BIM Clash Detection Report Template and Instructions

BIM Clash Detection Report Template and Instructions

The worst clash report I ever received was a spreadsheet of 4,812 rows. Each row had an ID, two element names, a distance and a status that read “New.” There was no summary, no grouping, no indication of which rows mattered, no names beside any of them and no mention of which models, versions or tolerances had been used. I was the mechanical coordinator, and I stared at it for some time, trying to decide what, if anything, I was being asked to do. The report was accurate in every cell and useless as a whole. It was a data dump, not a report.

A good clash report is the opposite: short, structured and aimed at decisions. It tells the reader what was tested (and what was not), how the situation has changed since the last cycle, which issues matter most, who must act and by when. It carries enough evidence (viewpoints, element identifiers, locations) for the owner to find the problem in thirty seconds. It leaves a trail so that, weeks later, anyone can see what was found, what was decided and when it was closed. The report is the interface between the clash software and the people, and its quality determines whether the software’s output turns into fixed models.

This guide provides a clash detection report template with instructions for each section, a step-by-step method for producing it from any clash tool, a grouping and prioritization approach, a worked fictional example for the invented Harbor View Clinic, distribution and follow-up practices, metrics and the mistakes to avoid. It works with BIM Clash Detection: The Complete Guide, How to Create a BIM Clash Detection Matrix, Navisworks Clash Detection: Step-by-Step Guide and BIM Coordination Meeting Checklist and Report Template. A clash report reports what was tested. It does not prove that a design is free of problems.


Free Download

Download: BIM clash detection report template (ZIP with Word file)

The download is a ZIP archive containing a Word document with every section of the clash report, from scope and summary to priority issues, exceptions and limits. It is free to use and adapt for your own projects. Adapt it to your contract, client requirements and standards; it supports professional judgment and is not legal advice.


The Short Answer

Anatomy of a clash report

PartContent
HeaderProject, date, cycle, models and versions
ScopeTests, tolerances, rules and exclusions
SummaryCounts by status, trend and top groups
IssuesGrouped by cause, location and owner
EvidenceViewpoints, images and element identifiers
ActionsOwner, decision needed and due date
VerificationRe-test results and closure
LimitsWhat was not tested

In one sentence:

A clash report turns raw test results into grouped, owned, evidenced issues with decisions needed, and records what was and was not tested.


How to Produce the Report: Step by Step

StepAction
1. Confirm the inputsModels, versions, statuses, alignment verified; clash matrix and tolerances agreed. See How to Create a BIM Clash Detection Matrix
2. Run the testsBy matrix, with recorded settings; keep the project file
3. Sanity-check the resultsCounts plausible; no systematic error (misalignment, missing tolerance, empty set)
4. Compare with the previous cycleNew, active (still open), resolved (no longer found)
5. Group the resultsBy cause, location, system pair and owner; one issue per decision
6. PrioritizeSafety and structure first; then program and cost impact; then convenience
7. Prepare evidenceA viewpoint per issue; element identifiers; a short description
8. Create or update issuesIn the tracker, linked to groups, with owners and due dates. See BIM Issue Tracking and Resolution Using BCF
9. Write the reportHeader, scope, summary, issues, limits
10. Review before sendingA second pair of eyes; check owners and dates
11. DistributeTo owners, project team and (summary) management
12. Follow up and verifyAt the next cycle: re-test; close with evidence

The Template

Header

FieldContent
Project[Harbor View Clinic]
Report title and number[Clash report, cycle 14]
Date and author[Date; coordinator name]
Cycle and period[Cycle 14, 1 to 8 March]
Distribution[Team list; CDE location]

Section 1: Scope

1.1 Models Tested

ModelAuthorVersionStatusDate receivedAlignment verified
[Architecture][ARC][v14][S1][Date][Yes]
[Structure][STR][v13][S1][Date][Yes]
[MEP][MEP][v14][S1][Date][Yes, after correction]

1.2 Tests Run

TestSelection ASelection BTypeToleranceRules applied
[T01][Structure frame][Supply ducts][Hard][10 mm][Ignore same-file items]
[T02][Ducts][Sprinkler pipes][Hard][10 mm]
[T03][Equipment][Architecture][Clearance][600 mm access]

