The first renovation project I modeled taught me a humbling lesson about the word “existing”. We had a set of as-built drawings, a survey and a client who assured us that the building had “not changed much” since it was drawn. We modeled it carefully, from the drawings, and the model was a perfect representation of the building as it had been designed in 1974. On the first site visit, we discovered that a floor was eighty millimeters lower than the drawings said, that a partition had been moved at some point in the nineties, that the ceiling void contained a duct that no drawing mentioned and that the “straight” corridor bowed outward by thirty millimeters over its length. None of this was dramatic. All of it mattered, because the new work was designed to fit tightly.
Renovation and work on existing buildings is a different problem from new design. In new work, the model defines what will be built. In existing buildings, the model must represent what is already there, which is partly known, partly assumed and partly hidden. The central challenge is not geometry. It is uncertainty: how reliable is each piece of information, how much accuracy do we need, what do we do about what we cannot see and how do we make the uncertainty visible to everyone who relies on the model?
This guide explains how to approach BIM modeling for renovation and existing buildings. It covers the information sources and their reliability, how to decide what to model and to what accuracy, how to represent existing, demolished and new work, how to handle irregular geometry and hidden conditions, how to work with structural engineers and services, heritage and hazard information, deliverables for renovation and how to deal with discoveries during works. It connects to the dedicated guide on point clouds, Scan-to-BIM: Converting Point Clouds into Intelligent Models, and to the wider architectural modeling guide, Architectural BIM Modeling: The Complete Guide.
The Short Answer
Modeling existing buildings means building a fit-for-purpose, honestly labeled representation of what exists, then designing the new work in phases against it.

| Principle | In practice |
|---|---|
| Define the purpose first | What decisions will the existing-conditions model support? |
| Choose the accuracy deliberately | Survey and model to the accuracy the design and construction need |
| Model what you need, not everything | Detail where the new work interacts with the old |
| Label reliability | Record how each element was known: measured, assumed or unknown |
| Use phases | Existing, demolished, new and temporary work stay distinct |
| Plan for discovery | Expect surprises; keep the model and records updatable |
In one sentence:
An existing-conditions model is a statement of what we know and how well we know it. Make both visible.
Step 1: Define the Purpose and the Required Accuracy
Before any survey or modeling, ask what the existing model is for.
| Purpose | Accuracy and detail implications |
|---|---|
| Feasibility and options | Overall dimensions, floor areas, principal structure; modest accuracy |
| Planning and design development | Reliable layouts, levels, floor-to-floor heights, openings; moderate accuracy |
| Detailed design and fit of new elements | High accuracy where new work meets existing: openings, structure, services routes |
| Fabrication (façades, joinery, steel) | Very high accuracy, often measured specifically |
| Quantities of demolition and retention | Good element identification and measurement |
| Heritage documentation | High accuracy and detailed record of fabric and condition |
| Asset and operation | Spaces, assets and data; geometry may be modest |
Specifying Accuracy
Accuracy is separate from detail. The Level of Accuracy (LOA) Specification published by the US Institute of Building Documentation distinguishes measured accuracy (how accurately the data was captured) from represented accuracy (how accurately the model or drawing represents the captured data), with five levels (LOA10 to LOA50) of increasingly strict tolerance. The specification is free to download, and its version 3.1 appeared in 2025. It is used alongside level of development frameworks, which address how much detail the model elements have, not how accurate the data underlying them is. Whatever framework you use, write the accuracy requirement into the survey and modeling brief. See Scan-to-BIM: Converting Point Clouds into Intelligent Models.
Step 2: Gather Information and Judge Its Reliability
Existing information varies greatly in quality. Treat each source honestly.
| Source | Typical value | Typical limitations |
|---|---|---|
| Original design drawings | Intent, layout, structure type | Often differ from what was built; later alterations missing |
| As-built or record drawings | Closer to reality | Quality varies; may be outdated |
| Previous alteration drawings | Show changes | Incomplete sets are common |
| Measured survey | Reliable dimensions | Only visible surfaces; cost and scope vary |
| Laser scan or photogrammetry | Dense, accurate capture of visible geometry | Does not see inside walls, voids or behind objects |
| Site investigations and opening-up works | Reveal hidden construction | Local; intrusive; cost and disruption |
| Structural and condition surveys | Material and condition data | Specialist; often sampling |
| Services surveys | Locations of installations | Concealed services difficult to trace |
| Hazard and environmental surveys | Presence of hazardous materials | Specialist and regulated; keep results controlled |
| Historical records and photographs | Context and previous states | Interpretation needed |
| Client and user knowledge | Practical history | Memories vary |
The Reliability Idea
Give each element or area a reliability status. A simple scale:
| Status | Meaning | Example |
|---|---|---|
| Verified | Measured or scanned and checked | Visible walls from a scan |
| Assumed | Taken from drawings or records, not verified | A wall inside a ceiling void taken from the original plans |
| Unknown | Hidden or no information | Structure behind a finish |
Record the status as data on elements (a parameter), or at least on a map layer. It communicates risk to everyone who relies on the model, and it directs where investigations are worth their cost.
