Creating Shop Drawings and Fabrication Models from BIM

Creating Shop Drawings and Fabrication Models from BIM

Shop drawings have a peculiar status in construction. They are not design drawings, because they are produced by the contractor, the fabricator or a specialist, not by the design team. They are not construction drawings in the sense of general arrangement, because they describe a single part or assembly. And they are not records, because they are produced before the work. They are, in the most literal sense, the instructions for making a thing: this beam, with these holes, these welds, this finish, to these tolerances, marked with this number, delivered on this date. Between the design and the product, they are the translation.

For most of the history of construction, shop drawings were produced by people looking at design drawings and redrawing what they needed. Each piece of information was re-keyed: dimensions, levels, positions, specifications. And each re-keying was an opportunity for error. When BIM entered the picture, the obvious promise was that the shop drawing could be derived from a model, a detailed, coordinated model of the part and its surroundings, rather than redrawn from scratch. In many trades, that promise has been kept so thoroughly that the fabrication model is now the primary document and the drawing is simply one of its outputs.

This guide explains how to create shop drawings and fabrication models from BIM. It covers what each is, how they relate to the design model, the workflow from design intent to approved shop drawings to fabrication release, the content of a fabrication model, how shop drawings are generated and checked, review and approval, responsibility and design intent, coordination and sign-off, data formats for fabrication, quality control, the differences between trades and the mistakes to avoid. It builds on the trade guides (BIM for Steel Structures: Modeling and Detailing, Reinforcement Modeling in BIM: Rebar and Detailing Workflows, BIM for Timber Structures: Modeling and Information Requirements and How to Develop MEP BIM Models for Construction). Design responsibility, approval processes and compliance with specifications and codes remain as defined in the contract. A shop drawing is not an invitation to redesign; changes to design intent require the design team’s approval.


The Short Answer

A fabrication model is a detailed, coordinated model of the parts to be made; shop drawings are views and documents derived from it that describe how to make, deliver and install each part, submitted for review and approval before release to fabrication.

From design model to shop drawings and fabrication

StepWhat happens
Design intentDesign model and specification define what is required
Detailing modelThe fabricator or contractor models parts, connections, tolerances and marks
Shop drawingsViews, parts lists and data are derived from the model
ReviewDesigner and contractor check against design intent and specification
ReleaseApproved, frozen information goes to fabrication under revision control
FieldParts are installed, verified and recorded

In one sentence:

The shop drawing is the instruction for making a part; the fabrication model is the source of that instruction; review and approval keep the part true to the design.


Definitions

TermMeaning
Design modelThe model of design intent, produced by the design team
Coordination modelThe federated model used to resolve conflicts between trades
Detailing model / fabrication modelThe detailed model of parts and assemblies as they will be made, with connections, fixings, tolerances and marks
Shop drawingsDrawings and documents that describe fabrication and installation of parts or assemblies
Fabrication dataMachine-readable data for production equipment: cutting, drilling, bending, welding, assembly
SubmittalItems submitted for review and approval: shop drawings, product data, samples, calculations
Installation drawingsDocuments showing where and how assemblies are installed
As-built recordRecord of what was built. See BIM for As-Built Documentation and Project Handover

Terms vary by region and contract; agree meanings in the EIR, BEP and contract documents.


The Relationship With the Design Model

QuestionTypical position
Is the design model the fabrication model?Rarely. Design models are not detailed to fabrication level and are authored by different parties for different purposes
Does the fabricator start from the design model?Often yes: for geometry, grids, levels and design intent; then builds a detailing model
Can the fabricator rely on the design model?Only as the contract states; typically design intent, not fabrication dimensions. Verify with site survey where critical
Who owns design intent?The design team; changes require their approval
What is delegated?As the contract states: for example connection design in steel, sprinkler design, panel design
Which model governs if they differ?Defined in the contract and BEP; conflicts are resolved through RFIs and approvals

Write the answers in the BEP and responsibility matrix. See How to Create a BIM Responsibility Matrix and BIM Contracts and Legal Considerations.


