The most useful single sheet of paper I have ever put on a coordination room wall is a table with disciplines along both axes and a few letters in the cells. It took an afternoon to design. It prevented, over the following months, a great deal of argument, because it answered the question that every new team member and every new subcontractor asks sooner or later: “What exactly are we testing against what?” Without that sheet, the answer is always the same: “Everything, against everything.” And “everything against everything” is the quickest route to a clash report that nobody can use.
The mathematics alone explains the problem. If a federated model has eight groups of elements, there are twenty-eight different pairs to test. Add test types (hard, clearance, duplicates) and zones (levels, areas) and variations by stage, and a project can easily generate hundreds of potential tests. Most of them are pointless: no one needs to test the plumbing against the landscape model on a building’s third floor. A few are vital: structure against ducts, drainage against everything, fire protection against everything. The clash matrix is how you decide which tests exist, what each one is for and who owns the results.
This guide shows how to create one. It covers what a matrix is, how to define the groups, how to choose the pairs, how to set test types, tolerances and clearances, how to account for zones and stages, how to write the matrix as a living document and how to maintain it. It includes a template and worked examples. It supports BIM Clash Detection: The Complete Guide and BIM Coordination: The Complete Guide.
The Short Answer
A clash detection matrix is a table that defines which groups of model elements are tested against which, with the test type, tolerance, scope, stage, frequency and owner for each test.

| Element of the matrix | What it decides |
|---|---|
| Groups (sets) | What is tested: structural frame, ducts, pipes, trays, and so on |
| Pairs | Which groups are tested against which |
| Test type | Hard, clearance, duplicates or others |
| Tolerance and clearance values | How strict each test is |
| Scope | Zones, levels or areas |
| Stage and frequency | When the test applies and how often it runs |
| Owner | Who reviews results and who resolves |
In one sentence:
The matrix turns “check everything” into a deliberate list of questions, each with a purpose, a tolerance and an owner.
Why You Need a Matrix
| Without a matrix | With a matrix |
|---|---|
| Tests are created ad hoc by whoever runs them | Tests are agreed and repeatable |
| Results vary between runs and between people | Results are comparable across cycles |
| Disciplines do not know what will be tested | Disciplines know in advance what is expected |
| Many pointless tests inflate results | Each test has a purpose |
| Important tests are forgotten | Critical interfaces are covered |
| Responsibility is unclear | Each test has an owner |
| New team members have to guess | The matrix is a reference |
A matrix is also a communication tool: it tells every party what the coordination expects of their model (what level of detail, which clearances, which categories).
Step 1: Define the Groups
What Is a Group?
A group (or set) is a collection of elements that behaves as a unit in tests: for example “all structural columns”, “all supply air ducts”, “all domestic water pipes”, “all cable trays”, “all sprinkler pipes”, “all fire-rated walls”. Groups should be defined by properties (category, system, discipline, level) so that they update when models change. See BIM Clash Detection: The Complete Guide on dynamic sets.
Grouping Principles
| Principle | Reason |
|---|---|
| Group by what conflicts with what | Pairs of groups should make sense |
| Separate systems that need different tolerances or rules | Insulated pipes versus bare pipes; large ducts versus small conduits |
| Separate structure by type where relevant | Beams and slabs versus columns; walls versus slabs |
| Separate clearance volumes | Access zones, working space zones |
| Keep the number manageable | Ten to twenty groups is common on large projects; fewer on small ones |
| Name consistently | Discipline, system, element type |
An Example List of Groups
| ID | Group | Defined by |
|---|---|---|
| S1 | Structural frame (columns, beams, slabs, walls) | Structural model, structural categories |
| A1 | Architectural walls, floors, ceilings, doors | Architectural model |
| A2 | Architectural shafts and rooms (for space checks) | Spaces and shaft elements |
| H1 | Ducts and fittings (all systems) | Mechanical model, duct categories |
| H2 | HVAC pipes and equipment | Mechanical model, pipe and equipment categories |
| P1 | Drainage pipes (gravity) | Plumbing model, drainage systems |
| P2 | Supply pipes | Plumbing model, supply systems |
| E1 | Cable containment | Electrical model |
| E2 | Electrical equipment and boards with clearance volumes | Electrical model |
| F1 | Sprinkler pipes and heads | Fire protection model |
| C1 | Clearance volumes (access, maintenance, working space) | Any model with clearance objects |
| W1 | Façade elements | Façade model |
Step 2: Choose the Pairs
The Starting Point
Create a table with groups along both axes. Then, for each pair, ask three questions:
- Can these two groups conflict in a way that matters?
- Is it possible to resolve such a conflict by someone’s decision?
- Will the test produce results that are worth reviewing?
If the answer to any is “no”, leave the cell empty.
