How to Create a BIM Clash Detection Matrix

How to Create a BIM Clash Detection Matrix

The most useful single sheet of paper I have ever put on a coordination room wall is a table with disciplines along both axes and a few letters in the cells. It took an afternoon to design. It prevented, over the following months, a great deal of argument, because it answered the question that every new team member and every new subcontractor asks sooner or later: “What exactly are we testing against what?” Without that sheet, the answer is always the same: “Everything, against everything.” And “everything against everything” is the quickest route to a clash report that nobody can use.

The mathematics alone explains the problem. If a federated model has eight groups of elements, there are twenty-eight different pairs to test. Add test types (hard, clearance, duplicates) and zones (levels, areas) and variations by stage, and a project can easily generate hundreds of potential tests. Most of them are pointless: no one needs to test the plumbing against the landscape model on a building’s third floor. A few are vital: structure against ducts, drainage against everything, fire protection against everything. The clash matrix is how you decide which tests exist, what each one is for and who owns the results.

This guide shows how to create one. It covers what a matrix is, how to define the groups, how to choose the pairs, how to set test types, tolerances and clearances, how to account for zones and stages, how to write the matrix as a living document and how to maintain it. It includes a template and worked examples. It supports BIM Clash Detection: The Complete Guide and BIM Coordination: The Complete Guide.


The Short Answer

A clash detection matrix is a table that defines which groups of model elements are tested against which, with the test type, tolerance, scope, stage, frequency and owner for each test.

A clash matrix (illustrative)

Element of the matrixWhat it decides
Groups (sets)What is tested: structural frame, ducts, pipes, trays, and so on
PairsWhich groups are tested against which
Test typeHard, clearance, duplicates or others
Tolerance and clearance valuesHow strict each test is
ScopeZones, levels or areas
Stage and frequencyWhen the test applies and how often it runs
OwnerWho reviews results and who resolves

In one sentence:

The matrix turns “check everything” into a deliberate list of questions, each with a purpose, a tolerance and an owner.


Why You Need a Matrix

Without a matrixWith a matrix
Tests are created ad hoc by whoever runs themTests are agreed and repeatable
Results vary between runs and between peopleResults are comparable across cycles
Disciplines do not know what will be testedDisciplines know in advance what is expected
Many pointless tests inflate resultsEach test has a purpose
Important tests are forgottenCritical interfaces are covered
Responsibility is unclearEach test has an owner
New team members have to guessThe matrix is a reference

A matrix is also a communication tool: it tells every party what the coordination expects of their model (what level of detail, which clearances, which categories).


Step 1: Define the Groups

What Is a Group?

A group (or set) is a collection of elements that behaves as a unit in tests: for example “all structural columns”, “all supply air ducts”, “all domestic water pipes”, “all cable trays”, “all sprinkler pipes”, “all fire-rated walls”. Groups should be defined by properties (category, system, discipline, level) so that they update when models change. See BIM Clash Detection: The Complete Guide on dynamic sets.

Grouping Principles

PrincipleReason
Group by what conflicts with whatPairs of groups should make sense
Separate systems that need different tolerances or rulesInsulated pipes versus bare pipes; large ducts versus small conduits
Separate structure by type where relevantBeams and slabs versus columns; walls versus slabs
Separate clearance volumesAccess zones, working space zones
Keep the number manageableTen to twenty groups is common on large projects; fewer on small ones
Name consistentlyDiscipline, system, element type

An Example List of Groups

IDGroupDefined by
S1Structural frame (columns, beams, slabs, walls)Structural model, structural categories
A1Architectural walls, floors, ceilings, doorsArchitectural model
A2Architectural shafts and rooms (for space checks)Spaces and shaft elements
H1Ducts and fittings (all systems)Mechanical model, duct categories
H2HVAC pipes and equipmentMechanical model, pipe and equipment categories
P1Drainage pipes (gravity)Plumbing model, drainage systems
P2Supply pipesPlumbing model, supply systems
E1Cable containmentElectrical model
E2Electrical equipment and boards with clearance volumesElectrical model
F1Sprinkler pipes and headsFire protection model
C1Clearance volumes (access, maintenance, working space)Any model with clearance objects
W1Façade elementsFaçade model

Step 2: Choose the Pairs

The Starting Point

Create a table with groups along both axes. Then, for each pair, ask three questions:

  1. Can these two groups conflict in a way that matters?
  2. Is it possible to resolve such a conflict by someone’s decision?
  3. Will the test produce results that are worth reviewing?

If the answer to any is “no”, leave the cell empty.