The Workflow

Step 1: Define Requirements and Responsibilities

ItemContent
ScopeWhich systems and parts require shop drawings and fabrication models
Design intent levelWhat the design team has fixed; what is left to the fabricator
StandardsDrawing standards, marking systems, tolerances, formats
Submittal procedureWhat to submit, when, to whom, review times, statuses
Coordination requirementsSign-off before release
Format requirementsModel formats, drawing formats, fabrication data formats
Freeze and release rulesWhat must be approved before production
Change controlHow changes after approval are managed

Step 2: Receive and Review the Design Information

TaskPurpose
Review the design model and documentsUnderstand design intent and constraints
Check coordinates, levels and gridsAlign the detailing model
Identify gaps and questionsRaise requests for information early
Check the siteSurvey or scan existing conditions where fabrication depends on them. See Scan-to-BIM: Converting Point Clouds into Intelligent Models
Agree interface informationWith adjacent trades

Step 3: Build the Detailing Model

ContentNotes
Parts and assembliesEvery item to be made, with real geometry
Connections and fixingsWelds, bolts, brackets, plates, anchors
Holes, cuts, notches, penetrationsAs required, coordinated with other trades
Tolerances and allowancesFabrication and installation tolerances; adjustment provisions
Marks and numberingUnique marks for parts and assemblies, consistent across model, drawings and data
Materials and finishesGrades, coatings, treatments
DataWeight, dimensions, quantities, product references, test requirements
InterfacesPositions and details where the part meets structure, services or finishes
Transport and installation informationSize, weight, lifting points, sequence

See the material and system guides for the detail: BIM for Steel Structures: Modeling and Detailing, Reinforcement Modeling in BIM: Rebar and Detailing Workflows, BIM for Timber Structures: Modeling and Information Requirements, BIM for Concrete Structures: Modeling and Coordination and How to Develop MEP BIM Models for Construction.

Step 4: Coordinate

TaskPurpose
Federate the detailing model with othersCheck fit
Run clash and clearance testsInclude supports, insulation, access. See BIM Clash Detection: The Complete Guide
Resolve and verifyUpdate models; confirm
Obtain sign-offCoordination complete for the zone
Freeze interfacesPositions of penetrations and supports agreed

Do not release to fabrication before coordination is signed off for the relevant zone. See BIM Coordination: The Complete Guide.

Step 5: Generate Shop Drawings and Data

OutputContent
Assembly drawingsHow an assembly is made: parts, positions, dimensions, welds, fixings, finishes
Part drawingsIndividual part details where needed
General arrangement and erection or installation drawingsWhere assemblies go, sequence, connections
Parts lists and bills of materialsQuantities of each part, material and fixing
Cutting lists and bending schedulesFor stock and processing
Hole and fixing schedulesPositions and sizes
Fabrication data filesMachine-readable data for production equipment
Weight and logistics listsFor transport and lifting
Inspection and test plansRequired checks

Derive drawings from the model. A drawing that is edited by hand and no longer matches the model is a risk. If 2D annotation is added, keep it tied to model views and check it. See Architectural BIM Documentation: Plans, Sections, and Schedules for documentation principles.

Step 6: Submit, Review and Approve

StepPractice
Submit with a transmittalIdentify the submittal, revision, scope, status and what approval is requested
Review by the design team and contractorCheck against design intent, specification, coordination and constructability
Comments and markupsRecorded, tracked and answered. See BIM Issue Tracking and Resolution Using BCF
Status outcomeApproved, approved with comments, revise and resubmit, rejected (names vary by contract)
ResubmitUntil approved
RecordKeep the approval record linked to the submittal revision

Step 7: Release to Fabrication

CheckPurpose
Approval obtainedStatus as required by the contract
Coordination sign-offZone is coordinated
Survey confirmationExisting conditions verified where needed
Model validatedChecks passed. See MEP BIM Model Quality Control and Validation and Structural BIM Model Validation and Quality Assurance
Fabrication data testedA sample exchange with the factory
Revision controlThe released revision identified; superseded versions withdrawn
Release recordDate, revision, authorizer

Step 8: Fabricate, Deliver, Install and Record

TaskPractice
First article inspectionCheck the first part against the model and drawings
Fabrication quality controlInspect parts against model-derived documents; record
Delivery and identificationMarks, labels and tracking; check against lists
InstallationUse installation drawings; verify positions and tolerances
ChangesField modifications recorded and approved; model updated
As-built updateRecord deviations. See BIM for As-Built Documentation and Project Handover

What Makes a Good Fabrication Model

QualityDescription
CompleteEvery part to be made is modeled or specified
AccurateDimensions, positions and tolerances match what will be made and installed
CoordinatedFits with adjacent work
ConsistentMarks, data and views agree
ManufacturableRespects the fabricator’s processes and constraints
TraceableRevision and approval history
StructuredNaming, classification and data per standards
Light enoughUsable; detailed parts do not burden the federation

The Detail Question

Fabrication level is high, but it is still a choice. Model what production, coordination and installation need; avoid modeling what nobody will use. Use agreed levels of information. See ISO 7817-1: Level of Information Need Explained.


