issue the report?
Every coordination cycle.
Does a clean clash report mean the design is correct?
No. It means the tested conflicts were resolved; many aspects of design adequacy are untested.
Final Thoughts
A coordinator I admire has a rule that governs her reports: “Every page must change what someone does on Monday.” She cuts any paragraph that merely describes. A summary line reading “Open groups fell from 31 to 27” is allowed only if the next line says what remains blocked and who must act. A table of clash counts by test is allowed only if it supports a decision about which test to change. Her reports are two pages, her appendices are long and her meetings are short. “The software finds the clashes,” she says. “My job is to decide what the clashes mean for people.”
Use the template to bring that discipline: record what you tested, show what changed, group and prioritize, give each issue an owner and a date, state what you did not test and verify before you close. The report will then do what it exists to do: carry the software’s findings across the gap between a screen and a decision.
Download the template: BIM clash detection report template (ZIP with Word file).
Where to go next: for the process, read BIM Clash Detection: The Complete Guide and How to Create a BIM Clash Detection Matrix. For the meeting that uses the report, continue with BIM Coordination Meeting Checklist and Report Template, and for the tool, Navisworks Clash Detection: Step-by-Step Guide.