Step 3: Decide What to Model and How
Model What the Design Needs
A complete as-built model of every pipe, board and bracket is expensive and usually unnecessary. Consider:
| Area | Typical decision |
|---|---|
| Areas to be retained and unchanged | Model the envelope and main spaces at moderate detail |
| Areas where new work interacts with existing | Model to higher accuracy: walls, openings, structure, levels |
| Areas to be demolished | Model enough to quantify and sequence demolition |
| Services | Model main routes and plant if relevant; use survey data and assumptions for concealed items |
| Structure | Model the principal frame as known; coordinate with the structural engineer |
| Finishes | As data or simple layers, according to need |
| Decorative or heritage fabric | Detail according to the documentation or conservation requirements |
Irregular Geometry
Existing buildings are rarely orthogonal or level. Options:
| Strategy | When |
|---|---|
| Idealize | Model walls plumb and floors level, with the deviations recorded elsewhere; adequate where tolerance is large |
| Model as measured | Represent actual positions, slopes and curvature where the design requires fitting to them |
| Hybrid | Idealized model plus a separate deviation record (scan comparison or survey notes) |
| Mesh or point cloud as reference | Use point clouds as underlays for measuring and verification, with modeled elements simplified |
State the tolerance the model accepts: for instance, “walls modeled plumb; deviations beyond twenty millimeters recorded in the survey report”. Without a stated tolerance, users do not know how far to trust positions.
Levels, Grids and Coordinates
Existing buildings seldom have clean level datums. Establish project levels for the design, relate them to the measured floor heights, and document the differences. Use shared coordinates to relate the model to the survey control. See BIM Georeferencing: Coordinate Systems and Model Positioning.
Step 4: Phases and Work Status
Renovation projects need to distinguish time and work status. Most BIM software supports phases and phase filters (or equivalents).
| Status | Meaning | Typical display |
|---|---|---|
| Existing | Elements that exist and remain | Normal or grey |
| Demolished | Elements to be removed | Dashed or colored |
| New | Proposed work | Normal weight, distinct fill |
| Temporary | Propping, protection, hoardings | Special style |
| Retained and modified | Existing elements altered | Marked separately |
Rules for Phases
- Assign phase created and phase demolished to every element, not just visually.
- Use phase filters in views so existing, demolition and new drawings come from the same model.
- Keep naming consistent across disciplines.
- Check quantities by phase so demolition and new work schedules are reliable.
- For multi-stage works (occupied buildings), add construction phases or sequencing information.
Phase data also helps handover: the final model should show what exists after the works, not the history, unless the client wants a record. Plan how the post-construction model is derived.
Step 5: Structure, Services and Hidden Conditions
Structure
- Do not guess. If the structure matters to the design, involve the structural engineer early, and request investigation where uncertainty is high.
- Model structure as known, labeled by reliability.
- Record the sources of information: original drawings, opening-up, tests.
- Coordinate new structural interventions through the usual process. See BIM Coordination: The Complete Guide.
Services
Existing services are often poorly documented.
- Use surveys and scanning for visible services.
- Model main routes and plant where they affect design; show the rest as 2D or notes.
- Label unknown routes clearly, and plan investigation and isolation procedures.
- Do not present assumed routes as verified.
Hidden Conditions
Assume that some conditions will be discovered during works. Plan:
- an assumptions register (what the design assumes about hidden conditions);
- contingency in programme and budget;
- a procedure for recording discoveries (photographs, measurements, model updates);
- review points where designers reassess after opening-up.
Heritage and Historic Buildings
Historic buildings add conservation duties and complex geometry. The term HBIM (heritage or historic BIM) is often used for modeling historic structures.
| Consideration | Practice |
|---|---|
| Documentation purpose | Conservation, interpretation, repair design, monitoring |
| Accuracy and detail | Often high; irregular, hand-made elements |
| Representation of fabric | Material, age, condition, intervention history as data |
| Specialist input | Conservation architects and surveyors define requirements |
| Complex geometry | Mesh or point cloud references; parametric modeling where it clarifies; accept simplification with clear tolerances |
| Record and archive | Long-term preservation of survey data and models in open formats. See openBIM Explained: Principles, Standards, and Benefits |
Take advice from conservation specialists and the relevant authorities. The model supports decisions; it does not replace professional judgment.
Hazards and Regulated Information
Existing buildings may contain hazardous materials and other regulated risks. Rules differ by country and are legally important.
- Do not make hazard judgments in the model. Information comes from qualified surveys.
- Record survey results as controlled information, with clear sources, dates and limitations.
- Control access according to the sensitivity. See BIM Information Security, Access Control, and Data Governance and ISO 19650-6: Health and Safety Information Management.
- Show hazard locations in models and plans where the safety plan requires, using the agreed convention.
- Follow the legal requirements of your jurisdiction. Seek specialist advice.