Review and Approval: What Reviewers Check

ReviewerFocus
Design teamConformance with design intent, performance, specification, interfaces, aesthetics where relevant
Structural engineerConnections, loads, member sizes, supports (within the responsibility defined by the contract)
Services engineerSystems, routes, sizes, capacities, supports
ArchitectAppearance, finishes, tolerances, interfaces
Fire and acoustic consultantsRatings, penetrations, seals
ContractorConstructability, sequence, coordination, logistics
Client or authorityWhere required

Reviewer’s Checklist (Illustrative)

  1. Is the submittal complete (drawings, data, calculations, product information)?
  2. Does it conform to the design intent and the specification?
  3. Are interfaces correct and coordinated?
  4. Are tolerances and finishes as specified?
  5. Are materials and products as approved?
  6. Are marks, revisions and statuses clear?
  7. Have deviations from design been identified and justified?
  8. Is it constructible and safe to install (with the contractor’s input)?

An Important Point About Approval

Approval by the design team typically means that the submittal appears to conform to the design intent. It usually does not relieve the fabricator or contractor of their responsibility for accuracy, fit or compliance with the contract. The wording of the contract governs; seek advice. See BIM Contracts and Legal Considerations.


Fabrication Data and Formats

DataNotes
Machine-readable fabrication filesUsed by cutting, drilling, bending, welding and assembly equipment; formats depend on the trade and equipment
Neutral exchange formatsUsed for design-to-detail exchange and model coordination; examples relevant to specific trades are discussed in the trade guides
IFC modelsFor coordination and handover; test geometry and property exchange
Native modelsHighest fidelity within one platform
Parts lists and schedulesTabular data for procurement and production
Labels and tagsBarcode or QR codes for tracking
DrawingsPDF and CAD for review and shop use

Agree formats and information content with the fabricator, and test a sample. Different trades use different formats: for example steel detailing and fabrication data, reinforcement bar bending data, timber panel machining data and pipework fabrication data. See How to Export and Import IFC Models Correctly.


Differences by Trade

TradeCharacteristics
Structural steelDetailing models with connections; machine files; assembly marking; erection drawings
ReinforcementBar schedules, shape codes, cages; machine bending data; placing drawings
Precast concreteUnit drawings with inserts and lifting; factory data; erection sequence
Timber and mass timberPanel and member machining data; connection details; moisture and logistics
Mechanical and plumbing pipeworkSpool drawings; hangers; prefabricated racks
DuctworkDuct sections and fittings; flanges; hangers; machine data
ElectricalContainment layouts; prefabricated assemblies; panel details
Façade and curtain wallUnit drawings, framing, glazing, anchors, tolerances, performance testing
Joinery and interior fit-outDetailed workshop drawings and cutting data
Specialist systemsLifts, kitchens, laboratory equipment: manufacturer drawings

Each has its own conventions. See the trade guides.


Quality Control and Records

StageControl
ModelValidation checks; coordination sign-off
DrawingsChecked against the model; marks, dimensions and notes verified
SubmittalCompleteness and correctness before submission
ApprovalRecords of review and status
ReleaseRevision control; only approved revisions in production
First articleInspection of the first part
ProductionIn-process and final inspection
DeliveryMarks and condition
InstallationPosition and tolerance checks
Close-outRecords and as-built updates

Maintain a submittal register with status and revisions for each item, and a drawing and model register linked to releases. See Common Data Environment (CDE): The Complete Guide.