Typical Priority Pairs (Building Projects)

PairReason
Structure versus ducts, pipes, traysPenetrations through structure; supports; depths
Structure versus architectureColumns and walls; slabs and stairs; duplicates
Ducts versus pipes, trays, sprinklerSpace competition in voids
Drainage versus everythingDrainage has the least flexibility
Sprinkler versus everythingHead positions and pipe routes; obstructions
Services versus ceilings and architectureClear heights; reflected ceiling coordination
Equipment versus clearance volumesAccess and maintenance
Electrical equipment versus other servicesWorking space and segregation
Façade versus structureEdge conditions and fixings
Same group versus itselfDuplicates and self-overlap checks

Reducing the Number

  • Limit by zone: test only where groups coexist (for example plant rooms, risers, ceiling voids).
  • Limit by stage: do not test detail-level pairs at concept stage.
  • Combine pairs where results will be handled by the same people.
  • Drop pointless pairs. Be willing to say “we do not test this”.

Step 3: Define Test Types, Tolerances and Clearances

Test Types

TestUse
HardIntersections
Hard (conservative)Where missed intersections are a risk and false positives can be handled
ClearanceRequired distances and clearance volumes
DuplicatesSame element twice

Tolerances

For each test, state the tolerance and its meaning. The values below are illustrative placeholders; set yours with the disciplines.

TestTolerance (illustrative placeholder)Meaning
Hard, structure versus servicesSmall value agreed with structureOverlaps smaller than this are ignored
Hard, services versus servicesSmall value agreedSame
Clearance, insulated servicesInsulation thickness plus installation allowanceRequired distance
Clearance, access and maintenanceFrom manufacturer or codeRequired space
DuplicatesVery smallMatches within this are treated as duplicates

Where the Values Come From

SourceUsed for
Manufacturer data and installation manualsEquipment clearances
Design standards and codesWorking space, access, minimum distances
SpecificationsInsulation, supports, fire stopping
Installer practiceInstallation allowances
Project agreementModeling tolerance

Record the source of each value. See Hard Clashes vs. Soft Clashes vs. Workflow Clashes.


Step 4: Set Scope, Stage and Frequency

ColumnContent
Zone or scopeWhole building, a level, plant rooms, risers, corridors
StageConcept, developed design, technical design, trade coordination, pre-fabrication
FrequencyEvery cycle, milestone only, on demand
PreconditionsModels at the required level of information; clearance volumes present
ExclusionsKnown acceptable overlaps; temporary or placeholder objects

Link the stage to the level of information. Running a pair too early produces noise; too late loses the benefit. See BIM Project Planning: Milestones, Deliverables, and Coordination.


Step 5: Assign Owners and Resolution Rules

ColumnContent
ReviewerWho reviews the results (usually the coordinator)
Resolution ownerWho typically resolves (by priority rules or by default)
EscalationWho decides if the owners cannot agree
Approval authorityWho can approve a deviation (for example clearance deviations or penetrations)
NotesRules of thumb: “structure yields only with approval”; “drainage has priority”

Add the routing priorities to the matrix document. See MEP BIM Coordination: Identifying and Resolving Clashes.


A Template

IDSet ASet BTest typeTolerance and sourceScopeStageFrequencyReviewerResolution ownerNotes
T01S1 StructureH1 DuctsHardAgreed hard toleranceWhole buildingDeveloped to technical designEach cycleCoordinatorMechanical (with structure approval)Penetrations require approved openings
T02S1 StructureP1 DrainageHardAgreed hard toleranceWhole buildingDeveloped to technical designEach cycleCoordinatorPlumbing (with structure approval)Check falls and openings
T03H1 DuctsP1 DrainageHard and clearanceInsulation plus allowanceVoids and corridorsDeveloped design onwardEach cycleCoordinatorMechanical yields unless priority rule states otherwiseDrainage priority
T04F1 SprinklersAll servicesHard and clearancePer sprinkler designerCeiling voidsTechnical design onwardEach cycleCoordinator and sprinkler designerOwner of the obstructing elementObstruction rules by designer
T05E2 Electrical equipmentC1 Clearance volumesHardZeroElectrical roomsTechnical design onwardEach cycleCoordinatorOwner of intruding elementWorking space per code and manufacturer
T06H1 DuctsA1 CeilingsHard and clearanceCeiling zone allowanceCeiling zonesDeveloped design onwardEach cycleCoordinatorMechanical or architecture per zoningClear height
T07S1 StructureA1 ArchitectureHard and duplicatesAgreedWhole buildingAll stagesEach cycleCoordinatorStructure and architectureDuplicates between models
T08All modelsSelfDuplicatesVery smallWhole buildingAll stagesEach cycleCoordinatorModel ownerSame element in two places
T09W1 FaçadeS1 StructureHard and clearanceMovement allowancePerimeterTechnical design onwardMilestonesCoordinatorFaçade and structureFixings and edge conditions

The matrix image above is a compact overview; the table is the working document.