Typical Priority Pairs (Building Projects)
| Pair | Reason |
|---|---|
| Structure versus ducts, pipes, trays | Penetrations through structure; supports; depths |
| Structure versus architecture | Columns and walls; slabs and stairs; duplicates |
| Ducts versus pipes, trays, sprinkler | Space competition in voids |
| Drainage versus everything | Drainage has the least flexibility |
| Sprinkler versus everything | Head positions and pipe routes; obstructions |
| Services versus ceilings and architecture | Clear heights; reflected ceiling coordination |
| Equipment versus clearance volumes | Access and maintenance |
| Electrical equipment versus other services | Working space and segregation |
| Façade versus structure | Edge conditions and fixings |
| Same group versus itself | Duplicates and self-overlap checks |
Reducing the Number
- Limit by zone: test only where groups coexist (for example plant rooms, risers, ceiling voids).
- Limit by stage: do not test detail-level pairs at concept stage.
- Combine pairs where results will be handled by the same people.
- Drop pointless pairs. Be willing to say “we do not test this”.
Step 3: Define Test Types, Tolerances and Clearances
Test Types
| Test | Use |
|---|---|
| Hard | Intersections |
| Hard (conservative) | Where missed intersections are a risk and false positives can be handled |
| Clearance | Required distances and clearance volumes |
| Duplicates | Same element twice |
Tolerances
For each test, state the tolerance and its meaning. The values below are illustrative placeholders; set yours with the disciplines.
| Test | Tolerance (illustrative placeholder) | Meaning |
|---|---|---|
| Hard, structure versus services | Small value agreed with structure | Overlaps smaller than this are ignored |
| Hard, services versus services | Small value agreed | Same |
| Clearance, insulated services | Insulation thickness plus installation allowance | Required distance |
| Clearance, access and maintenance | From manufacturer or code | Required space |
| Duplicates | Very small | Matches within this are treated as duplicates |
Where the Values Come From
| Source | Used for |
|---|---|
| Manufacturer data and installation manuals | Equipment clearances |
| Design standards and codes | Working space, access, minimum distances |
| Specifications | Insulation, supports, fire stopping |
| Installer practice | Installation allowances |
| Project agreement | Modeling tolerance |
Record the source of each value. See Hard Clashes vs. Soft Clashes vs. Workflow Clashes.
Step 4: Set Scope, Stage and Frequency
| Column | Content |
|---|---|
| Zone or scope | Whole building, a level, plant rooms, risers, corridors |
| Stage | Concept, developed design, technical design, trade coordination, pre-fabrication |
| Frequency | Every cycle, milestone only, on demand |
| Preconditions | Models at the required level of information; clearance volumes present |
| Exclusions | Known acceptable overlaps; temporary or placeholder objects |
Link the stage to the level of information. Running a pair too early produces noise; too late loses the benefit. See BIM Project Planning: Milestones, Deliverables, and Coordination.
Step 5: Assign Owners and Resolution Rules
| Column | Content |
|---|---|
| Reviewer | Who reviews the results (usually the coordinator) |
| Resolution owner | Who typically resolves (by priority rules or by default) |
| Escalation | Who decides if the owners cannot agree |
| Approval authority | Who can approve a deviation (for example clearance deviations or penetrations) |
| Notes | Rules of thumb: “structure yields only with approval”; “drainage has priority” |
Add the routing priorities to the matrix document. See MEP BIM Coordination: Identifying and Resolving Clashes.
A Template
| ID | Set A | Set B | Test type | Tolerance and source | Scope | Stage | Frequency | Reviewer | Resolution owner | Notes |
|---|---|---|---|---|---|---|---|---|---|---|
| T01 | S1 Structure | H1 Ducts | Hard | Agreed hard tolerance | Whole building | Developed to technical design | Each cycle | Coordinator | Mechanical (with structure approval) | Penetrations require approved openings |
| T02 | S1 Structure | P1 Drainage | Hard | Agreed hard tolerance | Whole building | Developed to technical design | Each cycle | Coordinator | Plumbing (with structure approval) | Check falls and openings |
| T03 | H1 Ducts | P1 Drainage | Hard and clearance | Insulation plus allowance | Voids and corridors | Developed design onward | Each cycle | Coordinator | Mechanical yields unless priority rule states otherwise | Drainage priority |
| T04 | F1 Sprinklers | All services | Hard and clearance | Per sprinkler designer | Ceiling voids | Technical design onward | Each cycle | Coordinator and sprinkler designer | Owner of the obstructing element | Obstruction rules by designer |
| T05 | E2 Electrical equipment | C1 Clearance volumes | Hard | Zero | Electrical rooms | Technical design onward | Each cycle | Coordinator | Owner of intruding element | Working space per code and manufacturer |
| T06 | H1 Ducts | A1 Ceilings | Hard and clearance | Ceiling zone allowance | Ceiling zones | Developed design onward | Each cycle | Coordinator | Mechanical or architecture per zoning | Clear height |
| T07 | S1 Structure | A1 Architecture | Hard and duplicates | Agreed | Whole building | All stages | Each cycle | Coordinator | Structure and architecture | Duplicates between models |
| T08 | All models | Self | Duplicates | Very small | Whole building | All stages | Each cycle | Coordinator | Model owner | Same element in two places |
| T09 | W1 Façade | S1 Structure | Hard and clearance | Movement allowance | Perimeter | Technical design onward | Milestones | Coordinator | Façade and structure | Fixings and edge conditions |
The matrix image above is a compact overview; the table is the working document.