1.3 Exclusions and Assumptions

ItemDetail
Not modeled or not tested[Hangers and supports; insulation not modeled in MEP v14]
Zones excluded[Level R plant room pending equipment selection]
Assumptions[Tolerances per the matrix; models at the information level for developed design]

Section 2: Summary

ItemContent
Headline[Three sentences: overall situation; main risks; what is needed]

2.1 Counts by Status

StatusPrevious cycleThis cycleChange
New (found for the first time)
Active (found before, still open)
Resolved (not found now)
Reviewed or approved (accepted exceptions)
Total open groups

2.2 Trend

MetricCycle 12Cycle 13Cycle 14
Raw clash count
Open issue groups
Average age of open groups (days)
Groups resolved

Section 3: Priority Issues

For each priority issue, one block:

FieldContent
Issue ID and group[CI-031; Group G-07]
Title[Supply duct crosses primary beam, level 2 corridor]
Location[Grid C to D, level 2; coordinates]
Systems and elements[Supply air duct SA-203 and beam B-2C-14; element identifiers]
Number of raw clashes in the group[12]
Cause[Duct route ignores beam depth; no sleeve agreed]
Impact[Prevents ceiling build-up at corridor; program risk for services first fix]
Decision needed[Reroute duct below beam, or approve a structural opening]
Options[A: lower duct by 200 mm and reduce ceiling height; B: sleeve through web, subject to structural approval]
Owner[MEP lead (action); structural engineer (consulted)]
Due date[Date]
Evidence[Viewpoint link; image]
Status[Open]

Section 4: Other Groups and Observations

IDTitleLocationOwnerDueStatus
[CI-032][Fire damper access][L1][MEP][Date][Open]

Section 5: Resolved and Verified Since Last Cycle

IDTitleResolved byVerified howDate
[CI-020][Pipe vs slab edge][MEP][Re-test: no result in T02; viewed in model][Date]

Section 6: Accepted Exceptions

IDDescriptionReason acceptedApproved byDate
[CI-011][Pipe touches ceiling hanger, tolerance exceeded by 3 mm][No functional impact; confirmed by contractor][Coordinator and MEP lead][Date]

Section 7: Limits of This Report

LimitStatement
Coverage[The report covers only the tests in Section 1.2]
Model maturity[Results reflect model content at the date received]
Tolerance[Clashes below the tolerance are not reported]
Interpretation[Clash tests identify geometric conflicts; they do not assess design adequacy, safety or compliance]

Section 8: Next Steps

ItemDate
[Next model cut-off][Date]
[Next clash run][Date]
[Next coordination meeting][Date]

Appendices

AppendixContent
AFull test list and settings
BClash matrix
CComplete issue list (export)
DViewpoint index

Grouping and Prioritizing

TechniqueHow
Group by causeMany raw clashes share one cause (for example a duct crossing a row of beams)
Group by locationA corridor, a riser, a plant room
Group by system pairChilled water against sprinklers
Group by elementOne pipe against many hangers
Group by ownerThe party who must act
One group, one decisionIf it needs two decisions, split it

A Simple Priority Scheme

PriorityCriteriaResponse
P1 CriticalStructural integrity, life safety, fire compartmentation, major program riskResolve this cycle; escalate if blocked
P2 HighPrevents installation or access; significant cost or program impactResolve within two cycles
P3 MediumAffects clearances, maintenance or finishesResolve before the stage gate
P4 LowMinor, cosmetic or tolerance-levelResolve when convenient or accept as exception

Prioritize by consequence, not by the number of raw clashes.

A Worked Illustration (Fictional)

Cycle 14 of the Harbor View Clinic returns 412 raw clashes across three tests. After alignment and tolerance checks and the removal of same-file items, 318 remain. Grouping by cause and location produces 27 issue groups. (Arithmetic: 412 − 94 removed = 318 raw clashes carried forward; 318 raw clashes in 27 groups is an average of 318 ÷ 27 ≈ 11.8 raw clashes per group.) The report presents five priority groups (P1 and P2) for decision in the meeting, lists the other 22 groups in a table for offline resolution and notes that 94 raw clashes were excluded by documented rules. The reader sees five decisions, not 412 problems. (Figures are invented for illustration.)