Making the Matrix Work

Publish It

Include it in the BEP or its appendix, and in the onboarding pack for each new party. Make sure each discipline knows which of its elements will be tested against what, and what level of detail they must provide.

Link It to the Models

  • Define sets in the coordination tool to match the groups, using properties that every model carries (system, category, level).
  • Agree parameters so that sets can be built reliably. See BIM Metadata, Attributes, and Property Sets Explained.
  • Test the matrix on a pilot model before the first official cycle.

Maintain It

PracticeReason
Version controlThe matrix changes; track versions
Review at each stageAdd detail-level tests when models mature
Review after surprisesA problem found on site means a missing test
Remove useless testsKeep the matrix lean
Record rule changesRules and tolerances affect comparability between cycles

Use It in Reports

Report results by matrix test: “T03: 12 open issues, 5 new, 7 active.” This lets you see which interfaces are converging and which are not.


Special Matrices

MatrixPurpose
Infrastructure and utility matrixUtilities versus structures, roads, drainage, with vertical and horizontal clearance rules. See Infrastructure BIM: The Complete Guide
Prefabrication matrixSpools, modules and racks versus structure, lifting paths and other trades
As-built verification matrixModel versus scan or survey data
Fire and life safety matrixFire stopping, compartments, sprinklers, dampers
Quality checks matrixInformation and rule checks, beyond geometry. See BIM Model Checking: Geometric and Information Validation

Common Problems and Remedies

ProblemCauseRemedy
Everything against everythingNo matrixDefine groups and pairs
Matrix not followedNot communicated; tool setup differsPublish; train; shared test files
Too many groupsOver-divisionMerge; combine by owner
No clearance testsOnly hard testsAdd clearance columns and volumes
Missing tolerancesDefaults usedDocument values and sources
Matrix out of dateNo reviewReview per stage and after surprises
Results cannot be comparedRules and tolerances change silentlyVersion control; record changes
Owners unclearNo assignmentAdd reviewer and resolution owner columns
Tests run on immature modelsNo stage columnLink tests to level of information

Common Mistakes

  1. No matrix.
  2. Too many pairs, too many groups.
  3. No clearance tests.
  4. Tolerances without sources.
  5. No owners or escalation.
  6. No stage or scope.
  7. Fixed selections instead of rule-based groups.
  8. A matrix nobody has seen.
  9. No maintenance.
  10. Not testing the matrix on a pilot.
  11. Reporting without reference to the matrix.
  12. Copying a matrix from another project without adaptation.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we defined groups by properties, consistent across models?
  2. Have we chosen pairs deliberately, with purposes?
  3. Are test types, tolerances and clearance values defined, with sources?
  4. Are scope, stage and frequency specified?
  5. Are reviewers, owners, escalation and approval authority assigned?
  6. Is the matrix in the BEP and onboarding materials?
  7. Is the coordination tool configured to match, and tested on a pilot?
  8. Is the matrix versioned and reviewed at each stage?
  9. Do reports follow the matrix?
  10. Do we learn from surprises and update it?

Frequently Asked Questions

What is a clash matrix?

A table defining which groups of elements are tested against which, with test type, tolerance, scope, stage, frequency and owner.

How many tests should a project have?

As few as needed to cover the important interfaces: often ten to thirty on a building project, fewer on small ones.

What should I test first?

Structure against services and architecture, drainage against everything, sprinklers against everything and equipment against clearance volumes.

Where do clearance values come from?

Manufacturer instructions, design standards, codes and specifications. Record the source.

Should the matrix change during the project?

Yes, as models mature and as surprises reveal missing tests, with version control.

Who creates the matrix?

The BIM coordinator, with the discipline leads, approved in the BEP.

How do I set up the matrix in software?

Define dynamic sets based on properties for each group, then create tests for each matrix row with the right type and tolerance, and test them on a pilot.

Can I use the same matrix on every project?

Use it as a starting template, but adapt groups, tolerances and scope to each project.


Final Thoughts

The wall-mounted matrix still hangs in a coordination room I visit. Over the years, it has acquired handwriting: new tests added in blue ink, obsolete ones struck through, a note beside one cell reading “check again after the plant move”. Nobody has ever tidied it up, because it is alive. It records what the team has learned about its own building.

A good matrix is a map of the interfaces that matter. Define the groups, choose the pairs with purpose, set honest tolerances with sources, assign owners and keep the document alive. The software will then test what you meant it to test, and the reports will mean what you thought they meant.

Where to go next: for the tests the matrix drives, read BIM Clash Detection: The Complete Guide. For the definitions behind the cells, continue with Hard Clashes vs. Soft Clashes vs. Workflow Clashes, and for the meetings that use the results, BIM Coordination Meetings: Planning, Reporting, and Best Practices.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.