Common Problems and Remedies

ProblemCauseRemedy
Fabricated parts do not fitSurvey errors; coordination gaps; tolerance issuesSurvey control; coordination sign-off; tolerance strategy; first article
Design intent changed in detailingPoor reviewDesign review; clear intent; approval procedure
Shop drawings differ from the modelManual editsDerive from the model; check
Wrong revision fabricatedPoor revision controlCDE; release records; withdrawal of superseded revisions
Review delaysLate or incomplete submittals; unclear procedureSubmittal schedule; completeness checks; agreed review times
Fabrication data unusableFormat untestedSample exchange
Disputes over responsibilityUnclear contract and BEPResponsibility matrix; approval wording
Late changesNo freezeFreeze and change control
Over-detailed modelsNo purposeLevel of information; focus

Common Mistakes

  1. Treating the design model as the fabrication model.
  2. Detailing without design intent clarity.
  3. Releasing before coordination sign-off.
  4. Manual edits to drawings outside the model.
  5. Weak revision control.
  6. No survey of existing conditions.
  7. No first-article check.
  8. Untested fabrication formats.
  9. Incomplete submittals.
  10. Assuming approval relieves responsibility.
  11. No submittal and drawing registers.
  12. No record of field changes.

See also Common BIM Mistakes Beginners Should Avoid.


A Short Checklist

  1. Are scope, design intent, responsibilities and procedures defined?
  2. Is the detailing model complete, accurate, coordinated and consistent, with marks and data?
  3. Are shop drawings and data derived from the model and checked?
  4. Is coordination signed off and existing conditions verified before release?
  5. Are submittals complete, with a register, transmittals and review times?
  6. Do reviewers check design intent, interfaces, tolerances, products and constructability?
  7. Are fabrication formats tested with a sample?
  8. Is revision control in place, with release records and withdrawal of old versions?
  9. Is there a first-article check and quality control through delivery and installation?
  10. Are changes and as-built deviations recorded and fed back?

Frequently Asked Questions

What is a shop drawing?

A drawing or document produced by a contractor, fabricator or specialist that describes how a part or assembly will be made, delivered and installed.

What is a fabrication model?

A detailed model of parts and assemblies as they will be made, including connections, fixings, tolerances and marks, used to produce shop drawings and fabrication data.

Can I produce shop drawings directly from the design model?

Usually not. The design model is not detailed to fabrication level. Fabricators build a detailing model, using the design model for intent, grids and levels.

Who approves shop drawings?

The parties named in the contract, typically the design team and the contractor. Approval usually confirms conformity with design intent and does not relieve the fabricator of responsibility for accuracy.

What file formats are used for fabrication?

Trade-specific machine data, neutral exchange formats and IFC for coordination, plus PDF and CAD drawings. Agree and test with the fabricator.

When can fabrication start?

After approval, coordination sign-off, survey confirmation where needed, validation of the model and tested fabrication data, with a controlled release.

Why produce a first article?

To check design, data formats, tolerances and interfaces on one part before full production.

How do I control revisions?

With a CDE, a register of submittals and releases, clear statuses and withdrawal of superseded revisions.


Final Thoughts

I once reviewed a set of shop drawings for a steel frame that were, by any reasonable standard, beautiful. Every connection was detailed, every part marked, every weld symbol correct. The reviewing engineer, a quiet man with forty years of experience, spent twenty minutes on one sheet and then asked a question that stopped the room: “Where is the survey?” The drawings had been produced from the design model, and the design model had the slab edge where the design said it would be. The slab, as built, was forty millimeters further out. Nobody had measured it. The steel would have been fabricated to a position that did not exist.

That is the lesson of shop drawings and fabrication models: beauty is not truth. A detailed model is only as true as the information beneath it, and approval only confirms what was submitted. Define intent and responsibility, model what production needs, coordinate and sign off, verify the site, derive the drawings, review against intent, test the data, control the revision and check the first article. A part made this way arrives on site as a promise kept.

Where to go next: for the trade detail, read BIM for Steel Structures: Modeling and Detailing, Reinforcement Modeling in BIM: Rebar and Detailing Workflows and How to Develop MEP BIM Models for Construction. For the off-site context, continue with BIM for Prefabrication and Modular Construction, and for subcontractor requirements, BIM for Subcontractors: Requirements, Workflows, and Deliverables.

Rachid Khouri

Rachid Khouri

Rachid Khouri is a CAD, BIM and GIS professional, Autodesk Authorized Developer, trainer and technical author with more than 30 years of experience, working with AutoCAD since 1992. He founded TheBIMAuthority.com to share practical guidance on BIM workflows, information management, industry standards, digital construction technologies and best practices for AEC professionals.