Design and Deliverables for Renovation
| Deliverable | Content |
|---|---|
| Existing-conditions model | Verified, assumed and unknown conditions labeled; stated accuracy and tolerance |
| Survey and scan data | Point clouds, survey reports, control, accuracy statements |
| Phased design model | Existing, demolition, new and temporary work |
| Demolition and strip-out documents | Plans, schedules, quantities |
| New-work documentation | Plans, sections, details showing interfaces with existing fabric |
| Phasing and sequencing information | For occupied buildings and multi-stage works |
| Assumptions register | What is assumed and how it will be verified |
| Quantities | Retained, demolished, new |
| Handover model | The building as completed, with asset data as the AIR requires |
See Architectural BIM Documentation: Plans, Sections, and Schedules and Asset Information Requirements (AIR): Complete Guide.
Working With the Client and the Contractor
- Explain uncertainty. Clients often expect the model to be perfectly accurate. Show the reliability map and explain what it means for cost and risk.
- Agree the survey scope and budget early, since survey cost is small compared with discovery cost on site.
- Involve the contractor in reviewing existing conditions and sequencing.
- Plan for change control: discoveries will alter the design. Use clear records and issue logs. See BIM Collaboration Format (BCF): The Complete Guide.
- Keep records: what was found, when, by whom, and how the model changed.
Checks for Existing-Conditions Models
| Check | What to look for |
|---|---|
| Purpose and accuracy | The brief states purpose, accuracy and tolerance, and the model matches |
| Sources | Every area traceable to a source |
| Reliability | Status recorded for elements and areas |
| Coordinates and levels | Consistent with survey control; documented differences |
| Deviation checks | Model compared with the point cloud or survey in key areas |
| Phases | Every element has phase created and demolished correctly |
| Quantities | Demolition and retained quantities plausible |
| Interfaces | New elements fit existing geometry with tolerance |
| Hazard information | Controlled, sourced and dated |
| Assumptions register | Maintained and linked to risks |
See Architectural BIM Model Auditing and Quality Control.
Common Mistakes
- Modeling from old drawings and calling it “existing”.
- No stated accuracy or purpose.
- Modeling everything at uniform detail.
- No reliability labels, so assumed looks verified.
- Idealized geometry with no deviation record.
- No phase discipline, so quantities mix existing and new.
- Guessing structure or services.
- No survey or an inadequate one to save cost.
- Mixing hazard information with general data without control.
- No assumptions register or contingency.
- Not updating the model with discoveries.
- Ignoring the client’s expectations about accuracy.
See also Common BIM Mistakes Beginners Should Avoid.
A Short Checklist
- Have we defined the purpose, accuracy and tolerance of the existing model?
- Have we listed sources and judged their reliability?
- Have we decided what to model and to what detail, by area?
- Is reliability recorded as data or on a map?
- Are phases set on all elements, with filters for existing, demolition and new?
- Have structure and services been investigated or labeled as assumed?
- Is there an assumptions register and a discovery procedure?
- Is hazard and regulated information controlled?
- Are deliverables for renovation defined, including quantities and phasing?
- Is there a plan for updating the model through the works and at handover?
Frequently Asked Questions
How do I model an existing building in BIM?
Define the purpose and accuracy, gather and rate the information, decide what to model, represent existing, demolished and new work through phases and label reliability and assumptions.
What is the difference between LOD and LOA?
Level of development describes how much detail a model element has; level of accuracy describes how accurately the data represents reality. See BIM Levels of Development (LOD) Explained.
Can I model from old drawings?
You can use them as a source, but treat them as assumed, not verified. Check against site measurements or scans where accuracy matters.
How accurate should an existing-conditions model be?
As accurate as the design and construction need, particularly where new work interfaces with existing fabric. Write the requirement into the brief.
How do I show demolition in BIM?
With phases and phase filters, assigning phase created and phase demolished to elements so that existing, demolition and new views come from one model.
How do I deal with hidden conditions?
With surveys and investigations where risk is high, an assumptions register, contingency and a procedure to record and incorporate discoveries.
What is HBIM?
Heritage or historic BIM: modeling of historic buildings with emphasis on documentation, conservation and complex geometry.
Do I need a laser scan?
Not always. Scans are valuable where accuracy and complete visible geometry matter. Choose the survey method for the purpose and budget. See Scan-to-BIM: Converting Point Clouds into Intelligent Models.
Final Thoughts
After the 1974 model, I changed how I introduce renovation projects to clients. In the first meeting, I show a simple traffic-light plan of the building: green areas measured, amber areas assumed, red areas unknown. Clients often look uncomfortable at the amount of amber and red. Then I say: “The money for investigating the red areas is small compared with what it will cost if we find out during construction.” In nearly every case, the client approves a targeted survey.
That conversation is the heart of renovation BIM. The model is not a claim of certainty. It is a map of knowledge, with honest edges. Define the purpose, specify the accuracy, label reliability, use phases and plan for discovery. The building will still surprise you, but you will have prepared your client, your team and your model for it.
Where to go next: for point-cloud workflows, read Scan-to-BIM: Converting Point Clouds into Intelligent Models. For the elements you will model, continue with BIM Modeling Standards for Walls, Floors, Roofs, and Ceilings, and for checks, Architectural BIM Model Auditing and Quality Control.