BIM Modeling for Renovation and Existing Buildings

BIM Modeling for Renovation and Existing Buildings

The first renovation project I modeled taught me a humbling lesson about the word “existing”. We had a set of as-built drawings, a survey and a client who assured us that the building had “not changed much” since it was drawn. We modeled it carefully, from the drawings, and the model was a perfect representation of the building as it had been designed in 1974. On the first site visit, we discovered that a floor was eighty millimeters lower than the drawings said, that a partition had been moved at some point in the nineties, that the ceiling void contained a duct that no drawing mentioned and that the “straight” corridor bowed outward by thirty millimeters over its length. None of this was dramatic. All of it mattered, because the new work was designed to fit tightly.

Renovation and work on existing buildings is a different problem from new design. In new work, the model defines what will be built. In existing buildings, the model must represent what is already there, which is partly known, partly assumed and partly hidden. The central challenge is not geometry. It is uncertainty: how reliable is each piece of information, how much accuracy do we need, what do we do about what we cannot see and how do we make the uncertainty visible to everyone who relies on the model?

This guide explains how to approach BIM modeling for renovation and existing buildings. It covers the information sources and their reliability, how to decide what to model and to what accuracy, how to represent existing, demolished and new work, how to handle irregular geometry and hidden conditions, how to work with structural engineers and services, heritage and hazard information, deliverables for renovation and how to deal with discoveries during works. It connects to the dedicated guide on point clouds, Scan-to-BIM: Converting Point Clouds into Intelligent Models, and to the wider architectural modeling guide, Architectural BIM Modeling: The Complete Guide.


The Short Answer

Modeling existing buildings means building a fit-for-purpose, honestly labeled representation of what exists, then designing the new work in phases against it.

Modeling renovation: phases and confidence

PrincipleIn practice
Define the purpose firstWhat decisions will the existing-conditions model support?
Choose the accuracy deliberatelySurvey and model to the accuracy the design and construction need
Model what you need, not everythingDetail where the new work interacts with the old
Label reliabilityRecord how each element was known: measured, assumed or unknown
Use phasesExisting, demolished, new and temporary work stay distinct
Plan for discoveryExpect surprises; keep the model and records updatable

In one sentence:

An existing-conditions model is a statement of what we know and how well we know it. Make both visible.


Step 1: Define the Purpose and the Required Accuracy

Before any survey or modeling, ask what the existing model is for.

PurposeAccuracy and detail implications
Feasibility and optionsOverall dimensions, floor areas, principal structure; modest accuracy
Planning and design developmentReliable layouts, levels, floor-to-floor heights, openings; moderate accuracy
Detailed design and fit of new elementsHigh accuracy where new work meets existing: openings, structure, services routes
Fabrication (façades, joinery, steel)Very high accuracy, often measured specifically
Quantities of demolition and retentionGood element identification and measurement
Heritage documentationHigh accuracy and detailed record of fabric and condition
Asset and operationSpaces, assets and data; geometry may be modest

Specifying Accuracy

Accuracy is separate from detail. The Level of Accuracy (LOA) Specification published by the US Institute of Building Documentation distinguishes measured accuracy (how accurately the data was captured) from represented accuracy (how accurately the model or drawing represents the captured data), with five levels (LOA10 to LOA50) of increasingly strict tolerance. The specification is free to download, and its version 3.1 appeared in 2025. It is used alongside level of development frameworks, which address how much detail the model elements have, not how accurate the data underlying them is. Whatever framework you use, write the accuracy requirement into the survey and modeling brief. See Scan-to-BIM: Converting Point Clouds into Intelligent Models.


Step 2: Gather Information and Judge Its Reliability

Existing information varies greatly in quality. Treat each source honestly.

SourceTypical valueTypical limitations
Original design drawingsIntent, layout, structure typeOften differ from what was built; later alterations missing
As-built or record drawingsCloser to realityQuality varies; may be outdated
Previous alteration drawingsShow changesIncomplete sets are common
Measured surveyReliable dimensionsOnly visible surfaces; cost and scope vary
Laser scan or photogrammetryDense, accurate capture of visible geometryDoes not see inside walls, voids or behind objects
Site investigations and opening-up worksReveal hidden constructionLocal; intrusive; cost and disruption
Structural and condition surveysMaterial and condition dataSpecialist; often sampling
Services surveysLocations of installationsConcealed services difficult to trace
Hazard and environmental surveysPresence of hazardous materialsSpecialist and regulated; keep results controlled
Historical records and photographsContext and previous statesInterpretation needed
Client and user knowledgePractical historyMemories vary

The Reliability Idea

Give each element or area a reliability status. A simple scale:

StatusMeaningExample
VerifiedMeasured or scanned and checkedVisible walls from a scan
AssumedTaken from drawings or records, not verifiedA wall inside a ceiling void taken from the original plans
UnknownHidden or no informationStructure behind a finish

Record the status as data on elements (a parameter), or at least on a map layer. It communicates risk to everyone who relies on the model, and it directs where investigations are worth their cost.