Making the Matrix Work
Publish It
Include it in the BEP or its appendix, and in the onboarding pack for each new party. Make sure each discipline knows which of its elements will be tested against what, and what level of detail they must provide.
Link It to the Models
- Define sets in the coordination tool to match the groups, using properties that every model carries (system, category, level).
- Agree parameters so that sets can be built reliably. See BIM Metadata, Attributes, and Property Sets Explained.
- Test the matrix on a pilot model before the first official cycle.
Maintain It
| Practice | Reason |
|---|---|
| Version control | The matrix changes; track versions |
| Review at each stage | Add detail-level tests when models mature |
| Review after surprises | A problem found on site means a missing test |
| Remove useless tests | Keep the matrix lean |
| Record rule changes | Rules and tolerances affect comparability between cycles |
Use It in Reports
Report results by matrix test: “T03: 12 open issues, 5 new, 7 active.” This lets you see which interfaces are converging and which are not.
Special Matrices
| Matrix | Purpose |
|---|---|
| Infrastructure and utility matrix | Utilities versus structures, roads, drainage, with vertical and horizontal clearance rules. See Infrastructure BIM: The Complete Guide |
| Prefabrication matrix | Spools, modules and racks versus structure, lifting paths and other trades |
| As-built verification matrix | Model versus scan or survey data |
| Fire and life safety matrix | Fire stopping, compartments, sprinklers, dampers |
| Quality checks matrix | Information and rule checks, beyond geometry. See BIM Model Checking: Geometric and Information Validation |
Common Problems and Remedies
| Problem | Cause | Remedy |
|---|---|---|
| Everything against everything | No matrix | Define groups and pairs |
| Matrix not followed | Not communicated; tool setup differs | Publish; train; shared test files |
| Too many groups | Over-division | Merge; combine by owner |
| No clearance tests | Only hard tests | Add clearance columns and volumes |
| Missing tolerances | Defaults used | Document values and sources |
| Matrix out of date | No review | Review per stage and after surprises |
| Results cannot be compared | Rules and tolerances change silently | Version control; record changes |
| Owners unclear | No assignment | Add reviewer and resolution owner columns |
| Tests run on immature models | No stage column | Link tests to level of information |
Common Mistakes
- No matrix.
- Too many pairs, too many groups.
- No clearance tests.
- Tolerances without sources.
- No owners or escalation.
- No stage or scope.
- Fixed selections instead of rule-based groups.
- A matrix nobody has seen.
- No maintenance.
- Not testing the matrix on a pilot.
- Reporting without reference to the matrix.
- Copying a matrix from another project without adaptation.
See also Common BIM Mistakes Beginners Should Avoid.
A Short Checklist
- Have we defined groups by properties, consistent across models?
- Have we chosen pairs deliberately, with purposes?
- Are test types, tolerances and clearance values defined, with sources?
- Are scope, stage and frequency specified?
- Are reviewers, owners, escalation and approval authority assigned?
- Is the matrix in the BEP and onboarding materials?
- Is the coordination tool configured to match, and tested on a pilot?
- Is the matrix versioned and reviewed at each stage?
- Do reports follow the matrix?
- Do we learn from surprises and update it?
Frequently Asked Questions
What is a clash matrix?
A table defining which groups of elements are tested against which, with test type, tolerance, scope, stage, frequency and owner.
How many tests should a project have?
As few as needed to cover the important interfaces: often ten to thirty on a building project, fewer on small ones.
What should I test first?
Structure against services and architecture, drainage against everything, sprinklers against everything and equipment against clearance volumes.
Where do clearance values come from?
Manufacturer instructions, design standards, codes and specifications. Record the source.
Should the matrix change during the project?
Yes, as models mature and as surprises reveal missing tests, with version control.
Who creates the matrix?
The BIM coordinator, with the discipline leads, approved in the BEP.
How do I set up the matrix in software?
Define dynamic sets based on properties for each group, then create tests for each matrix row with the right type and tolerance, and test them on a pilot.
Can I use the same matrix on every project?
Use it as a starting template, but adapt groups, tolerances and scope to each project.
Final Thoughts
The wall-mounted matrix still hangs in a coordination room I visit. Over the years, it has acquired handwriting: new tests added in blue ink, obsolete ones struck through, a note beside one cell reading “check again after the plant move”. Nobody has ever tidied it up, because it is alive. It records what the team has learned about its own building.
A good matrix is a map of the interfaces that matter. Define the groups, choose the pairs with purpose, set honest tolerances with sources, assign owners and keep the document alive. The software will then test what you meant it to test, and the reports will mean what you thought they meant.
Where to go next: for the tests the matrix drives, read BIM Clash Detection: The Complete Guide. For the definitions behind the cells, continue with Hard Clashes vs. Soft Clashes vs. Workflow Clashes, and for the meetings that use the results, BIM Coordination Meetings: Planning, Reporting, and Best Practices.