Distribution and Follow-up

PracticeWhy
Send a short summary to management and the full report to ownersDifferent audiences
Link issues in the trackerOwners work in the tracker, not the report
Share viewpointsFast orientation
Publish the report in the CDEOne source
State the response time expectedExpectation
Review at the coordination meetingDecisions
Chase between meetingsDo not wait
Verify fixes in the next runRe-test
Archive the report and the test fileRecord

Metrics from the Report

MetricUse
Open groups and ageWhether hard issues are being resolved
New versus resolved per cycleFlow
Raw clashes per thousand elements (or per area)Model maturity
First-time resolution rateQuality of fixes
Issues by discipline and causeWhere to improve
Share of clashes caused by late or misaligned modelsProcess quality
Exceptions acceptedControl

See BIM Data Analytics: Dashboards, KPIs, and Automated Reporting.


Tool-Specific Notes

The template is tool-independent. In practice:

Tool typeNotes
Desktop clash toolsExport reports and viewpoints; group results; use statuses (new, active, reviewed, approved, resolved) to track progress; save the project file with settings. See Navisworks Clash Detection: Step-by-Step Guide
Rule-based checkersClash results with matrix and responsibilities; BCF export. See Solibri: BIM Model Checking and Validation Guide
Cloud and coordination platformsAutomatic tests and issues; check how results are exported. See Revizto: BIM Coordination and Issue Management Guide and Autodesk Construction Cloud: BIM Collaboration and Data Management
BCF-based toolsCreate issues with viewpoints and exchange them across tools. See BIMcollab: BCF-Based Coordination and Issue Tracking

Whatever the tool, record the settings so that the next run is comparable.


Common Mistakes

  1. Sending raw clash exports as the report.
  2. No record of models, versions and tolerances.
  3. Reporting counts without grouping.
  4. No owners or due dates.
  5. No priorities.
  6. Treating every clash as equal.
  7. No evidence (viewpoints, identifiers).
  8. Hiding exclusions and limits.
  9. Closing groups without verification.
  10. No trend or comparison with the previous cycle.
  11. Too long to read.
  12. Reports that nobody acts on.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Are models, versions, statuses and alignment recorded?
  2. Are tests, tolerances, rules and exclusions listed?
  3. Did we sanity-check the results?
  4. Are results grouped by cause, location and owner, with priorities?
  5. Does each priority issue have evidence, a decision needed, options, owner and date?
  6. Does the report show trend and changes since last cycle?
  7. Are exceptions, resolved items and limits documented?
  8. Are issues in the tracker and the report distributed?
  9. Will we verify fixes in the next run?

Frequently Asked Questions

What should a clash report include?

Models and versions, tests and tolerances, a summary with trends, grouped priority issues with evidence, owners and dates, exceptions, limits and next steps.

How long should a clash report be?

One to three pages for the main body, with appendices for detail.

Should I send the full list of clashes?

Provide it as an appendix or export; the report should present grouped issues and decisions.

How do I decide which issues are priorities?

By consequence: safety and structure, then program and cost, then convenience.

What is the difference between a clash and an issue?

A clash is a raw test result; an issue is a decision-oriented grouping of one or more clashes with an owner and action.

Should I include accepted exceptions?

Yes, with reasons and approvals, so the record is complete.

How often should I issue the report?

Every coordination cycle.

Does a clean clash report mean the design is correct?

No. It means the tested conflicts were resolved; many aspects of design adequacy are untested.


Final Thoughts

A coordinator I admire has a rule that governs her reports: “Every page must change what someone does on Monday.” She cuts any paragraph that merely describes. A summary line reading “Open groups fell from 31 to 27” is allowed only if the next line says what remains blocked and who must act. A table of clash counts by test is allowed only if it supports a decision about which test to change. Her reports are two pages, her appendices are long and her meetings are short. “The software finds the clashes,” she says. “My job is to decide what the clashes mean for people.”

Use the template to bring that discipline: record what you tested, show what changed, group and prioritize, give each issue an owner and a date, state what you did not test and verify before you close. The report will then do what it exists to do: carry the software’s findings across the gap between a screen and a decision.

Download the template: BIM clash detection report template (ZIP with Word file).

Where to go next: for the process, read BIM Clash Detection: The Complete Guide and How to Create a BIM Clash Detection Matrix. For the meeting that uses the report, continue with BIM Coordination Meeting Checklist and Report Template, and for the tool, Navisworks Clash Detection: Step-by-Step Guide.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.