Step 3: Decide What to Model and How

Model What the Design Needs

A complete as-built model of every pipe, board and bracket is expensive and usually unnecessary. Consider:

AreaTypical decision
Areas to be retained and unchangedModel the envelope and main spaces at moderate detail
Areas where new work interacts with existingModel to higher accuracy: walls, openings, structure, levels
Areas to be demolishedModel enough to quantify and sequence demolition
ServicesModel main routes and plant if relevant; use survey data and assumptions for concealed items
StructureModel the principal frame as known; coordinate with the structural engineer
FinishesAs data or simple layers, according to need
Decorative or heritage fabricDetail according to the documentation or conservation requirements

Irregular Geometry

Existing buildings are rarely orthogonal or level. Options:

StrategyWhen
IdealizeModel walls plumb and floors level, with the deviations recorded elsewhere; adequate where tolerance is large
Model as measuredRepresent actual positions, slopes and curvature where the design requires fitting to them
HybridIdealized model plus a separate deviation record (scan comparison or survey notes)
Mesh or point cloud as referenceUse point clouds as underlays for measuring and verification, with modeled elements simplified

State the tolerance the model accepts: for instance, “walls modeled plumb; deviations beyond twenty millimeters recorded in the survey report”. Without a stated tolerance, users do not know how far to trust positions.

Levels, Grids and Coordinates

Existing buildings seldom have clean level datums. Establish project levels for the design, relate them to the measured floor heights, and document the differences. Use shared coordinates to relate the model to the survey control. See BIM Georeferencing: Coordinate Systems and Model Positioning.


Step 4: Phases and Work Status

Renovation projects need to distinguish time and work status. Most BIM software supports phases and phase filters (or equivalents).

StatusMeaningTypical display
ExistingElements that exist and remainNormal or grey
DemolishedElements to be removedDashed or colored
NewProposed workNormal weight, distinct fill
TemporaryPropping, protection, hoardingsSpecial style
Retained and modifiedExisting elements alteredMarked separately

Rules for Phases

  • Assign phase created and phase demolished to every element, not just visually.
  • Use phase filters in views so existing, demolition and new drawings come from the same model.
  • Keep naming consistent across disciplines.
  • Check quantities by phase so demolition and new work schedules are reliable.
  • For multi-stage works (occupied buildings), add construction phases or sequencing information.

Phase data also helps handover: the final model should show what exists after the works, not the history, unless the client wants a record. Plan how the post-construction model is derived.


Step 5: Structure, Services and Hidden Conditions

Structure

  • Do not guess. If the structure matters to the design, involve the structural engineer early, and request investigation where uncertainty is high.
  • Model structure as known, labeled by reliability.
  • Record the sources of information: original drawings, opening-up, tests.
  • Coordinate new structural interventions through the usual process. See BIM Coordination: The Complete Guide.

Services

Existing services are often poorly documented.

  • Use surveys and scanning for visible services.
  • Model main routes and plant where they affect design; show the rest as 2D or notes.
  • Label unknown routes clearly, and plan investigation and isolation procedures.
  • Do not present assumed routes as verified.

Hidden Conditions

Assume that some conditions will be discovered during works. Plan:

  • an assumptions register (what the design assumes about hidden conditions);
  • contingency in programme and budget;
  • a procedure for recording discoveries (photographs, measurements, model updates);
  • review points where designers reassess after opening-up.

Heritage and Historic Buildings

Historic buildings add conservation duties and complex geometry. The term HBIM (heritage or historic BIM) is often used for modeling historic structures.

ConsiderationPractice
Documentation purposeConservation, interpretation, repair design, monitoring
Accuracy and detailOften high; irregular, hand-made elements
Representation of fabricMaterial, age, condition, intervention history as data
Specialist inputConservation architects and surveyors define requirements
Complex geometryMesh or point cloud references; parametric modeling where it clarifies; accept simplification with clear tolerances
Record and archiveLong-term preservation of survey data and models in open formats. See openBIM Explained: Principles, Standards, and Benefits

Take advice from conservation specialists and the relevant authorities. The model supports decisions; it does not replace professional judgment.


Hazards and Regulated Information

Existing buildings may contain hazardous materials and other regulated risks. Rules differ by country and are legally important.


Design and Deliverables for Renovation

DeliverableContent
Existing-conditions modelVerified, assumed and unknown conditions labeled; stated accuracy and tolerance
Survey and scan dataPoint clouds, survey reports, control, accuracy statements
Phased design modelExisting, demolition, new and temporary work
Demolition and strip-out documentsPlans, schedules, quantities
New-work documentationPlans, sections, details showing interfaces with existing fabric
Phasing and sequencing informationFor occupied buildings and multi-stage works
Assumptions registerWhat is assumed and how it will be verified
QuantitiesRetained, demolished, new
Handover modelThe building as completed, with asset data as the AIR requires

See Architectural BIM Documentation: Plans, Sections, and Schedules and Asset Information Requirements (AIR): Complete Guide.


Working With the Client and the Contractor

  • Explain uncertainty. Clients often expect the model to be perfectly accurate. Show the reliability map and explain what it means for cost and risk.
  • Agree the survey scope and budget early, since survey cost is small compared with discovery cost on site.
  • Involve the contractor in reviewing existing conditions and sequencing.
  • Plan for change control: discoveries will alter the design. Use clear records and issue logs. See BIM Collaboration Format (BCF): The Complete Guide.
  • Keep records: what was found, when, by whom, and how the model changed.

Checks for Existing-Conditions Models

CheckWhat to look for
Purpose and accuracyThe brief states purpose, accuracy and tolerance, and the model matches
SourcesEvery area traceable to a source
ReliabilityStatus recorded for elements and areas
Coordinates and levelsConsistent with survey control; documented differences
Deviation checksModel compared with the point cloud or survey in key areas
PhasesEvery element has phase created and demolished correctly
QuantitiesDemolition and retained quantities plausible
InterfacesNew elements fit existing geometry with tolerance
Hazard informationControlled, sourced and dated
Assumptions registerMaintained and linked to risks

See Architectural BIM Model Auditing and Quality Control.


Common Mistakes

  1. Modeling from old drawings and calling it “existing”.
  2. No stated accuracy or purpose.
  3. Modeling everything at uniform detail.
  4. No reliability labels, so assumed looks verified.
  5. Idealized geometry with no deviation record.
  6. No phase discipline, so quantities mix existing and new.
  7. Guessing structure or services.
  8. No survey or an inadequate one to save cost.
  9. Mixing hazard information with general data without control.
  10. No assumptions register or contingency.
  11. Not updating the model with discoveries.
  12. Ignoring the client’s expectations about accuracy.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Have we defined the purpose, accuracy and tolerance of the existing model?
  2. Have we listed sources and judged their reliability?
  3. Have we decided what to model and to what detail, by area?
  4. Is reliability recorded as data or on a map?
  5. Are phases set on all elements, with filters for existing, demolition and new?
  6. Have structure and services been investigated or labeled as assumed?
  7. Is there an assumptions register and a discovery procedure?
  8. Is hazard and regulated information controlled?
  9. Are deliverables for renovation defined, including quantities and phasing?
  10. Is there a plan for updating the model through the works and at handover?

Frequently Asked Questions

How do I model an existing building in BIM?

Define the purpose and accuracy, gather and rate the information, decide what to model, represent existing, demolished and new work through phases and label reliability and assumptions.

What is the difference between LOD and LOA?

Level of development describes how much detail a model element has; level of accuracy describes how accurately the data represents reality. See BIM Levels of Development (LOD) Explained.

Can I model from old drawings?

You can use them as a source, but treat them as assumed, not verified. Check against site measurements or scans where accuracy matters.

How accurate should an existing-conditions model be?

As accurate as the design and construction need, particularly where new work interfaces with existing fabric. Write the requirement into the brief.

How do I show demolition in BIM?

With phases and phase filters, assigning phase created and phase demolished to elements so that existing, demolition and new views come from one model.

How do I deal with hidden conditions?

With surveys and investigations where risk is high, an assumptions register, contingency and a procedure to record and incorporate discoveries.

What is HBIM?

Heritage or historic BIM: modeling of historic buildings with emphasis on documentation, conservation and complex geometry.

Do I need a laser scan?

Not always. Scans are valuable where accuracy and complete visible geometry matter. Choose the survey method for the purpose and budget. See Scan-to-BIM: Converting Point Clouds into Intelligent Models.


Final Thoughts

After the 1974 model, I changed how I introduce renovation projects to clients. In the first meeting, I show a simple traffic-light plan of the building: green areas measured, amber areas assumed, red areas unknown. Clients often look uncomfortable at the amount of amber and red. Then I say: “The money for investigating the red areas is small compared with what it will cost if we find out during construction.” In nearly every case, the client approves a targeted survey.

That conversation is the heart of renovation BIM. The model is not a claim of certainty. It is a map of knowledge, with honest edges. Define the purpose, specify the accuracy, label reliability, use phases and plan for discovery. The building will still surprise you, but you will have prepared your client, your team and your model for it.

Where to go next: for point-cloud workflows, read Scan-to-BIM: Converting Point Clouds into Intelligent Models. For the elements you will model, continue with BIM Modeling Standards for Walls, Floors, Roofs, and Ceilings, and for checks, Architectural BIM Model Auditing and Quality Control.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.